86m Layher scaffold completed at Giotto’s Bell Tower

An 86-metre Layher scaffold erected in just over four months will support the first full restoration of Florence’s Giotto’s Bell Tower.

ADVERTISEMENT

An 86-metre scaffold erected in just over four months will support a five-year restoration of the Florence landmark while keeping it open to visitors.

Scaffolding has been completed around Giotto’s Bell Tower in Florence, clearing the way for the historic landmark’s first full internal and external restoration.

The 86-metre structure uses Layher’s modular steel system and was designed by Opera di Santa Maria del Fiore in collaboration with Tecno System Appalti and Layher S.p.A.

The Opera confirmed completion on 1 October, following just over four months of assembly. The restoration is expected to take around five years and cost more than €7 million, funded entirely by the institution.

The scaffold has been configured around the tower’s changing geometry and projecting architectural features, with working platforms arranged to meet the restoration team’s needs.

Full-height scaffold at Giotto’s Bell Tower with protective mesh around the upper working section
A full-height view of the scaffold at Giotto’s Bell Tower, with the upper working section enclosed in protective mesh. Courtesy: Opera di Santa del Fiore/foto Fabio Muzzi

Samuele Caciagli, head of the Opera’s technical office, said the design sought to avoid altering the tower’s structural equilibrium while keeping its architecture visible. Components and equipment have also been selected for recovery and reuse on future projects.

Work will progress from the top down, revealing restored sections in stages. Caciagli told Italian news agency askanews that the scaffold had been designed to leave at least 60% of the marble surfaces visible.

The first stage will involve diagnostic investigations and preliminary tests to confirm the restoration approach before treatment of the stonework begins.

Visitors will continue to be able to climb the tower’s 414 steps and reach its rooftop terrace throughout the works, although views may be partially restricted.

Construction of the bell tower began under Giotto in 1334 and was completed by Francesco Talenti in 1359. Its exterior is clad in white, red and green marble.

Assembly of the scaffold also had to accommodate a pair of nesting peregrine falcons.

A photographic survey of the tower’s 149 putlog holes identified a female incubating eggs on the west side. Working with bird conservation organisation Lipu and other specialists, the Opera rescheduled assembly to avoid disturbing the nest.

Three chicks subsequently hatched and fledged successfully.

Featured image: The completed restoration scaffold around Giotto’s Bell Tower, pictured beside Florence Cathedral. Courtesy: Opera di Santa del Fiore/foto Fabio Muzzi

Daniel Norton
Daniel NortonFounder & Editorhttps://www.scaffmag.com
Daniel Norton is the founder and editor of Scaffmag and Editor-in-Chief of Scaffold & Access Magazine. A former scaffolder, he founded Scaffmag in 2008 and now leads its news and editorial coverage of the global scaffolding and access industry, including safety, regulation, business, innovation and major industry events.

Most popular ↑

SAIA names teams for 2027 Scaffold Builders Competition

Manchester-based AK Scaffolding is on the list for Las Vegas, alongside 4 first-time entrants from the US, Lithuania, Switzerland and Canada.

Mobile scaffold falls three decks on offshore support vessel

Marine Safety Forum reports a three-tier scaffold collapse during repositioning, with seized wheels and no exclusion zone on the deck below.

Scaffold firm fined £16,000 after trainee’s fatal fall

HSE found that safe zones had not been established when Michael Swales fell 5 metres from a partially erected scaffold near Ripon.

Four injured in Taiwan market scaffold collapse

Taipei has halted work at the old Beitou market demolition site after a scaffold collapse injured four people. Investigations are continuing.

Vistry begins job cuts ahead of January regional shake-up

The housebuilder is reducing its operating regions from 25 to 12 and matching build rates to demand as private housing conditions remain difficult.

Latest news

Safety and Access wins Hackney inspection contract

Safety and Access will carry out statutory scaffold inspections across Hackney Council's housing stock under a £74,100 award.
- Advertisement -
More from

Doka details climbing systems for Burj Binghatti tower

Doka’s project update sets out the climbing and edge-protection systems being used on Burj Binghatti, with a target of 1 floor a week.

Worker seriously injured in Swiss scaffold dismantling fall

A 37-year-old worker was seriously injured while dismantling scaffolding in Oberstammheim, Switzerland. Police are investigating the cause of the fall.

PHD Access joins £190m Dungeness A decommissioning team

Aureos has named PHD Access as its scaffolding partner for the removal of eight 800-tonne boilers at Dungeness A. The overall programme is worth up to £190m.

Shield tackles hilltop access challenge in 19-day scaffold build

Shield erected access around the 38-metre Lansdowne Monument in 19 days despite a steep, rutted route that kept vans and lorries away from the hilltop.
Latest articles