Harsco completes one of Europe’s largest scaffolding projects

ADVERTISEMENT

Harsco Infrastructure has announced the successful completion of what was, at the time it began, one of the largest scaffolding projects of its type in Europe.

The 3-year, £35M project has enabled a major programme of cleaning and refurbishment work to be completed on the roof at London’s Victoria Station, while allowing the station to retain its normal schedule of operations.

As a Grade Two listed building. the roof itself is widely recognised as an engineering masterpiece which dates back to 1865 and had undergone a series of ad-hoc repair works over the years. Along with the fact that the project was far more complex than originally envisaged, this presented Harsco with a series of unique challenges.

“The listed nature of the building and the fact that the station had to remain operational meant that we had to work in very close collaboration with both May Gurney, who were the main contractor, and also with Network Rail,” comments Harsco’s Project Engineering Manager, Brendan Fox.

“We erected three temporary roof structures, one in each roof barrel and concourse. These were multi-functional and provided a weatherproof, dustproof, acoustic structure which also gave support for the access scaffold above, so that blasting, painting and glazing works could be carried out during normal working hours. In the Eastern barrel a 31.4m mansard roof structure spanning four platforms was built during the day, above a construction gantry. At night this was then pushed out over the platforms in 24-metre sections. These ran on steel tracks which were supported on steel grillages and towers over the platforms.

In the Western barrel a part-mobile and part-static mono-pitch temporary roof structure was built. The static section was supported at one end on specially designed gallows brackets bolted to the West wall and this allowed the shops, bars and restaurants below to carry on business as usual. The spans were maximised wherever appropriate so that as much platform space as possible was retained for the full operational use of the station. This helped Harsco meet the challenge of maximising pedestrian footfall and passenger access to maintain the rain service.

“There were many challenges that arose from working in a live environment, “ adds Brendan Fox. “These included having very limited storage facilities and only being able to complete certain works at night. However with careful and detailed planning, plus the use of innovative solutions to the various challenges that arose, we succeeded in completing the project to everyone’s satisfaction and with no impact on train services.”

SM Newsdesk
SM Newsdeskhttps://www.scaffmag.com
The staff at ScaffMag.com the leading scaffolding site for a digital generation.

Most popular ↑

Housebuilder fined £300k after scaffolding labourer suffers serious fall

A West Yorkshire housebuilder has been fined £300,000 after a scaffolding labourer suffered serious spinal injuries in a fall through an unprotected stairwell opening.

Australian scaffolding group enters administration with over 650 jobs at risk

A group of companies linked to one of Australia’s...

New scaffolding festival announced for summer 2027

ScaffFest 2027 will bring international scaffolding championships, a trade exhibition and family entertainment to NAEC Stoneleigh in Warwickshire next July, Scaffmag can exclusively reveal.

CISRS says CSCS exit can be reversed if rule changes agreed

CISRS has said it could withdraw its notice to leave CSCS if agreement can be reached over the Construction Leadership Council rule at the centre of the dispute.

Scottish scaffolding apprentices to compete at ScaffChamp 2026

A team of young scaffolders from Scotland and Northern...

Latest news

HAKI halves workforce as Combisafe integration gathers pace

HAKI Safety has halved the workforce across Combisafe and its UK fall protection operation as it moves to integrate the recently acquired business.
- Advertisement -
More from

HAKI halves workforce as Combisafe integration gathers pace

HAKI Safety has halved the workforce across Combisafe and its UK fall protection operation as it moves to integrate the recently acquired business.

Singapore to mandate fire-retardant scaffold netting from 2027

Singapore will require scaffold netting used outside buildings to meet fire-retardant specifications on projects awarded from 1 March 2027.

National Scaffolding Week returns in October

National Scaffolding Week will return from 5 to 9 October, with businesses across the industry being encouraged to showcase their people, projects and career opportunities.

BGB wins Baltica 2 offshore scaffolding framework

BGB Group has secured a framework agreement to provide offshore scaffolding and construction support across four offshore substations on Poland's 1.5GW Baltica 2 wind farm.
Latest articles