Scaffolding contractors should check where boilers and other fuel-burning appliances vent before enclosing a scaffold, the National Access and Scaffolding Confederation (NASC) has said in an update to its confined space guidance.
The revised guidance, announced on 26 November, warns that sheeting can restrict ventilation or leave a flue discharging into an enclosed scaffold. That can allow carbon monoxide and other combustion products to build up, even if the scaffolders never enter the space affected.
In Hoxton, east London, gas engineers shut down boilers at a block of flats after scaffold sheeting obstructed flues and raised concerns about carbon monoxide.
NASC says contractors should identify flues serving gas, oil, biomass and solid fuel appliances and agree suitable controls with the client before the enclosure is completed. The advice applies to temporary roofs as well as sheeted scaffolds.
The update also asks firms to check what a confined-space job will need before they quote. Permits, air monitoring, standby staff and specialist rescue provision can all affect the price and how long the job takes. The guidance covers commercial, industrial and offshore work, from planning and erection through to alteration and dismantling.
The Health and Safety Executive says to avoid entering a confined space wherever reasonably practicable. If entry is unavoidable, a safe system of work and adequate emergency arrangements are required. NASC says rescue staff and equipment should be ready before work starts, and firms that lack the relevant experience should seek specialist advice at the planning stage.
The SG21:26 download is free for NASC members and costs £10.10 for non-members.