Harsco Helps To Hold Back The Water At A Jersey Dam

ADVERTISEMENT

 

A project to refurbish a dam on the island of Jersey has highlighted the bespoke nature of the access equipment solutions which Harsco Infrastructure provides for its customers.

Harsco designed and installed a unique combination of suspended access platforms and a load bearing support gantry system (constructed from MkII shoring soldiers and scaffolding materials) to provide access to the entire inside face of the dam so that vital maintenance work could be completed.

First constructed in 1962, the Val de la Mare dam holds back 900 million litres of water, making it the second largest reservoir on the island. The concrete on the dam is suffering from an alkali aggregate reaction and this created the need for the inside face to be covered with a heavy-duty waterproof membrane to re-seal the dam. This will prolong the life of the dam for many years, but required the reservoir to be drained so that the inside face could be accessed.

“This was a very unusual and difficult project which is why a totally bespoke solution was required,” comments Harsco Project Manager Jon Herbert. “It is the first time the reservoir has ever been partially drained and the project had a very tight schedule as the reservoir needed to be refilled as soon as possible.

“The fact that the trades were working at height, and also above water, made this a very complex project. Access to the façade had to be from the walkway on top of the dam wall which was very narrow. This had to remain clear throughout the project to allow the waterproof membrane to be positioned and unrolled down the inner façade. This was achieved by designing a walk-though, ‘tunnel-like’ support structure from scaffolding and shoring MkII Soldier materials.”

Five suspended access cradles were suspended from the load bearing framework and four were fitted with motorised bogies which allowed them to traverse along the façade as well as up and down. This was made possible by a steel support track supported on the underside of the load-bearing framework structure. The fifth suspended access platform was a specially designed and fabricated horse-shoe shaped machine that provided access to the pump tower. This platform was specially designed with six separate winching units which were also supported by the load bearing framework structure. This arrangement of access platforms and egress to the top of the dam’s façade allowed both the team of membrane installers and concrete repair specialists complete access to the façade.

“It was a terrific piece of teamwork to get this project up and running,” comments Project Manager Nathan Clothier, of civil engineering contractor Jayen Ltd which was responsible for the refurbishment work. “We needed a real bespoke access solution to solve a difficult set of requirements. Harsco’s response was really well thought through and they were even able to build a test section of the support gantry for the project team to evaluate prior to work commencing. The schedule on this job was particularly tight so the access system had to be really effective and I’m happy to say that the suspended access platforms worked very well.”

Via: Press Release 

 

Most popular ↑

£4.5m scaffolding framework opens for contractors in North East and Yorkshire

Beyond Housing has opened bidding for a £4.5m scaffolding framework covering planned and reactive works across Redcar and Cleveland and parts of North Yorkshire.

£260k Newcastle Cathedral scaffolding contract opens for bids

Newcastle City Council has opened a £260,000 scaffolding tender to provide specialist access for conservation repairs to Newcastle Cathedral’s historic 15th-century Lantern Tower.

Australia steps up push for scaffolding to gain skilled-trade status

Scaffolding Association Australia has taken its campaign for formal trade recognition and a structured apprenticeship pathway to federal decision-makers in Canberra.

Robot inspection removes need for scaffold access on 70m Cemex kiln

A wall-climbing robot has completed ultrasonic testing across a 70m rotary kiln at Cemex’s Rugby cement plant, removing the need for personnel to work at height and avoiding a conventional scaffold or rope-access operation.

NASC calls for HSE funding boost and national scaffolding training network

The NASC has called for increased HSE funding, a nationwide network of scaffolding training providers and stronger protections for contractors as it launches its updated 2026 manifesto.

Latest news

£500k scaffolding package opens on major North Somerset campus

A £500,000 scaffolding package is among a series of opportunities being brought to market for Epic Systems’ new European headquarters near Bristol, with local contractors being urged to register their interest.
- Advertisement -
More from

Major fire hits scaffolding yard in Mitcham

Around 125 firefighters were deployed to a major fire in Mitcham that affected a scaffolding yard, workshop and nearby property, with investigators now examining the cause of the blaze.

£260k Newcastle Cathedral scaffolding contract opens for bids

Newcastle City Council has opened a £260,000 scaffolding tender to provide specialist access for conservation repairs to Newcastle Cathedral’s historic 15th-century Lantern Tower.

NASC calls for HSE funding boost and national scaffolding training network

The NASC has called for increased HSE funding, a nationwide network of scaffolding training providers and stronger protections for contractors as it launches its updated 2026 manifesto.

£4.5m scaffolding framework opens for contractors in North East and Yorkshire

Beyond Housing has opened bidding for a £4.5m scaffolding framework covering planned and reactive works across Redcar and Cleveland and parts of North Yorkshire.
Latest articles