Harsco Helps To Hold Back The Water At A Jersey Dam

ADVERTISEMENT

 

A project to refurbish a dam on the island of Jersey has highlighted the bespoke nature of the access equipment solutions which Harsco Infrastructure provides for its customers.

Harsco designed and installed a unique combination of suspended access platforms and a load bearing support gantry system (constructed from MkII shoring soldiers and scaffolding materials) to provide access to the entire inside face of the dam so that vital maintenance work could be completed.

First constructed in 1962, the Val de la Mare dam holds back 900 million litres of water, making it the second largest reservoir on the island. The concrete on the dam is suffering from an alkali aggregate reaction and this created the need for the inside face to be covered with a heavy-duty waterproof membrane to re-seal the dam. This will prolong the life of the dam for many years, but required the reservoir to be drained so that the inside face could be accessed.

“This was a very unusual and difficult project which is why a totally bespoke solution was required,” comments Harsco Project Manager Jon Herbert. “It is the first time the reservoir has ever been partially drained and the project had a very tight schedule as the reservoir needed to be refilled as soon as possible.

“The fact that the trades were working at height, and also above water, made this a very complex project. Access to the façade had to be from the walkway on top of the dam wall which was very narrow. This had to remain clear throughout the project to allow the waterproof membrane to be positioned and unrolled down the inner façade. This was achieved by designing a walk-though, ‘tunnel-like’ support structure from scaffolding and shoring MkII Soldier materials.”

Five suspended access cradles were suspended from the load bearing framework and four were fitted with motorised bogies which allowed them to traverse along the façade as well as up and down. This was made possible by a steel support track supported on the underside of the load-bearing framework structure. The fifth suspended access platform was a specially designed and fabricated horse-shoe shaped machine that provided access to the pump tower. This platform was specially designed with six separate winching units which were also supported by the load bearing framework structure. This arrangement of access platforms and egress to the top of the dam’s façade allowed both the team of membrane installers and concrete repair specialists complete access to the façade.

“It was a terrific piece of teamwork to get this project up and running,” comments Project Manager Nathan Clothier, of civil engineering contractor Jayen Ltd which was responsible for the refurbishment work. “We needed a real bespoke access solution to solve a difficult set of requirements. Harsco’s response was really well thought through and they were even able to build a test section of the support gantry for the project team to evaluate prior to work commencing. The schedule on this job was particularly tight so the access system had to be really effective and I’m happy to say that the suspended access platforms worked very well.”

Via: Press Release 

 

Most popular ↑

Fatal New Malden fall followed missed scaffold inspections

Lima Construction Limited has been fined £50,000 after a...

360 Degrees Consultancy: From Start-Up to Top 5 UK Scaffolding Consultancy

When Karl launched 360 Degrees Consultancy in 2020, he...

NASC AGM confirms new president and 10-region structure

Sarah Klieve has taken over as NASC president as...

The apprentice team that took on ScaffChamp

Ross Brown and Robbie Andrews didn’t take an all-apprentice...

AT-PAC establishes permanent Middle East base with UAE launch

AT-PAC has officially launched a dedicated business in the...

Latest news

ADVERTISEMENT
More from
Latest articles

ScaffChamp confirmed to return to Vilnius in 2027

ScaffChamp will return to Vilnius in 2027 after Layher confirmed the global scaffolding competition...

Government clarifies Building Safety Act position on temporary scaffolds

NASC says scaffold contractors should not be asked to meet Building Safety Act dutyholder...

AT-PAC establishes permanent Middle East base with UAE launch

AT-PAC has officially launched a dedicated business in the United Arab Emirates, strengthening its...

Double Seawork award for ScaffFloat’s hoisted pontoon system

ScaffFloat has won two awards at Seawork 2026 in Southampton for a hoisted access...

360 Degrees Consultancy: From Start-Up to Top 5 UK Scaffolding Consultancy

When Karl launched 360 Degrees Consultancy in 2020, he was drawing on more than...

The apprentice team that took on ScaffChamp

Ross Brown and Robbie Andrews didn’t take an all-apprentice team to ScaffChamp to chase...

NASC AGM confirms new president and 10-region structure

Sarah Klieve has taken over as NASC president as the trade body introduces a...

Fatal New Malden fall followed missed scaffold inspections

Lima Construction Limited has been fined £50,000 after a worker fell to his death...