A project to refurbish a dam on the island of Jersey has highlighted the bespoke nature of the access equipment solutions which Harsco Infrastructure provides for its customers.

Harsco designed and installed a unique combination of suspended access platforms and a load bearing support gantry system (constructed from MkII shoring soldiers and scaffolding materials) to provide access to the entire inside face of the dam so that vital maintenance work could be completed.

First constructed in 1962, the Val de la Mare dam holds back 900 million litres of water, making it the second largest reservoir on the island. The concrete on the dam is suffering from an alkali aggregate reaction and this created the need for the inside face to be covered with a heavy-duty waterproof membrane to re-seal the dam. This will prolong the life of the dam for many years, but required the reservoir to be drained so that the inside face could be accessed.

“This was a very unusual and difficult project which is why a totally bespoke solution was required,” comments Harsco Project Manager Jon Herbert. “It is the first time the reservoir has ever been partially drained and the project had a very tight schedule as the reservoir needed to be refilled as soon as possible.

“The fact that the trades were working at height, and also above water, made this a very complex project. Access to the façade had to be from the walkway on top of the dam wall which was very narrow. This had to remain clear throughout the project to allow the waterproof membrane to be positioned and unrolled down the inner façade. This was achieved by designing a walk-though, ‘tunnel-like’ support structure from scaffolding and shoring MkII Soldier materials.”

Five suspended access cradles were suspended from the load bearing framework and four were fitted with motorised bogies which allowed them to traverse along the façade as well as up and down. This was made possible by a steel support track supported on the underside of the load-bearing framework structure. The fifth suspended access platform was a specially designed and fabricated horse-shoe shaped machine that provided access to the pump tower. This platform was specially designed with six separate winching units which were also supported by the load bearing framework structure. This arrangement of access platforms and egress to the top of the dam’s façade allowed both the team of membrane installers and concrete repair specialists complete access to the façade.

“It was a terrific piece of teamwork to get this project up and running,” comments Project Manager Nathan Clothier, of civil engineering contractor Jayen Ltd which was responsible for the refurbishment work. “We needed a real bespoke access solution to solve a difficult set of requirements. Harsco’s response was really well thought through and they were even able to build a test section of the support gantry for the project team to evaluate prior to work commencing. The schedule on this job was particularly tight so the access system had to be really effective and I’m happy to say that the suspended access platforms worked very well.”

Via: Press Release 

 

ADVERTISEMENT

Popular Categories

Latest news

Connolly Scaffolding strengthens partnership with TRAD UK in £3.5m investment

Connolly Scaffolding Ltd has agreed a further £3.5 million investment in TRAD UK’s Plettac Metrix system, reinforcing a partnership that has shaped both businesses...

Benetics introduces AI voice tool to cut site paperwork

A German construction technology firm has launched an AI-powered voice assistant designed to help site teams cut paperwork and speed up reporting. Benetics, based in...

Scaffolders at Sullom Voe Terminal walk out over pay dispute

Around 60 scaffolders, painters, insulators, and supervisors at the Sullom Voe Terminal in the Shetland Islands have staged a 24-hour walkout in an escalating...

Hong Kong contractors ‘hid unsafe scaffolding netting’ as tower fire toll rises to 151

Investigators in Hong Kong say contractors used unsafe scaffolding netting at the housing estate destroyed by last week’s deadly fire, and then tried to...

Costs climb again on Manchester Town Hall project as delays worsen

The cost of restoring Manchester Town Hall has risen by a further £95m, with completion now pushed back to spring 2027. The Grade I-listed...

CSCS Alliance appoints new Chair

The CSCS Alliance has confirmed the appointment of Marion Marsland as its new Chair, marking a significant leadership change for the body representing 37...

ScaffEx26 set for growth as NASC prepares expanded programme

NASC says ScaffEx26 is on track to grow further, with early exhibitor demand already exceeding last year’s levels. The trade body confirmed to Scaffmag that...

New Gale Force Bolt introduced to honour industry figure Alan Gale

Tilbury Scaffolding has introduced a new fixing in honour of Alan Gale, a widely respected figure in the scaffolding supply sector whose career spanned...

Scaffolding under scrutiny after Hong Kong tower blaze kills 128

This article has been updated as authorities confirm a revised death toll and launch a criminal and corruption inquiry. At least 128 people have died,...

Budget 2025: NASC warns of rising costs as new tax increases hit construction firms and housing delivery stalls

The Autumn Budget has drawn strong criticism from scaffolding, construction and housebuilding leaders, who warn that a combination of higher wage costs, frozen tax...

Latest news

ADVERTISEMENT

The magazine

Issue 27 | Past issues >>

Popular

Connolly Scaffolding strengthens partnership with TRAD UK in £3.5m investment

Connolly Scaffolding Ltd has agreed a further £3.5 million...

Scaffolders at Sullom Voe Terminal walk out over pay dispute

Around 60 scaffolders, painters, insulators, and supervisors at the...

Hong Kong contractors ‘hid unsafe scaffolding netting’ as tower fire toll rises to 151

Investigators in Hong Kong say contractors used unsafe scaffolding...

CISRS reforms face delay as new QAC Chair withdraws

CISRS has reopened its search for a new Chair...

ScaffEx26 set for growth as NASC prepares expanded programme

NASC says ScaffEx26 is on track to grow further,...

Related articles

Hong Kong contractors ‘hid unsafe scaffolding netting’ as tower fire toll rises to 151

Investigators in Hong Kong say contractors used unsafe scaffolding netting at the housing estate destroyed by last week’s deadly fire, and then tried to cover it up during inspections. The death toll at Wang...
ADVERTISEMENTS

Latest topics

CISRS reforms face delay as new QAC Chair withdraws

CISRS has reopened its search for a new Chair...

Connolly Scaffolding strengthens partnership with TRAD UK in £3.5m investment

Connolly Scaffolding Ltd has agreed a further £3.5 million...

Benetics introduces AI voice tool to cut site paperwork

A German construction technology firm has launched an AI-powered...

Scaffolders at Sullom Voe Terminal walk out over pay dispute

Around 60 scaffolders, painters, insulators, and supervisors at the...
ADVERTISEMENTS