Ad
Thursday, December 4, 2025

Complete Access installs major power line protection over M25

ADVERTISEMENT

Scaffolding contractors, Complete, have installed over 200 tons of scaffolding to successfully complete a huge challenging power line protection scaffold over the M25 motorway.

The Barnsley based firm, Complete Access Specialist Contracts Ltd have finished a substantial large-scale system scaffold with a protective netting spanning the busy M25 motorway below.

Working for Interserve Industrial on behalf of SSE, Complete erected the scaffold to provide protection to the M25 motorway between junctions 16 (M40) and 17 (Rickmansworth) while refurbishment of the power line are carried out overhead.

The scaffolds are 154m long, due to the angle at which the power line crossed the motorway, stand 9m-13.5m tall with protective netting spanning 82.0m over the carriageway. The scaffold design, approved by M25 agents Connect Plus M25 and Highways Agency, was produced to cope with winter loads; considering the potential for ice on components and snow on platforms and net producing massive tensile loads in the catenary support wires. As a result, bay sizes were reduced, more than doubling the number of frames throughout. Specially made heavy duty 12mm diameter wire rope catenaries were required, a total of 550 stay wires and ground anchors were installed for stability and a total of 880 half-railway sleepers (60 tonne) were used for foundations in order to distribute the scaffold leg loads .

m25

The scaffold was formed from approximately 200 tons of Layher all round system scaffold and took 12 men 4 weeks to erect from start to finish. A complex traffic management scheme involving the simultaneous total closure of both M25 carriageways, junction 17 on-slip road and both Eastbound and Westbound M40 link-roads was necessary to install the netting, which was coordinated between three separate TM contractors, Connect Plus M25 and Buckinghamshire County Council, and took place over 3 consecutive evenings.

A spokesperson for Complete Access Specialist Contracts Ltd said:

“This item in particular presented great challenges, not only in design but also in coordination and interface with highways’ and other third parties. The sheer scale and amount of material in the job is testament to the resolve of the operatives involved in the erection and netting. We believe that it’s the first time M25 has had this kind of protection scaffold installed. Complete have worked on some major crossings in the uk which include the A1, M1, A9 in Scotland & M40 to name a few. The M25 has been the most difficult to date for installing netting taking 15 men 3 consecutive night shifts to install.”

ADVERTISEMENT

Popular Categories

Latest news

Connolly Scaffolding strengthens partnership with TRAD UK in £3.5m investment

Connolly Scaffolding Ltd has agreed a further £3.5 million investment in TRAD UK’s Plettac Metrix system, reinforcing a partnership that has shaped both businesses...

Benetics introduces AI voice tool to cut site paperwork

A German construction technology firm has launched an AI-powered voice assistant designed to help site teams cut paperwork and speed up reporting. Benetics, based in...

Scaffolders at Sullom Voe Terminal walk out over pay dispute

Around 60 scaffolders, painters, insulators, and supervisors at the Sullom Voe Terminal in the Shetland Islands have staged a 24-hour walkout in an escalating...

Hong Kong contractors ‘hid unsafe scaffolding netting’ as tower fire toll rises to 151

Investigators in Hong Kong say contractors used unsafe scaffolding netting at the housing estate destroyed by last week’s deadly fire, and then tried to...

Costs climb again on Manchester Town Hall project as delays worsen

The cost of restoring Manchester Town Hall has risen by a further £95m, with completion now pushed back to spring 2027. The Grade I-listed...

CSCS Alliance appoints new Chair

The CSCS Alliance has confirmed the appointment of Marion Marsland as its new Chair, marking a significant leadership change for the body representing 37...

ScaffEx26 set for growth as NASC prepares expanded programme

NASC says ScaffEx26 is on track to grow further, with early exhibitor demand already exceeding last year’s levels. The trade body confirmed to Scaffmag that...

New Gale Force Bolt introduced to honour industry figure Alan Gale

Tilbury Scaffolding has introduced a new fixing in honour of Alan Gale, a widely respected figure in the scaffolding supply sector whose career spanned...

Scaffolding under scrutiny after Hong Kong tower blaze kills 128

This article has been updated as authorities confirm a revised death toll and launch a criminal and corruption inquiry. At least 128 people have died,...

Budget 2025: NASC warns of rising costs as new tax increases hit construction firms and housing delivery stalls

The Autumn Budget has drawn strong criticism from scaffolding, construction and housebuilding leaders, who warn that a combination of higher wage costs, frozen tax...

Latest news

ADVERTISEMENT

The magazine

Issue 27 | Past issues >>

Popular

Connolly Scaffolding strengthens partnership with TRAD UK in £3.5m investment

Connolly Scaffolding Ltd has agreed a further £3.5 million...

Scaffolders at Sullom Voe Terminal walk out over pay dispute

Around 60 scaffolders, painters, insulators, and supervisors at the...

Hong Kong contractors ‘hid unsafe scaffolding netting’ as tower fire toll rises to 151

Investigators in Hong Kong say contractors used unsafe scaffolding...

CISRS reforms face delay as new QAC Chair withdraws

CISRS has reopened its search for a new Chair...

ScaffEx26 set for growth as NASC prepares expanded programme

NASC says ScaffEx26 is on track to grow further,...

Related articles

Game changing UK-First in Scaffolding Innovation under the Forth Road Bridge 

Layher pioneers its advanced cantilever technique with Hardrock Scaffolding using Layher’s Under-Deck Flex Beam  A colossal scaffolding project is underway beneath the iconic Forth Road Bridge, where West Lothian-based Hardrock Scaffolding Ltd is delivering...
ADVERTISEMENTS

Latest topics

CISRS reforms face delay as new QAC Chair withdraws

CISRS has reopened its search for a new Chair...

Connolly Scaffolding strengthens partnership with TRAD UK in £3.5m investment

Connolly Scaffolding Ltd has agreed a further £3.5 million...

Benetics introduces AI voice tool to cut site paperwork

A German construction technology firm has launched an AI-powered...

Scaffolders at Sullom Voe Terminal walk out over pay dispute

Around 60 scaffolders, painters, insulators, and supervisors at the...
ADVERTISEMENTS