Complete Access installs major power line protection over M25

ADVERTISEMENT

Scaffolding contractors, Complete, have installed over 200 tons of scaffolding to successfully complete a huge challenging power line protection scaffold over the M25 motorway.

The Barnsley based firm, Complete Access Specialist Contracts Ltd have finished a substantial large-scale system scaffold with a protective netting spanning the busy M25 motorway below.

Working for Interserve Industrial on behalf of SSE, Complete erected the scaffold to provide protection to the M25 motorway between junctions 16 (M40) and 17 (Rickmansworth) while refurbishment of the power line are carried out overhead.

The scaffolds are 154m long, due to the angle at which the power line crossed the motorway, stand 9m-13.5m tall with protective netting spanning 82.0m over the carriageway. The scaffold design, approved by M25 agents Connect Plus M25 and Highways Agency, was produced to cope with winter loads; considering the potential for ice on components and snow on platforms and net producing massive tensile loads in the catenary support wires. As a result, bay sizes were reduced, more than doubling the number of frames throughout. Specially made heavy duty 12mm diameter wire rope catenaries were required, a total of 550 stay wires and ground anchors were installed for stability and a total of 880 half-railway sleepers (60 tonne) were used for foundations in order to distribute the scaffold leg loads .

m25

The scaffold was formed from approximately 200 tons of Layher all round system scaffold and took 12 men 4 weeks to erect from start to finish. A complex traffic management scheme involving the simultaneous total closure of both M25 carriageways, junction 17 on-slip road and both Eastbound and Westbound M40 link-roads was necessary to install the netting, which was coordinated between three separate TM contractors, Connect Plus M25 and Buckinghamshire County Council, and took place over 3 consecutive evenings.

A spokesperson for Complete Access Specialist Contracts Ltd said:

“This item in particular presented great challenges, not only in design but also in coordination and interface with highways’ and other third parties. The sheer scale and amount of material in the job is testament to the resolve of the operatives involved in the erection and netting. We believe that it’s the first time M25 has had this kind of protection scaffold installed. Complete have worked on some major crossings in the uk which include the A1, M1, A9 in Scotland & M40 to name a few. The M25 has been the most difficult to date for installing netting taking 15 men 3 consecutive night shifts to install.”

Daniel Norton
Daniel NortonFounder & Editorhttps://www.scaffmag.com
Daniel Norton is the founder and editor of Scaffmag and Editor-in-Chief of Scaffold & Access Magazine. A former scaffolder, he founded Scaffmag in 2008 and now leads its news and editorial coverage of the global scaffolding and access industry, including safety, regulation, business, innovation and major industry events.

Most popular ↑

CISRS says CSCS notice was served to negotiate “from a stronger position”

NASC president Sarah Klieve says CISRS served CSCS notice to negotiate from a stronger position, as Build UK says the card rules don’t block other sectors.

86m Layher scaffold completed at Giotto’s Bell Tower

An 86-metre scaffold erected in just over four months will support a five-year restoration of the Florence landmark while keeping it open to visitors.

Adrian Chiles puts scaffolding skills shortage in national spotlight

A Guardian column has brought wider attention to recruitment pressures already affecting scaffolding contractors.

Queensland coroner calls for mandatory tower scaffold controls after fatal collapse

A Queensland coroner has called for mandatory additional controls on freestanding tower scaffolds in public places after finding that the industry’s accepted height-to-base rule of thumb was not enough to protect against strong winds.

Scottish scaffolding apprentices to compete at ScaffChamp 2026

A team of young scaffolders from Scotland and Northern...

Latest news

Decorator given suspended sentence after fatal ladder electrocution

Daniel Watton was given a suspended sentence after his stepson Connor Lambert was electrocuted moving a ladder near an overhead power line. HSE found the access plans unsafe.
- Advertisement -
More from

86m Layher scaffold completed at Giotto’s Bell Tower

An 86-metre scaffold erected in just over four months will support a five-year restoration of the Florence landmark while keeping it open to visitors.

STAR Housing seeks scaffolding suppliers for £600K framework lot

STAR Housing is seeking scaffolding suppliers for a Shropshire housing framework, with the dedicated access lot estimated at £606,625 including VAT.

Golden Gate Bridge prepares temporary access platforms for seismic works

Night-time lane closures will allow crews to lower access platforms beneath the roadway as work progresses on the bridge’s final seismic retrofit phase.

Right-to-work rules extend liability through construction supply chains

Contractors face new responsibilities for labour supplied through subcontracting chains as expanded right-to-work rules come into force.
Latest articles