Complete Access installs major power line protection over M25

ADVERTISEMENT

Scaffolding contractors, Complete, have installed over 200 tons of scaffolding to successfully complete a huge challenging power line protection scaffold over the M25 motorway.

The Barnsley based firm, Complete Access Specialist Contracts Ltd have finished a substantial large-scale system scaffold with a protective netting spanning the busy M25 motorway below.

Working for Interserve Industrial on behalf of SSE, Complete erected the scaffold to provide protection to the M25 motorway between junctions 16 (M40) and 17 (Rickmansworth) while refurbishment of the power line are carried out overhead.

The scaffolds are 154m long, due to the angle at which the power line crossed the motorway, stand 9m-13.5m tall with protective netting spanning 82.0m over the carriageway. The scaffold design, approved by M25 agents Connect Plus M25 and Highways Agency, was produced to cope with winter loads; considering the potential for ice on components and snow on platforms and net producing massive tensile loads in the catenary support wires. As a result, bay sizes were reduced, more than doubling the number of frames throughout. Specially made heavy duty 12mm diameter wire rope catenaries were required, a total of 550 stay wires and ground anchors were installed for stability and a total of 880 half-railway sleepers (60 tonne) were used for foundations in order to distribute the scaffold leg loads .

m25

The scaffold was formed from approximately 200 tons of Layher all round system scaffold and took 12 men 4 weeks to erect from start to finish. A complex traffic management scheme involving the simultaneous total closure of both M25 carriageways, junction 17 on-slip road and both Eastbound and Westbound M40 link-roads was necessary to install the netting, which was coordinated between three separate TM contractors, Connect Plus M25 and Buckinghamshire County Council, and took place over 3 consecutive evenings.

A spokesperson for Complete Access Specialist Contracts Ltd said:

“This item in particular presented great challenges, not only in design but also in coordination and interface with highways’ and other third parties. The sheer scale and amount of material in the job is testament to the resolve of the operatives involved in the erection and netting. We believe that it’s the first time M25 has had this kind of protection scaffold installed. Complete have worked on some major crossings in the uk which include the A1, M1, A9 in Scotland & M40 to name a few. The M25 has been the most difficult to date for installing netting taking 15 men 3 consecutive night shifts to install.”

Most popular ↑

Two workers killed in Spain after mast climbing platform collapse

Two workers have been killed following the collapse of...

Scottish offshore workers urged to consider scaffolding careers

The Construction Industry Training Board is targeting workers from...

NASC warns members over online conduct in new media policy

The National Access and Scaffolding Confederation said the new...

Robot named Douglas begins work on Tilbury Douglas site

Tilbury Douglas has begun using a humanoid robot to...

Latest news

Complete Access installs major power line protection over M25

ADVERTISEMENT

Scaffolding contractors, Complete, have installed over 200 tons of scaffolding to successfully complete a huge challenging power line protection scaffold over the M25 motorway.

The Barnsley based firm, Complete Access Specialist Contracts Ltd have finished a substantial large-scale system scaffold with a protective netting spanning the busy M25 motorway below.

Working for Interserve Industrial on behalf of SSE, Complete erected the scaffold to provide protection to the M25 motorway between junctions 16 (M40) and 17 (Rickmansworth) while refurbishment of the power line are carried out overhead.

The scaffolds are 154m long, due to the angle at which the power line crossed the motorway, stand 9m-13.5m tall with protective netting spanning 82.0m over the carriageway. The scaffold design, approved by M25 agents Connect Plus M25 and Highways Agency, was produced to cope with winter loads; considering the potential for ice on components and snow on platforms and net producing massive tensile loads in the catenary support wires. As a result, bay sizes were reduced, more than doubling the number of frames throughout. Specially made heavy duty 12mm diameter wire rope catenaries were required, a total of 550 stay wires and ground anchors were installed for stability and a total of 880 half-railway sleepers (60 tonne) were used for foundations in order to distribute the scaffold leg loads .

m25

The scaffold was formed from approximately 200 tons of Layher all round system scaffold and took 12 men 4 weeks to erect from start to finish. A complex traffic management scheme involving the simultaneous total closure of both M25 carriageways, junction 17 on-slip road and both Eastbound and Westbound M40 link-roads was necessary to install the netting, which was coordinated between three separate TM contractors, Connect Plus M25 and Buckinghamshire County Council, and took place over 3 consecutive evenings.

A spokesperson for Complete Access Specialist Contracts Ltd said:

“This item in particular presented great challenges, not only in design but also in coordination and interface with highways’ and other third parties. The sheer scale and amount of material in the job is testament to the resolve of the operatives involved in the erection and netting. We believe that it’s the first time M25 has had this kind of protection scaffold installed. Complete have worked on some major crossings in the uk which include the A1, M1, A9 in Scotland & M40 to name a few. The M25 has been the most difficult to date for installing netting taking 15 men 3 consecutive night shifts to install.”

Popular Categories

Latest posts

Scaffolding firms urged to review RIDDOR procedures as HSE consults on changes

The Health and Safety Executive has launched a consultation on proposed changes to the Reporting of Injuries, Diseases and Dangerous Occurrences Regulations 2013, known...

Scottish offshore workers urged to consider scaffolding careers

The Construction Industry Training Board is targeting workers from Scotland’s offshore energy sector as part of efforts to widen the construction talent pool and...

NASC warns members over online conduct in new media policy

The National Access and Scaffolding Confederation said the new Social Media and General Media Policy sets expectations for how its members, CISRS centres and...

Two workers killed in Spain after mast climbing platform collapse

Two workers have been killed following the collapse of a twin mast climbing work platform in Benidorm, Spain. The incident happened on Wednesday, 22 April,...

Brogan wins Manchester student accommodation access package

Brogan Group has secured the powered access package for a student accommodation building in Manchester. The access specialist will provide several passenger and goods hoists...

‘Not every scaffolder is ok’: Alan Osborn backs mental health campaign at ScaffChamp

Alan Osborn is set to shave his head at ScaffChamp 2026 as part of a campaign to raise £5,000 for men’s mental health and...

Baton opens early adopter programme for scaffolding contractors

Baton has opened applications for its Early Adopter Programme, giving scaffolding contractors early access to a software platform designed specifically for construction subcontractors. The company...

SCA joins Coriant in move to widen access and industrial services capability

Coriant has announced the acquisition of specialist contractor SCA, in a move that further expands the group’s capabilities in access, temporary containment and industrial...

Robot named Douglas begins work on Tilbury Douglas site

Tilbury Douglas has begun using a humanoid robot to carry out administrative and data-collection tasks on a live construction site. The contractor says the...

HAKI reports sharp UK sales drop as construction starts stall

The Swedish-listed scaffolding and access safety group said UK revenues fell to SEK 52 million (£4.2 million) in the three months to 31 March,...

Spring Issue #29 | Past issues >>

Latest topics

Most popular ⚡︎

Two workers killed in Spain after mast climbing platform collapse

Two workers have been killed following the collapse of...

Scottish offshore workers urged to consider scaffolding careers

The Construction Industry Training Board is targeting workers from...

NASC warns members over online conduct in new media policy

The National Access and Scaffolding Confederation said the new...

Robot named Douglas begins work on Tilbury Douglas site

Tilbury Douglas has begun using a humanoid robot to...

Related articles

ADVERTISEMENTS
More from
Latest articles

TRAD UK launches charity campaign supporting Epilepsy Action

TRAD UK has launched a new fundraising campaign in support of Epilepsy Action, the...

Scaffolding firms urged to review RIDDOR procedures as HSE consults on changes

The Health and Safety Executive has launched a consultation on proposed changes to the...

Scottish offshore workers urged to consider scaffolding careers

The Construction Industry Training Board is targeting workers from Scotland’s offshore energy sector as...

NASC warns members over online conduct in new media policy

The National Access and Scaffolding Confederation said the new Social Media and General Media...

Two workers killed in Spain after mast climbing platform collapse

Two workers have been killed following the collapse of a twin mast climbing work...

Brogan wins Manchester student accommodation access package

Brogan Group has secured the powered access package for a student accommodation building in...