Industrial services contractor Cape plc, has secured a two year contract with Woodside in Western Australia.

The new contract has been awarded to a 50/50 joint venture between Cape and UGL for services on the Woodside operated Karratha Gas Plant Life Extension Program. Services to be provided include the detailed planning and execution of access, fire protection application, blasting and painting, cladding and insulation, mechanical, pipe-spool equipment replacement and electrical services. The contract is for a two year period with work expected to commence on site at the beginning of 2016.

Located 1,260 kilometres north of Perth, Western Australia and covering approximately 200 hectares, the Karratha Gas Plant includes five LNG processing trains, two domestic gas trains, six condensate stabilisation units, three LPG fractionation units as well as storage and loading facilities for LNG, LPG and condensate. The plant has the capacity to produce 12,000 tonnes of domestic gas per day.

Joe Oatley, Chief Executive of Cape, said: “We are delighted to announce the award of this new contract with Woodside which was won through our innovative approach and combined service offering with our contract partner, UGL. Woodside is an important client and we look forward to working with them closely to deliver safe and efficient service on this extensive project.”

SM Newsdesk
SM Newsdeskhttps://www.scaffmag.com
The staff at ScaffMag.com the leading scaffolding site for a digital generation.

Most popular ↑

CISRS says CSCS notice was served to negotiate “from a stronger position”

NASC president Sarah Klieve says CISRS served CSCS notice to negotiate from a stronger position, as Build UK says the card rules don’t block other sectors.

86m Layher scaffold completed at Giotto’s Bell Tower

An 86-metre scaffold erected in just over four months will support a five-year restoration of the Florence landmark while keeping it open to visitors.

Adrian Chiles puts scaffolding skills shortage in national spotlight

A Guardian column has brought wider attention to recruitment pressures already affecting scaffolding contractors.

Scaffold Innovations: GapClamp™

  Since the Work at Height Regulations 2005 came into...

Queensland coroner calls for mandatory tower scaffold controls after fatal collapse

A Queensland coroner has called for mandatory additional controls on freestanding tower scaffolds in public places after finding that the industry’s accepted height-to-base rule of thumb was not enough to protect against strong winds.

Latest news

Decorator given suspended sentence after fatal ladder electrocution

Daniel Watton was given a suspended sentence after his stepson Connor Lambert was electrocuted moving a ladder near an overhead power line. HSE found the access plans unsafe.
- Advertisement -
More from

UK construction downturn eases as new work falls faster

The UK construction PMI rose to 46.1 in September, but new work fell faster and subcontractor usage returned to decline.

SAA backs scaffold safety education after Queensland coroner’s findings

SAA supports education following any changes to Queensland’s scaffolding code and calls for stability assessments to account for wind exposure and public safety.

HAKI Safety appoints Tomas Hilmarsson as CEO

HAKI Safety has appointed CFO Tomas Hilmarsson as CEO and president from 1 November, succeeding Sverker Lindberg.

WorkSafe targets fall risks on New Zealand residential sites

WorkSafe New Zealand is inspecting residential sites from October to December, with falls from height accounting for 70% of construction prohibition notices.
Latest articles