XERVON Palmers London Bridge Station roof project nears completion

ADVERTISEMENT

palmers london bridge

Leading scaffolding contractor, XERVON Palmers, are in the final stages of a 14-month contract worth £20 million to deconstruct the train shed roof at the historic, busy London Bridge Railway Station – opening up the station to the sky for the first time in over 100 years.

[dropcap]C[/dropcap]rucially, the XERVON Palmers contract has been completed without the use of major cranes and with all railway operations continuing as normal, 24-hours a day – with the station still capable of serving its 100,000+ passengers per day, and no disruption to station operations, or traffic surrounding the venue – with XERVON Palmers running a separate day and a night shift of operatives and managers.

The huge project – which included creating a structurally-supportive 18,000 square metre protection deck running the full 70m across the station with some 10,000 aluminium special access panels and 350 tonnes of temporary steel and a secondary mobile access system – is part of a £600 million, five year long (running to 2018) refurbishment programme aiming to successfully redevelop one of London’s most historic and busy stations, in partnership with main contractor Costain and Network Rail.

In addition to the design and construction of the mobile protection deck (rolled into place using modern ‘cassette’ techniques), the sequenced, safe removal of the dilapidated, historic, crescent-shaped train shed roof and the creation of a mobile access walkway in the side roofs to remove the roof cladding (with a bespoke access in the central barrel of the site with integral support beams), XERVON Palmers operatives also managed waste and recycling. More than 1,200 tons of steel has been removed (all by hand) and asbestos has been removed from site along with rare heritage material, in the form of pre-1880, Georgian wrought iron and polished re-enforced glass, which has also been recycled.

palmers

The vast London Bridge project adds to XERVON Palmers extensive transport scaffolding and access CV, with recent jobs including St. Pancras, Paddington, Waterloo, Waverley and King’s Cross in addition to works on the iconic Forth and Tay bridges. And with further historic railway station scaffolding, access and other specialist works planned and tendered for during 2013 into 2014, XERVON Palmers continue to provide services for this key market sector.

“This has been an exciting and challenging task,” said Ian McFarlane, Director for Business & Project Development at XERVON Palmers. “We have been very happy to take it on and have succeeded in developing an excellent solution – developing sophisticated and innovative access and scaffolding solutions.

“The creation of the protection deck has allowed work above to continue whilst the station operates as normally as possible at ground level: Thanks to XERVON Palmers design and execution, commuters would know nothing of the comprehensive work plan which allowed the roof to be deconstructed into manageable sizes and weights. The deconstruction sequence ensured that each piece removed was compliant with the detailed loadings allowed. Each piece was manually removed from site via loading paths created within the protection deck. Planning and coordinating the works, managing the logistics and transport to remove and safely dispose of the waste has been a significant success for XERVON Palmers. We used all of our experiences from the past to develop this excellent, expert solution.”

David Crabtree, who headed the XERVON Palmers team throughout the London Bridge project, said: “We’re coming to the end of a huge 14-month scaffolding and access job. And the XERVON Palmers design provided has delivered a safe, cost effective, viable and on-budget and on-schedule solution for the whole project – allowing railway and passenger movements to continue as normal.

“The protection deck was a major design solution, created to fit in with Network Rail’s extensive health and safety regulations for the safety and protection of the general public, railway operatives and the operating railway. We needed to create a safe working environment for everyone. As such, before construction began, we carried out extensive drop testing in the design process on a test rig – to prove to Network Rail and Costain the integrity of our protection deck design. And it has proved to be an extremely safe and successful set-up – as well as simultaneously providing lateral restraint for the two external walls of the station structure, with a 70m tied and braced system, putting loads back into the protection deck with a bracing plane throughout the works. It’s been a big, rewarding and successful job for XERVON Palmers, showcasing the depth of talent in the company and our ability to take on complicated jobs like this, on sites of historical importance and at busy operational centers, with the minimum of disruption.”

And Donald Morrison, CEO of XERVON Palmers added: “This contract is a good example of the company’s expertise in the provision of high end design lead protection decks. This solution has allowed us to carry out the significant deconstruction works safely whilst maintaining 100% passenger throughput at the railway station.”

The XERVON Palmers London Bridge Station project is expected to finish at the end of May, on time and on budget.

ADVERTISEMENT

Popular Categories

Latest posts

Scaffolding sector joins April Fools’ Day with wave of industry jokes

Scaffolding companies and industry figures have taken to social media to mark April Fools’ Day, with a wide range of posts blending humour with...

Founders step away as City Access Scaffolding completes buyout

From Left to Right: Ryan Scott, Mark Skinner, and Ross Archibald

JMAC completes first acquisition with Tees Site Support deal

JMAC Industrial and Access Group Ltd has acquired a majority shareholding in Tees Site Support Ltd, marking the company’s first acquisition as it looks...

Final 20 teams confirmed for ScaffChamp 2026

The final 20 teams competing at ScaffChamp powered by Layher 2026 have been confirmed, with the last place secured after a qualification event in...

£27bn road strategy opens major pipeline for specialist contractors

The government has confirmed Roads Investment Strategy 3 (RIS3), a £27 billion programme covering England's motorway and A-road network through to 2031. A record £8.4...

NASC expands regional leadership as membership rises 40%

The National Access and Scaffolding Confederation (NASC) has announced a series of new regional chair and vice chair appointments as part of a wider...

Layher UK launches ‘Sizzle & Learn’ open morning series for 2026

Layher UK has announced a series of open morning events aimed at giving customers and partners direct access to its latest systems, product developments...

Two taken to hospital after building collapse in Oldham

Two people have been taken to hospital after a building partially collapsed in Oldham town centre. Emergency services were called to King Street at about...

Scafom-rux delivers Manchester’s tallest ground-based scaffold

In the heart of Manchester’s financial district, a major high-rise development is setting new benchmarks for construction scaffolding in the UK. For this complex...

Teen scaffolding labourer dies after fall through shaft on London site

A construction company has been fined after a teenage scaffolding labourer died in a fall from height on a London building site. Renols Lleshi, 19,...

Latest news

Magazine

Spring Issue #29 | Past issues >>

Trending now ⚡︎

Fraud gang jailed for helping candidates cheat CITB safety tests

Three men have been sentenced for their role in...

JMAC completes first acquisition with Tees Site Support deal

JMAC Industrial and Access Group Ltd has acquired a...

Teen scaffolding labourer dies after fall through shaft on London site

A construction company has been fined after a teenage...

NASC expands regional leadership as membership rises 40%

The National Access and Scaffolding Confederation (NASC) has announced...

Scaffolding sector joins April Fools’ Day with wave of industry jokes

Scaffolding companies and industry figures have taken to social...

Related articles

Latest topics

Fraud gang jailed for helping candidates cheat CITB safety tests

Three men have been sentenced for their role in...

Scaffolding sector joins April Fools’ Day with wave of industry jokes

Scaffolding companies and industry figures have taken to social...

Founders step away as City Access Scaffolding completes buyout

From Left to Right: Ryan Scott, Mark Skinner, and Ross Archibald

JMAC completes first acquisition with Tees Site Support deal

JMAC Industrial and Access Group Ltd has acquired a...
ADVERTISEMENTS