86m Layher scaffold completed at Giotto’s Bell Tower

An 86-metre Layher scaffold erected in just over four months will support the first full restoration of Florence’s Giotto’s Bell Tower.

ADVERTISEMENT

An 86-metre scaffold erected in just over four months will support a five-year restoration of the Florence landmark while keeping it open to visitors.

Scaffolding has been completed around Giotto’s Bell Tower in Florence, clearing the way for the historic landmark’s first full internal and external restoration.

The 86-metre structure uses Layher’s modular steel system and was designed by Opera di Santa Maria del Fiore in collaboration with Tecno System Appalti and Layher S.p.A.

The Opera confirmed completion on 1 October, following just over four months of assembly. The restoration is expected to take around five years and cost more than €7 million, funded entirely by the institution.

The scaffold has been configured around the tower’s changing geometry and projecting architectural features, with working platforms arranged to meet the restoration team’s needs.

Full-height scaffold at Giotto’s Bell Tower with protective mesh around the upper working section
A full-height view of the scaffold at Giotto’s Bell Tower, with the upper working section enclosed in protective mesh. Courtesy: Opera di Santa del Fiore/foto Fabio Muzzi

Samuele Caciagli, head of the Opera’s technical office, said the design sought to avoid altering the tower’s structural equilibrium while keeping its architecture visible. Components and equipment have also been selected for recovery and reuse on future projects.

Work will progress from the top down, revealing restored sections in stages. Caciagli told Italian news agency askanews that the scaffold had been designed to leave at least 60% of the marble surfaces visible.

The first stage will involve diagnostic investigations and preliminary tests to confirm the restoration approach before treatment of the stonework begins.

Visitors will continue to be able to climb the tower’s 414 steps and reach its rooftop terrace throughout the works, although views may be partially restricted.

Construction of the bell tower began under Giotto in 1334 and was completed by Francesco Talenti in 1359. Its exterior is clad in white, red and green marble.

Assembly of the scaffold also had to accommodate a pair of nesting peregrine falcons.

A photographic survey of the tower’s 149 putlog holes identified a female incubating eggs on the west side. Working with bird conservation organisation Lipu and other specialists, the Opera rescheduled assembly to avoid disturbing the nest.

Three chicks subsequently hatched and fledged successfully.

Featured image: The completed restoration scaffold around Giotto’s Bell Tower, pictured beside Florence Cathedral. Courtesy: Opera di Santa del Fiore/foto Fabio Muzzi

Daniel Norton
Daniel NortonFounder & Editorhttps://www.scaffmag.com
Daniel Norton is the founder and editor of Scaffmag and Editor-in-Chief of Scaffold & Access Magazine. A former scaffolder, he founded Scaffmag in 2008 and now leads its news and editorial coverage of the global scaffolding and access industry, including safety, regulation, business, innovation and major industry events.

Most popular ↑

CISRS says CSCS notice was served to negotiate “from a stronger position”

NASC president Sarah Klieve says CISRS served CSCS notice to negotiate from a stronger position, as Build UK says the card rules don’t block other sectors.

Scaffold collapses at Sydney site weeks after two workers seriously injured

The scaffold came down at a development on Wattle...

Adrian Chiles puts scaffolding skills shortage in national spotlight

A Guardian column has brought wider attention to recruitment pressures already affecting scaffolding contractors.

Scaffold Innovations: GapClamp™

  Since the Work at Height Regulations 2005 came into...

SG4:10 We Think The Answer Is Fast Guard™

If Carlsberg made advance guardrails.....  could this be the...

Latest news

HAKI Safety appoints Tomas Hilmarsson as CEO

HAKI Safety has appointed CFO Tomas Hilmarsson as CEO and president from 1 November, succeeding Sverker Lindberg.
- Advertisement -
More from

HAKI Safety appoints Tomas Hilmarsson as CEO

HAKI Safety has appointed CFO Tomas Hilmarsson as CEO and president from 1 November, succeeding Sverker Lindberg.

Golden Gate Bridge prepares temporary access platforms for seismic works

Night-time lane closures will allow crews to lower access platforms beneath the roadway as work progresses on the bridge’s final seismic retrofit phase.
01:16:17

How do you get off the tools? Two men who did it properly

The latest episode of The Brace Yourself Podcast puts the question every scaffolder has asked to two guests who made the move into design: Buckley Design Solutions founder Lee Buckley and Altrad Denmark Technical Authority Tony Nicolaisen.

PERI scaffolding supports major HS2 Birmingham dive-under works

PERI UK has supplied access scaffolding, formwork and engineering support for a 400m-long concrete dive-under being built as part of HS2’s Delta Junction near Birmingham.
Latest articles