Tyne Bridge teams hit 70% protection deck target

ISS prepared and delivered more than 200 tonnes of scaffolding as teams completed 70% of the Tyne Bridge protection deck during its ten-day closure.

ADVERTISEMENT

Scaffolders met the target of completing 70% of the Tyne Bridge’s overhead protection deck during its ten-day closure

The installation moves the restoration closer to work on the main steel arch in early 2027. Subcontractor Infrastructure Site Services (ISS) prepared and delivered more than 200 tonnes of scaffolding for the closure phase, according to managing director Christian Farquhar.

The bridge was closed to vehicles, pedestrians and cyclists from 23 October to 2 November. Esh said it was the first full closure to all users since restoration began, giving teams unrestricted access above and across the carriageway.

Around 20 working hours were lost to bad weather at the start of the closure, but the contractor said teams recovered the programme. They also removed the remaining street lighting columns and carried out preparatory work for vehicle restraint system plates and further repairs.

Farquhar said:

“Logistically, we had to prepare and deliver over 200 tonnes of scaffolding for the closure phase.”

He said deliveries had to continue progressively throughout the working days. ISS, Esh and both councils had planned the operation together, coordinating materials, labour and access ahead of the October half-term closure while preparing for the remaining deck work.

As Scaffmag reported ahead of the closure, the protection deck spans the carriageway and footpaths. It will allow the crossing to remain in use while restoration moves onto the arch above.

The published installation plan uses independent scaffold legs along both footpaths, with twin aluminium beams spanning between them. Scaffold boards and temporary carriageway lighting complete the arrangement.

Esh senior project manager Gareth Dawson said structural repairs within the bridge’s voids were essential to the next stage. Restoring lost capacity allows the bridge to carry the additional scaffolding loads needed to reach the main arch, he said.

Dave Charnley Photography

Work on the remaining protection deck is continuing through November. Esh expects scaffolding around the main arch to become visible over the festive period and into 2027.

The arch restoration will include grit blasting, steelwork repairs and a specialist three-coat protective paint system, finished in Hollybush Green. Earlier phases have covered the under arches beside the towers, the underside of the main river span, hangers, parapets and curved screen plates.

Esh is delivering the scheme for Newcastle City Council and Gateshead Council. The contractor said the overall restoration remains on schedule to finish ahead of the bridge’s centenary in October 2028.

Daniel Norton
Daniel NortonFounder & Editorhttps://www.scaffmag.com
Daniel Norton is the founder and editor of Scaffmag and Editor-in-Chief of Scaffold & Access Magazine. A former scaffolder, he founded Scaffmag in 2008 and now leads its news and editorial coverage of the global scaffolding and access industry, including safety, regulation, business, innovation and major industry events.

Most popular ↑

SAIA names teams for 2027 Scaffold Builders Competition

Manchester-based AK Scaffolding is on the list for Las Vegas, alongside 4 first-time entrants from the US, Lithuania, Switzerland and Canada.

Scaffold firm fined £16,000 after trainee’s fatal fall

HSE found that safe zones had not been established when Michael Swales fell 5 metres from a partially erected scaffold near Ripon.

Mobile scaffold falls three decks on offshore support vessel

Marine Safety Forum reports a three-tier scaffold collapse during repositioning, with seized wheels and no exclusion zone on the deck below.

NASC warns on scaffold loads and driver fatigue

NASC highlights load security, fatigue and vehicle checks as a new free Truck Driver Toolkit puts scaffolding transport risks in focus.

Taylor Wimpey opens redundancy talks over local team changes

Taylor Wimpey is consulting staff over local team changes that could lead to redundancies. The number of roles affected has not been disclosed.

Latest news

Construction output falls 0.7% in third quarter

Construction output fell 0.7% between July and September, while the wider UK economy grew by the same margin.
- Advertisement -
More from

Construction output falls 0.7% in third quarter

Construction output fell 0.7% between July and September, while the wider UK economy grew by the same margin.

Taylor Wimpey scaffolders’ pay dispute moves to strike ballot

Unite says voting in the Sunderland pay dispute opened on 9 November and closes on 23 November. The dispute involves 19 scaffolders and 31 joiners.

KEWAZO to join debate on getting construction robots onto site

KEWAZO joins Groundworks in London on 11 November for discussions on the costs, buying models and practical barriers to wider use of construction robotics.

Safety and Access wins Hackney inspection contract

Safety and Access will carry out statutory scaffold inspections across Hackney Council's housing stock under a £74,100 award.
Latest articles