In Pictures: GKR completes major temporary roof structure at HS2 Euston

ADVERTISEMENT

GKR Scaffolding has completed a large temporary roof structure at HS2’s Euston site.

The installation sits beside the live station and supports enclosed works that are expected to continue for the next 12 months.

Project overview

  • Roof span: 32 metres
  • Apex height: 9.5 metres
  • Roof length: 76 metres
  • Track length: 130 metres
  • Weight: 98.4 tonnes
  • Build time: eight weeks

The structure provides a controlled and fully screened environment for complex activities on the Euston project. It has been designed so it can move as works progress, allowing teams to maintain activity without affecting nearby piling operations.

A key element of the project is the use of a rebar-free foundation system. The bases can be removed and reused as the encapsulation moves along Cardington Street. This is intended to support a faster programme once follow-on works begin.

GKR delivered the installation in collaboration with the MDJV project team, temporary works specialists and Network Rail.

The images will show the scale of the roof, the encapsulation detail and the track system used to relocate the structure as construction advances.

 

SM Newsdesk
SM Newsdeskhttps://www.scaffmag.com
The staff at ScaffMag.com the leading scaffolding site for a digital generation.

Most popular ↑

Contractor injured in fall during Port Kembla scaffold erection

ABC reports that a contractor was injured in a fall during scaffold erection at BlueScope’s Port Kembla steelworks on 29 October. SafeWork NSW inspectors visited the site.

Ibstock issues profit warning as brick demand weakens

Ibstock has reportedly cut production and lowered its earnings expectations after third-quarter brick sales fell short of forecasts.

Shield tackles hilltop access challenge in 19-day scaffold build

Shield erected access around the 38-metre Lansdowne Monument in 19 days despite a steep, rutted route that kept vans and lorries away from the hilltop.

Scaffolding firms face tighter harassment duties from 30 October

Stronger harassment duties and new union-access rules take effect across Great Britain on 30 October, with implications for firms working on client-controlled sites.

PHD Access joins £190m Dungeness A decommissioning team

Aureos has named PHD Access as its scaffolding partner for the removal of eight 800-tonne boilers at Dungeness A. The overall programme is worth up to £190m.

Latest news

NIE Networks tenders £4.8m scaffolding framework for power infrastructure

NIE Networks is seeking scaffolding services across Northern Ireland's electricity infrastructure through two lots, with an initial four-year term and extension options.
- Advertisement -
More from

PHD Access joins £190m Dungeness A decommissioning team

Aureos has named PHD Access as its scaffolding partner for the removal of eight 800-tonne boilers at Dungeness A. The overall programme is worth up to £190m.

Shield tackles hilltop access challenge in 19-day scaffold build

Shield erected access around the 38-metre Lansdowne Monument in 19 days despite a steep, rutted route that kept vans and lorries away from the hilltop.

Tyne Bridge to close for overhead scaffold deck installation

Advanced scaffolders will work around the clock during an October half-term closure to install a protection deck ahead of main arch restoration in early 2027.

86m Layher scaffold completed at Giotto’s Bell Tower

An 86-metre scaffold erected in just over four months will support a five-year restoration of the Florence landmark while keeping it open to visitors.
Latest articles