Chris Sedgeman Scaffolding Ltd completes challenging Cornish Viaduct project. 

ADVERTISEMENT

The Hayle Viaduct

The Hayle Railway, opened in 1837, it was situated in front of the magnificent viaduct, built in 1852 by the West Cornwall Railway to I. K. Brunel’s design. The original viaduct, which was made of wooden trestle, stood for 34 years before being rebuilt in granite in 1886. Hayle viaduct is very unique due to having three roads that run under it.

Infrastructure contractors Dyer & Butler enlisted Chris Sedgeman Scaffolding Ltd to erect a 300m long x 12m wide x 12m high scaffold for major refurbishment works on the viaduct. Approximately 1,000 life expired deck timbers, old track, ballast, 4,500 rivets and existing handrail needed to be replaced within a challenging 6 week period.

Work Commenced

NASC registered scaffolding contractors Chris Sedgeman Scaffolding Ltd commenced works with the main access scaffold which was 300m long x 12m wide x 12m high. Using the time saving Plettac Contur scaffold system the scaffold was erected to the outside face of the viaduct plus in-between each of it’s 37 piers.

250 x 780mm deep beams were used to bridge under the viaduct, in total over 10,000 system components, 5,500 short boards and a 1000 sheets of ply-wood were used. Six access staircases and a secondary birdcage came together to complete this impressive structure.

Eight highly skilled scaffolding professionals from Chris Sedgeman Scaffolding Ltd were given the task to erect the main scaffold working twelve hour day shifts completing the structure in five weeks. Once railway line closures were in-place four men were on day shifts and four on nights.

A rolling temporary roof was also erected as Dyer & Butler had only 16 days to complete the works. The roof was to enable the client to remove and renew approximately 1000 sleepers, old track and ballast. Chris Sedgeman Scaffolding Ltd were rolling on average 25m a shift and the roof was erected and dismantled in 6 days.

Chris Sedgeman Scaffolding Ltd

Once the line re-opened, scaffolders then shrink-wrapped the underside of the track and the sides of the viaduct for replacing steel work and repainting the whole viaduct. These works are still on going.

Project Challenges

  • Timescales in which to erect the scaffolding.
  • The viaduct curved for 10m over the length of the viaduct.
  • Access to the site was very restricted and difficult to deliver scaffolding equipment.
  • Working over public roads had to allow for traffic with stop go boards.

Do you have an interesting project you would like to share ? Drop us an email 


Most popular ↑

Amber heat alert puts scaffolding site welfare in focus

Scaffolding firms are being urged to review hot-weather controls...

New NASC TG4 guidance targets anchor tie safety on site

NASC has launched a new TG4 User Guide and...

JR Scaffold Services leads access project at Glasgow Royal Infirmary

JR Scaffold Services has completed a specialist scaffold and...

AT-PAC opens Darwin branch to support northern Australia projects

AT-PAC has opened a new branch in Darwin, Northern...

UK construction starts tipped to rise after difficult start to 2026

UK construction activity is expected to recover from 2027...

Latest news

ADVERTISEMENT
More from
Latest articles

Des Moore: “The next five years are critical” for scaffolding

As Des Moore approaches his 70th birthday, he is not interested in nostalgia. After...

AT-PAC expands European marketing support with Petite Agency

AT-PAC has expanded its marketing partnership with Petite Agency to cover parts of its...

HSE warns employers to protect workers as extreme heat alert begins

Scaffolding contractors across much of England are being urged to act on heat risk...

New NASC TG4 guidance targets anchor tie safety on site

NASC has launched a new TG4 User Guide and poster to support the safe...

Amber heat alert puts scaffolding site welfare in focus

Scaffolding firms are being urged to review hot-weather controls as an amber heat-health alert...

AT-PAC opens Darwin branch to support northern Australia projects

AT-PAC has opened a new branch in Darwin, Northern Territory, giving contractors in northern...

JR Scaffold Services leads access project at Glasgow Royal Infirmary

JR Scaffold Services has completed a specialist scaffold and temporary roof project at the...

UK construction will need 41,200 extra workers a year, CITB warns

The UK construction industry will need an average of 41,200 extra workers each year...