Chris Sedgeman Scaffolding Ltd completes challenging Cornish Viaduct project. 

ADVERTISEMENT

The Hayle Viaduct

The Hayle Railway, opened in 1837, it was situated in front of the magnificent viaduct, built in 1852 by the West Cornwall Railway to I. K. Brunel’s design. The original viaduct, which was made of wooden trestle, stood for 34 years before being rebuilt in granite in 1886. Hayle viaduct is very unique due to having three roads that run under it.

Infrastructure contractors Dyer & Butler enlisted Chris Sedgeman Scaffolding Ltd to erect a 300m long x 12m wide x 12m high scaffold for major refurbishment works on the viaduct. Approximately 1,000 life expired deck timbers, old track, ballast, 4,500 rivets and existing handrail needed to be replaced within a challenging 6 week period.

Work Commenced

NASC registered scaffolding contractors Chris Sedgeman Scaffolding Ltd commenced works with the main access scaffold which was 300m long x 12m wide x 12m high. Using the time saving Plettac Contur scaffold system the scaffold was erected to the outside face of the viaduct plus in-between each of it’s 37 piers.

250 x 780mm deep beams were used to bridge under the viaduct, in total over 10,000 system components, 5,500 short boards and a 1000 sheets of ply-wood were used. Six access staircases and a secondary birdcage came together to complete this impressive structure.

Eight highly skilled scaffolding professionals from Chris Sedgeman Scaffolding Ltd were given the task to erect the main scaffold working twelve hour day shifts completing the structure in five weeks. Once railway line closures were in-place four men were on day shifts and four on nights.

A rolling temporary roof was also erected as Dyer & Butler had only 16 days to complete the works. The roof was to enable the client to remove and renew approximately 1000 sleepers, old track and ballast. Chris Sedgeman Scaffolding Ltd were rolling on average 25m a shift and the roof was erected and dismantled in 6 days.

Chris Sedgeman Scaffolding Ltd

Once the line re-opened, scaffolders then shrink-wrapped the underside of the track and the sides of the viaduct for replacing steel work and repainting the whole viaduct. These works are still on going.

Project Challenges

  • Timescales in which to erect the scaffolding.
  • The viaduct curved for 10m over the length of the viaduct.
  • Access to the site was very restricted and difficult to deliver scaffolding equipment.
  • Working over public roads had to allow for traffic with stop go boards.

Do you have an interesting project you would like to share ? Drop us an email 


Daniel Norton
Daniel NortonFounder & Editorhttps://www.scaffmag.com
Daniel Norton is the founder and editor of Scaffmag and Editor-in-Chief of Scaffold & Access Magazine. A former scaffolder, he founded Scaffmag in 2008 and now leads its news and editorial coverage of the global scaffolding and access industry, including safety, regulation, business, innovation and major industry events.

Most popular ↑

Mace Dragados seeks scaffold contractor for £5m HS2 Euston package

Mace Dragados is inviting bids for a £2.5m–£5m scaffolding package supporting demolition work at HS2 Euston, with submissions due by noon on 27 November.

NASC ends muddle over ‘basic’ scaffolding definition

The trade body for scaffolding contractors has launched an...

Scaffolding supplier Tube Monkeys goes into liquidation

Kent-based Tube Monkeys Scaffolding Supplies has entered voluntary liquidation, with company documents estimating a £142,000 shortfall for creditors.

SG4:10 We Think The Answer Is Fast Guard™

If Carlsberg made advance guardrails.....  could this be the...

Scaffold Innovations: GapClamp™

  Since the Work at Height Regulations 2005 came into...

Latest news

TRS wins £255,000 scaffold job at listed Bristol hotel

Homes England has appointed TRS Group (South West) to carry out scaffolding works after an inspection condemned the existing scaffold at the former George Railway Hotel.
- Advertisement -
More from

The scaffolding behind London Museum’s Smithfield opening

London Museum opens at Smithfield on Saturday. JDC Scaffolding used a 3,000-board working deck and six temporary roofs during the restoration.

Inside BrandSafway’s extraordinary scaffold around space shuttle Endeavour

BrandSafway helped protect space shuttle Endeavour during one of the more unusual construction projects in recent years, as contractors built a 200ft-high museum gallery around the spacecraft while it was already standing upright inside.

Tyne Bridge teams hit 70% protection deck target

ISS prepared and delivered more than 200 tonnes of scaffolding as teams completed 70% of the Tyne Bridge protection deck during its ten-day closure.

Doka details climbing systems for Burj Binghatti tower

Doka’s project update sets out the climbing and edge-protection systems being used on Burj Binghatti, with a target of 1 floor a week.
Latest articles