Chris Sedgeman Scaffolding Ltd completes challenging Cornish Viaduct project. 

ADVERTISEMENT

The Hayle Viaduct

The Hayle Railway, opened in 1837, it was situated in front of the magnificent viaduct, built in 1852 by the West Cornwall Railway to I. K. Brunel’s design. The original viaduct, which was made of wooden trestle, stood for 34 years before being rebuilt in granite in 1886. Hayle viaduct is very unique due to having three roads that run under it.

Infrastructure contractors Dyer & Butler enlisted Chris Sedgeman Scaffolding Ltd to erect a 300m long x 12m wide x 12m high scaffold for major refurbishment works on the viaduct. Approximately 1,000 life expired deck timbers, old track, ballast, 4,500 rivets and existing handrail needed to be replaced within a challenging 6 week period.

Work Commenced

NASC registered scaffolding contractors Chris Sedgeman Scaffolding Ltd commenced works with the main access scaffold which was 300m long x 12m wide x 12m high. Using the time saving Plettac Contur scaffold system the scaffold was erected to the outside face of the viaduct plus in-between each of it’s 37 piers.

250 x 780mm deep beams were used to bridge under the viaduct, in total over 10,000 system components, 5,500 short boards and a 1000 sheets of ply-wood were used. Six access staircases and a secondary birdcage came together to complete this impressive structure.

Eight highly skilled scaffolding professionals from Chris Sedgeman Scaffolding Ltd were given the task to erect the main scaffold working twelve hour day shifts completing the structure in five weeks. Once railway line closures were in-place four men were on day shifts and four on nights.

A rolling temporary roof was also erected as Dyer & Butler had only 16 days to complete the works. The roof was to enable the client to remove and renew approximately 1000 sleepers, old track and ballast. Chris Sedgeman Scaffolding Ltd were rolling on average 25m a shift and the roof was erected and dismantled in 6 days.

Chris Sedgeman Scaffolding Ltd

Once the line re-opened, scaffolders then shrink-wrapped the underside of the track and the sides of the viaduct for replacing steel work and repainting the whole viaduct. These works are still on going.

Project Challenges

  • Timescales in which to erect the scaffolding.
  • The viaduct curved for 10m over the length of the viaduct.
  • Access to the site was very restricted and difficult to deliver scaffolding equipment.
  • Working over public roads had to allow for traffic with stop go boards.

Do you have an interesting project you would like to share ? Drop us an email 


Most popular ↑

£4.5m scaffolding framework opens for contractors in North East and Yorkshire

Beyond Housing has opened bidding for a £4.5m scaffolding framework covering planned and reactive works across Redcar and Cleveland and parts of North Yorkshire.

£260k Newcastle Cathedral scaffolding contract opens for bids

Newcastle City Council has opened a £260,000 scaffolding tender to provide specialist access for conservation repairs to Newcastle Cathedral’s historic 15th-century Lantern Tower.

Australia steps up push for scaffolding to gain skilled-trade status

Scaffolding Association Australia has taken its campaign for formal trade recognition and a structured apprenticeship pathway to federal decision-makers in Canberra.

Robot inspection removes need for scaffold access on 70m Cemex kiln

A wall-climbing robot has completed ultrasonic testing across a 70m rotary kiln at Cemex’s Rugby cement plant, removing the need for personnel to work at height and avoiding a conventional scaffold or rope-access operation.

NASC calls for HSE funding boost and national scaffolding training network

The NASC has called for increased HSE funding, a nationwide network of scaffolding training providers and stronger protections for contractors as it launches its updated 2026 manifesto.

Latest news

£500k scaffolding package opens on major North Somerset campus

A £500,000 scaffolding package is among a series of opportunities being brought to market for Epic Systems’ new European headquarters near Bristol, with local contractors being urged to register their interest.
- Advertisement -
More from

URTIM supplies scaffolding and formwork for $2bn Ceyhan petrochemical project

Turkish formwork and scaffolding manufacturer URTIM is supplying engineered temporary works systems for the major Ceyhan PDH/PP petrochemical development in southern Türkiye.

AT-PAC and partners deliver major weather protection scheme in Sweden

Around 700 tonnes of AT-PAC Ringlock scaffolding has been installed to support a major temporary weather protection system over...

JR Scaffold Services leads access project at Glasgow Royal Infirmary

JR Scaffold Services has completed a specialist scaffold and temporary roof project at the B-listed Walton Building at Glasgow...

Scaffolding takes centre stage at Arc Project’s 24-hour warehouse race

Midland Scaffolding Services has helped deliver an unusual event project after building a 270 sq m scaffold projection screen...
Latest articles