Chris Sedgeman Scaffolding Ltd completes challenging Cornish Viaduct project. 

ADVERTISEMENT

The Hayle Viaduct

The Hayle Railway, opened in 1837, it was situated in front of the magnificent viaduct, built in 1852 by the West Cornwall Railway to I. K. Brunel’s design. The original viaduct, which was made of wooden trestle, stood for 34 years before being rebuilt in granite in 1886. Hayle viaduct is very unique due to having three roads that run under it.

Infrastructure contractors Dyer & Butler enlisted Chris Sedgeman Scaffolding Ltd to erect a 300m long x 12m wide x 12m high scaffold for major refurbishment works on the viaduct. Approximately 1,000 life expired deck timbers, old track, ballast, 4,500 rivets and existing handrail needed to be replaced within a challenging 6 week period.

Work Commenced

NASC registered scaffolding contractors Chris Sedgeman Scaffolding Ltd commenced works with the main access scaffold which was 300m long x 12m wide x 12m high. Using the time saving Plettac Contur scaffold system the scaffold was erected to the outside face of the viaduct plus in-between each of it’s 37 piers.

250 x 780mm deep beams were used to bridge under the viaduct, in total over 10,000 system components, 5,500 short boards and a 1000 sheets of ply-wood were used. Six access staircases and a secondary birdcage came together to complete this impressive structure.

Eight highly skilled scaffolding professionals from Chris Sedgeman Scaffolding Ltd were given the task to erect the main scaffold working twelve hour day shifts completing the structure in five weeks. Once railway line closures were in-place four men were on day shifts and four on nights.

A rolling temporary roof was also erected as Dyer & Butler had only 16 days to complete the works. The roof was to enable the client to remove and renew approximately 1000 sleepers, old track and ballast. Chris Sedgeman Scaffolding Ltd were rolling on average 25m a shift and the roof was erected and dismantled in 6 days.

Chris Sedgeman Scaffolding Ltd

Once the line re-opened, scaffolders then shrink-wrapped the underside of the track and the sides of the viaduct for replacing steel work and repainting the whole viaduct. These works are still on going.

Project Challenges

  • Timescales in which to erect the scaffolding.
  • The viaduct curved for 10m over the length of the viaduct.
  • Access to the site was very restricted and difficult to deliver scaffolding equipment.
  • Working over public roads had to allow for traffic with stop go boards.

Do you have an interesting project you would like to share ? Drop us an email 


Daniel Norton
Daniel NortonFounder & Editorhttps://www.scaffmag.com
Daniel Norton is the founder and editor of Scaffmag and Editor-in-Chief of Scaffold & Access Magazine. A former scaffolder, he founded Scaffmag in 2008 and now leads its news and editorial coverage of the global scaffolding and access industry, including safety, regulation, business, innovation and major industry events.

Most popular ↑

CISRS says CSCS notice was served to negotiate “from a stronger position”

NASC president Sarah Klieve says CISRS served CSCS notice to negotiate from a stronger position, as Build UK says the card rules don’t block other sectors.

Lee Marley turnover hits £95.4m as profit falls

The masonry and scaffolding contractor invested £2.99m in scaffold and other fixed assets and entered 2026 with £131m of secured work.

Blencowe report details £620,000 asset sale and creditor shortfall

Newly filed administrators’ proposals detail the August equipment sale to Aiseandan Plant and forecast no dividend for Blencowe’s unsecured creditors.

Scottish scaffolding apprentices to compete at ScaffChamp 2026

A team of young scaffolders from Scotland and Northern...

China joins IASA as global membership continues to expand

China has become the latest country to join the...

Latest news

Man taken to hospital after Evesham scaffolding incident

Specialist paramedics and firefighters rescued a man following a fall from scaffolding near Evesham Library. He was taken to Worcestershire Royal Hospital.
- Advertisement -
More from

Tyne Bridge to close for overhead scaffold deck installation

Advanced scaffolders will work around the clock during an October half-term closure to install a protection deck ahead of main arch restoration in early 2027.

86m Layher scaffold completed at Giotto’s Bell Tower

An 86-metre scaffold erected in just over four months will support a five-year restoration of the Florence landmark while keeping it open to visitors.

Golden Gate Bridge prepares temporary access platforms for seismic works

Night-time lane closures will allow crews to lower access platforms beneath the roadway as work progresses on the bridge’s final seismic retrofit phase.

PERI scaffolding supports major HS2 Birmingham dive-under works

PERI UK has supplied access scaffolding, formwork and engineering support for a 400m-long concrete dive-under being built as part of HS2’s Delta Junction near Birmingham.
Latest articles