PERI’s Scaffolding System Chosen for Essex Contractor’s Biggest Project Yet

ADVERTISEMENT

PERI, PDC Scaffolding and PSD have joined forces to deliver a complex recladding project in East London.

Essex-based scaffolding contractor, PDC Scaffolding, has recently taken on its largest project to date using PERI’s scaffolding system, PERI UP Flex. 

Known as Payne Road, this geometrically complex recladding scheme is located in East London and required a scaffolding system that could adapt to the building’s irregular geometry as it increased in height.

The solution was a wrap-around design consisting of 221 tonnes of PERI UP Flex scaffolding, providing perimeter access to all 16 storeys to facilitate cladding replacement. Working in collaboration with PERI’s design team, the project’s principal scaffolding designer, PSD Prime Scaffold and Structural Designs Ltd, was able to understand the system’s specifications and capabilities during the planning phase, making the installation process on-site smoother.

According to Dion Penman, Scaffolding Project Delivery Manager at PERI, this project was particularly challenging due to the building’s awkward shape. He explains, “The scaffolding arrangement had to be designed to the absolute millimetre to make it work.” However, the PERI UP Flex system was ideal for this type of project because it lends itself to odd shapes, providing contractors unrestricted access around the scaffold to carry out the work.

Paul Casey, Managing Director of PDC Scaffolding, highlighted the benefits of the PERI UP system’s flexible components, explaining how the different deck sizes allowed them to accommodate the building’s shape. Furthermore, components like PERI’s console brackets enabled the team to navigate safely around every part of the building, covering all the gaps.

“The reason we’ve used the PERI UP system is because it’s the most versatile system out there,” he said. “The different deck sizes available in the range have been beneficial as we’ve been able to install a deck arrangement that accommodates the shape of the building. In addition to the decks, using components like the console brackets meant that we could get around every part of the building safely.”

This scaffold marks PDC Scaffolding’s fourth project using the PERI UP system, and the company is investing £2m in the system following its Payne Road project. This continual investment plan will support the company’s recladding and refurbishment projects over the coming years.

The collaboration between PDC Scaffolding, PERI, and PSD Prime Scaffold and Structural Designs Ltd has successfully delivered a complex recladding project using PERI UP Flex, demonstrating the system’s versatility and ability to adapt to challenging geometries.

SM Newsdesk
SM Newsdeskhttps://www.scaffmag.com
The staff at ScaffMag.com the leading scaffolding site for a digital generation.

Most popular ↑

CISRS says CSCS notice was served to negotiate “from a stronger position”

NASC president Sarah Klieve says CISRS served CSCS notice to negotiate from a stronger position, as Build UK says the card rules don’t block other sectors.

86m Layher scaffold completed at Giotto’s Bell Tower

An 86-metre scaffold erected in just over four months will support a five-year restoration of the Florence landmark while keeping it open to visitors.

Monthly Scaff Walk launched to support mental health conversations

A new monthly walking event aimed at bringing people from across the scaffolding and construction industry together to talk about mental health will begin in London later this month.

Scottish scaffolding apprentices to compete at ScaffChamp 2026

A team of young scaffolders from Scotland and Northern...

Scaffold Innovations: GapClamp™

  Since the Work at Height Regulations 2005 came into...

Latest news

Lee Marley turnover hits £95.4m as profit falls

The masonry and scaffolding contractor invested £2.99m in scaffold and other fixed assets and entered 2026 with £131m of secured work.
- Advertisement -
More from

Tyne Bridge to close for overhead scaffold deck installation

Advanced scaffolders will work around the clock during an October half-term closure to install a protection deck ahead of main arch restoration in early 2027.

86m Layher scaffold completed at Giotto’s Bell Tower

An 86-metre scaffold erected in just over four months will support a five-year restoration of the Florence landmark while keeping it open to visitors.

Golden Gate Bridge prepares temporary access platforms for seismic works

Night-time lane closures will allow crews to lower access platforms beneath the roadway as work progresses on the bridge’s final seismic retrofit phase.

PERI scaffolding supports major HS2 Birmingham dive-under works

PERI UK has supplied access scaffolding, formwork and engineering support for a 400m-long concrete dive-under being built as part of HS2’s Delta Junction near Birmingham.
Latest articles