Ad
Saturday, March 7, 2026

Demanding Project Highlights Harsco’s Customer Service Abilities

ADVERTISEMENT

H145 Uppingham College

A college refurbishment project in Rutland has thrown the spotlight onto the outstanding levels of customer service for which Harsco Infrastructure is widely recognised, and earned the company high praise from its client.

Despite the presence of asbestos and the need for frequent changes during the life of the project, Harsco was able to provide a CUPLOK® scaffolding system which allowed the windows at Uppingham Community College to be replaced in-line with an extremely demanding schedule.

“This was certainly a project which provided its fair share of difficulties, but the Erection and Dismantle team at our Birmingham branch in Tamworth was more than equal to the challenge“ explains Harsco’s Branch Manager Steve Bollans. “The scaffolding system itself was straightforward enough, but there were many other factors which made the job difficult.”

These included the fact that the school was live during the project, which required Harsco to schedule all deliveries to site outside of school hours. Limited road access also meant that delivery vehicles were halted some 70 yards away from the school. The Harsco equipment was then unloaded and transferred to site, past an adjacent nursery school, using lorry-mounted forklift trucks.

“We could only do this when there were no children in the nursery,” adds Steve. “Similarly, when we were installing the scaffolding we had to stop work every time pupils from the main school came outside at break times”  Despite this, and the fact that the decision was taken part way through to extend the project to cover the school’s second storey windows, Harsco was able to help the project meet its very demanding 10-week schedule.

“From the outset the Harsco team were extremely professional, pro-active and advisory, managing an extremely short mobilisation period with ease,” says Chris Cuthbert, Project Manager for the main contractor, Kier. “We had regular site meetings to make sure any design changes were dealt with in a timely fashion. Unfortunately one of the three main sub-contractors under-performed drastically which put a lot of pressure on the Harsco team due to late changes. With this in mind, and with the Harsco people being so pro-active and reactive, the project finished on time. Without this support I’m sure the project would have overrun.”

The fact that asbestos was being removed from the building as the windows were replaced meant that Harsco’s scaffolding design had to allow the proper protective sheeting to be installed all round the areas which were being worked on. This also involved Harsco being asked to make frequent changes to the scaffolding as the project progressed, and often at a moment’s notice.

CUPLOK®

cuplok

Harsco’s CUPLOK® is a multi-purpose steel scaffold system which is ideal for general access, shoring and vertical load support duties. A unique node point design allows up to four components to be connected in one fastening action, making CUPLOK® quick and simple to erect and strike. The fully galvanised, high grade tube is 20% lighter than conventional alternatives, has high resistance to damage and is compatible with up to 3 kN/m² platform loadings, making it strong enough for use in the most demanding applications.

 

ADVERTISEMENT

Popular Categories

Latest news

Construction industry says Spring Statement lacked measures to boost building

Construction leaders have offered a mixed response to Chancellor Rachel Reeves’ Spring Statement, with industry bodies warning that the government missed an opportunity to...

ScaffPlan partners with Leach’s to expand access to scaffold design software

ScaffPlan has formed a strategic partnership with Leach’s, the UK’s largest supplier of scaffolding consumables and equipment, in a move designed to widen access...

Training provider reports disruption as Gulf tensions escalate

The escalating conflict in the Middle East is beginning to affect construction and safety training activity, with early disruption reported to training schedules in...

Subcontractors stay upbeat despite seven-year low in project volumes

Subcontractors across the UK and Ireland remain optimistic about the year ahead despite a tightening construction pipeline, according to a new annual report from...

Doka supports Denmark’s Storstrøm Bridge as 3.8km crossing nears completion

Denmark’s new Storstrøm Bridge is entering its final construction phase, with the 3.8km crossing set to become the country’s third-longest bridge when it opens...

If we achieve AGI, will we still need scaffolding?

Many scaffold firms worldwide are already using AI to analyse inspection records, flag anomalies, and reduce the administrative burden for site managers. It is...

IASA strengthens Asian presence as Taiwan and South Korea join global body

The International Access & Scaffolding Association has announced that the Taiwan Scaffold Development Association and the Korea Temporary Equipment & Engineering Association have joined...

Labour’s 1.5 million homes target faces scaffolder shortage warning

Labour’s pledge to build 1.5 million new homes over the course of this Parliament is facing fresh pressure amid warnings of a shortage of...

Subcontractor pay dips as weather hits sites but wider pressures loom

Self-employed tradespeople earned an average of £1,000 per week in January, according to analysis by Hudson Contract, which manages the industry’s largest payroll for...

Band of Builders releases six-month project list to boost volunteer support

Construction charity Band of Builders has released a six-month schedule of upcoming projects, aimed at encouraging tradespeople to commit time in advance. The registered charity...

Latest news

Magazine

Winter Issue #28 | Past issues >>

Popular

Subcontractors stay upbeat despite seven-year low in project volumes

Subcontractors across the UK and Ireland remain optimistic about...

Training provider reports disruption as Gulf tensions escalate

The escalating conflict in the Middle East is beginning...

ScaffPlan partners with Leach’s to expand access to scaffold design software

ScaffPlan has formed a strategic partnership with Leach’s, the...

Construction industry says Spring Statement lacked measures to boost building

Construction leaders have offered a mixed response to Chancellor...

Doka supports Denmark’s Storstrøm Bridge as 3.8km crossing nears completion

Denmark’s new Storstrøm Bridge is entering its final construction...

Related articles

Latest topics

NASC warns scaffolding skills gap could leave 40,000 roles to fill

NASC has warned the UK scaffolding and access sector...

Construction industry says Spring Statement lacked measures to boost building

Construction leaders have offered a mixed response to Chancellor...

ScaffPlan partners with Leach’s to expand access to scaffold design software

ScaffPlan has formed a strategic partnership with Leach’s, the...

Training provider reports disruption as Gulf tensions escalate

The escalating conflict in the Middle East is beginning...
ADVERTISEMENTS