Demanding Project Highlights Harsco’s Customer Service Abilities

ADVERTISEMENT

H145 Uppingham College

A college refurbishment project in Rutland has thrown the spotlight onto the outstanding levels of customer service for which Harsco Infrastructure is widely recognised, and earned the company high praise from its client.

Despite the presence of asbestos and the need for frequent changes during the life of the project, Harsco was able to provide a CUPLOK® scaffolding system which allowed the windows at Uppingham Community College to be replaced in-line with an extremely demanding schedule.

“This was certainly a project which provided its fair share of difficulties, but the Erection and Dismantle team at our Birmingham branch in Tamworth was more than equal to the challenge“ explains Harsco’s Branch Manager Steve Bollans. “The scaffolding system itself was straightforward enough, but there were many other factors which made the job difficult.”

These included the fact that the school was live during the project, which required Harsco to schedule all deliveries to site outside of school hours. Limited road access also meant that delivery vehicles were halted some 70 yards away from the school. The Harsco equipment was then unloaded and transferred to site, past an adjacent nursery school, using lorry-mounted forklift trucks.

“We could only do this when there were no children in the nursery,” adds Steve. “Similarly, when we were installing the scaffolding we had to stop work every time pupils from the main school came outside at break times”  Despite this, and the fact that the decision was taken part way through to extend the project to cover the school’s second storey windows, Harsco was able to help the project meet its very demanding 10-week schedule.

“From the outset the Harsco team were extremely professional, pro-active and advisory, managing an extremely short mobilisation period with ease,” says Chris Cuthbert, Project Manager for the main contractor, Kier. “We had regular site meetings to make sure any design changes were dealt with in a timely fashion. Unfortunately one of the three main sub-contractors under-performed drastically which put a lot of pressure on the Harsco team due to late changes. With this in mind, and with the Harsco people being so pro-active and reactive, the project finished on time. Without this support I’m sure the project would have overrun.”

The fact that asbestos was being removed from the building as the windows were replaced meant that Harsco’s scaffolding design had to allow the proper protective sheeting to be installed all round the areas which were being worked on. This also involved Harsco being asked to make frequent changes to the scaffolding as the project progressed, and often at a moment’s notice.

CUPLOK®

cuplok

Harsco’s CUPLOK® is a multi-purpose steel scaffold system which is ideal for general access, shoring and vertical load support duties. A unique node point design allows up to four components to be connected in one fastening action, making CUPLOK® quick and simple to erect and strike. The fully galvanised, high grade tube is 20% lighter than conventional alternatives, has high resistance to damage and is compatible with up to 3 kN/m² platform loadings, making it strong enough for use in the most demanding applications.

 

SM Newsdesk
SM Newsdeskhttps://www.scaffmag.com
The staff at ScaffMag.com the leading scaffolding site for a digital generation.

Most popular ↑

Saudi firm breaks 27-year-old scaffolding world record

Saudi scaffolding firm Manar Al Omran has set a new Guinness World Record after building a 67.40m free-standing scaffold in Dammam.

Australian scaffolding group enters administration with over 650 jobs at risk

A group of companies linked to one of Australia’s...

Fulcrum wins new HMP Brinsford scaffolding training contract

Fulcrum Scaffold Safety and Training has been awarded a new Ministry of Justice contract to deliver practical scaffolding training to prisoners at HMP Brinsford.

CSCS challenges CISRS case for leaving card scheme

CSCS has challenged the reasons for CISRS’s planned departure, while CISRS tells ScaffMag its legal advice and concerns over duplicate cards underpin the decision.

Singapore to mandate fire-retardant scaffold netting from 2027

Singapore will require scaffold netting used outside buildings to meet fire-retardant specifications on projects awarded from 1 March 2027.

Latest news

Saudi firm plans SR1.2bn scaffolding manufacturing complex

Manar Al Omran plans a million-square-metre industrial complex in Saudi Arabia to manufacture scaffolding and formwork for domestic projects and export markets.
- Advertisement -
More from

£4.22m Falkirk scaffolding framework opens for bids

Falkirk Council is inviting scaffold contractors to bid for a four-year framework covering scaffold hire, erection, maintenance, inspections and tie testing across its housing properties.

PERI scaffolding supports major HS2 Birmingham dive-under works

PERI UK has supplied access scaffolding, formwork and engineering support for a 400m-long concrete dive-under being built as part of HS2’s Delta Junction near Birmingham.

CSCS challenges CISRS case for leaving card scheme

CSCS has challenged the reasons for CISRS’s planned departure, while CISRS tells ScaffMag its legal advice and concerns over duplicate cards underpin the decision.

Diesel hits record high as scaffolders face rising fuel costs

UK diesel prices have climbed to a record high of around £1.99 a litre, putting fresh pressure on scaffolding contractors running vans, lorries and site fleets.
Latest articles