Malvern Scaffolding and UKSSH rise to park-life

ADVERTISEMENT

Re-surfacing work on a Hereford roof-top shopping centre car park might seem a simple operation but it can present some major challenges.

Not least a complete encapsulation involving some 2,500 sq. metres of lightweight covers… that’s equivalent to 13 full-size tennis courts!

Securely tying down these shelters involved complex discussions with scaffold designers, structural engineers, scaffold contractors and specialist subcontractors to design six separate shelters and not only ensure that the roof would accept the kentledge load, but that the shelters lined up with the falls to the new drains and that some of the shelters could be bolted to existing steelwork on the parapet.

Main contractors Sir Robert McAlpine were confident that Malvern Scaffolding was the company to rise to the challenge, as Roger Smart, Robert McAlpine’s Central. Wales and West Regional Chief Engineer explains:

“The personal attention to detail and proactive involvement of Malvern Scaffolding’s Directors, right from the initial phone call, gave us confidence that they could make this work for us.

“They have proven to be a technically proficient, highly reliable and forward-thinking sub-contractor whose commitment to overcoming obstacles on site has been crucial to the smooth running of this project”.

Malvern Scaffolding is experts in the temporary cover field and holds stocks of the HAKI 750 shelter system. For this project, they designed a series of covers providing an internal workspace with a 14.6-metre clear span.

The various methods of anchoring and Kentledge packs were carefully designed and executed.

Throughout the negotiation period, Malvern kept key suppliers like UK SYSTEM SCAFFOLD HIRE in the loop as it was likely that the bulk of the cover system would have to be hired in for the job.

UKSSH were willing and able to invest in whatever stock was required for the contract. 

Although originally working to an agreed four-week lead time, when this was halved to two weeks UKSSH swung into action and came up with a “just in time” schedule to keep the job rolling along.

As Gary Griffiths, MD of UKSSH explains, “In all, we made a total of 20 delivery runs to site and our site support team worked with Malvern Scaffolding to ensure things were kept to programme. 

“At UKSSH the focus is always on customer support – our success is reliant on our customers succeeding, so all our efforts go into supporting that ethos.

“We are proud to be associated with a highly professional outfit like Malvern Scaffolding”.

SM Newsdesk
SM Newsdeskhttps://www.scaffmag.com
The staff at ScaffMag.com the leading scaffolding site for a digital generation.

Most popular ↑

Contractor injured in fall during Port Kembla scaffold erection

ABC reports that a contractor was injured in a fall during scaffold erection at BlueScope’s Port Kembla steelworks on 29 October. SafeWork NSW inspectors visited the site.

Ibstock issues profit warning as brick demand weakens

Ibstock has reportedly cut production and lowered its earnings expectations after third-quarter brick sales fell short of forecasts.

Four injured in Taiwan market scaffold collapse

Taipei has halted work at the old Beitou market demolition site after a scaffold collapse injured four people. Investigations are continuing.

NIE Networks tenders £4.8m scaffolding framework for power infrastructure

NIE Networks is seeking scaffolding services across Northern Ireland's electricity infrastructure through two lots, with an initial four-year term and extension options.

Scaffold Innovations: GapClamp™

  Since the Work at Height Regulations 2005 came into...

Latest news

Mobile scaffold falls three decks on offshore support vessel

Marine Safety Forum reports a three-tier scaffold collapse during repositioning, with seized wheels and no exclusion zone on the deck below.
- Advertisement -
More from

Doka details climbing systems for Burj Binghatti tower

Doka’s project update sets out the climbing and edge-protection systems being used on Burj Binghatti, with a target of 1 floor a week.

PHD Access joins £190m Dungeness A decommissioning team

Aureos has named PHD Access as its scaffolding partner for the removal of eight 800-tonne boilers at Dungeness A. The overall programme is worth up to £190m.

Shield tackles hilltop access challenge in 19-day scaffold build

Shield erected access around the 38-metre Lansdowne Monument in 19 days despite a steep, rutted route that kept vans and lorries away from the hilltop.

Tyne Bridge to close for overhead scaffold deck installation

Advanced scaffolders will work around the clock during an October half-term closure to install a protection deck ahead of main arch restoration in early 2027.
Latest articles