Malvern Scaffolding and UKSSH rise to park-life

ADVERTISEMENT

Re-surfacing work on a Hereford roof-top shopping centre car park might seem a simple operation but it can present some major challenges.

Not least a complete encapsulation involving some 2,500 sq. metres of lightweight covers… that’s equivalent to 13 full-size tennis courts!

Securely tying down these shelters involved complex discussions with scaffold designers, structural engineers, scaffold contractors and specialist subcontractors to design six separate shelters and not only ensure that the roof would accept the kentledge load, but that the shelters lined up with the falls to the new drains and that some of the shelters could be bolted to existing steelwork on the parapet.

Main contractors Sir Robert McAlpine were confident that Malvern Scaffolding was the company to rise to the challenge, as Roger Smart, Robert McAlpine’s Central. Wales and West Regional Chief Engineer explains:

“The personal attention to detail and proactive involvement of Malvern Scaffolding’s Directors, right from the initial phone call, gave us confidence that they could make this work for us.

“They have proven to be a technically proficient, highly reliable and forward-thinking sub-contractor whose commitment to overcoming obstacles on site has been crucial to the smooth running of this project”.

Malvern Scaffolding is experts in the temporary cover field and holds stocks of the HAKI 750 shelter system. For this project, they designed a series of covers providing an internal workspace with a 14.6-metre clear span.

The various methods of anchoring and Kentledge packs were carefully designed and executed.

Throughout the negotiation period, Malvern kept key suppliers like UK SYSTEM SCAFFOLD HIRE in the loop as it was likely that the bulk of the cover system would have to be hired in for the job.

UKSSH were willing and able to invest in whatever stock was required for the contract. 

Although originally working to an agreed four-week lead time, when this was halved to two weeks UKSSH swung into action and came up with a “just in time” schedule to keep the job rolling along.

As Gary Griffiths, MD of UKSSH explains, “In all, we made a total of 20 delivery runs to site and our site support team worked with Malvern Scaffolding to ensure things were kept to programme. 

“At UKSSH the focus is always on customer support – our success is reliant on our customers succeeding, so all our efforts go into supporting that ethos.

“We are proud to be associated with a highly professional outfit like Malvern Scaffolding”.

SM Newsdesk
SM Newsdeskhttps://www.scaffmag.com
The staff at ScaffMag.com the leading scaffolding site for a digital generation.

Most popular ↑

SAIA names teams for 2027 Scaffold Builders Competition

Manchester-based AK Scaffolding is on the list for Las Vegas, alongside 4 first-time entrants from the US, Lithuania, Switzerland and Canada.

Scaffold firm fined £16,000 after trainee’s fatal fall

HSE found that safe zones had not been established when Michael Swales fell 5 metres from a partially erected scaffold near Ripon.

Mobile scaffold falls three decks on offshore support vessel

Marine Safety Forum reports a three-tier scaffold collapse during repositioning, with seized wheels and no exclusion zone on the deck below.

NASC warns on scaffold loads and driver fatigue

NASC highlights load security, fatigue and vehicle checks as a new free Truck Driver Toolkit puts scaffolding transport risks in focus.

Taylor Wimpey opens redundancy talks over local team changes

Taylor Wimpey is consulting staff over local team changes that could lead to redundancies. The number of roles affected has not been disclosed.

Latest news

Tyne Bridge teams hit 70% protection deck target

ISS prepared and delivered more than 200 tonnes of scaffolding as teams completed 70% of the Tyne Bridge protection deck during its ten-day closure.
- Advertisement -
More from

Tyne Bridge teams hit 70% protection deck target

ISS prepared and delivered more than 200 tonnes of scaffolding as teams completed 70% of the Tyne Bridge protection deck during its ten-day closure.

Doka details climbing systems for Burj Binghatti tower

Doka’s project update sets out the climbing and edge-protection systems being used on Burj Binghatti, with a target of 1 floor a week.

PHD Access joins £190m Dungeness A decommissioning team

Aureos has named PHD Access as its scaffolding partner for the removal of eight 800-tonne boilers at Dungeness A. The overall programme is worth up to £190m.

Shield tackles hilltop access challenge in 19-day scaffold build

Shield erected access around the 38-metre Lansdowne Monument in 19 days despite a steep, rutted route that kept vans and lorries away from the hilltop.
Latest articles