HAKI Maintains The Flow On Gade Valley Project

ADVERTISEMENT

Located between junctions 20 and 21 of London’s M25, the 450m-long Gade Valley Viaduct carries thousands of commuters as they make their way around the capital’s busy motorway. During planned strengthening works expected to run from November 2019 to December 2021, temporary solutions provider, HAKI, supplied its market-leading scaffolding systems to assure safe access to the Gade Valley project’s programme of works.

Gade Valley Viaduct is a multi-span composite viaduct comprising twin decks; both of which are fashioned from four open top steel girders with an in-situ cast concrete slab. To ensure the viaduct continues to perform at its best, strengthening works were a complete necessity. HAKI worked alongside main contractor, Osborne, on this project, utilising up to 300 tonnes of its materials on this site. HAKI’s Universal system and tube and fitting scaffolding were specified to enable crucial access to strengthening works at the underside of the viaduct, through vast birdcage structures.

Ideal for projects where high-level access is essential, birdcage applications using HAKI are efficient to erect and enable the safe ingress and egress from particularly hazardous areas on an infrastructure site. HAKI’s scaffolding system is also highly robust, meaning it can withstand greater loadings than most comparative solutions.

Furthermore, the simple ‘hook-on’ and spring-lock catch mechanism – unique to HAKI – reduces the risk of component displacement and falling materials, and minimises noise pollution, to protect both workers and wider public from injury. As well as keeping workers safe, the sophisticated system also lowers installation time, meaning works can be executed to strict programmes and deadlines common within the infrastructure industry.

Scaffolding, insulation and asbestos management specialist, Alltask, installed HAKI’s products and praised their sophistication: “As well as delivering on technical support, HAKI crafts products which encompass the essential safety and access requirements set by complex projects. For the Gade Valley Viaduct’s strengthening works, the utilisation of HAKI’s temporary works solutions allowed the project’s high safety and access demands to be made a reality. With the project due for completion at the close of 2021, everything will no doubt run smoothly with the presence of HAKI’s expert solutions.”

SM Newsdesk
SM Newsdeskhttps://www.scaffmag.com
The staff at ScaffMag.com the leading scaffolding site for a digital generation.

Most popular ↑

Contractor injured in fall during Port Kembla scaffold erection

ABC reports that a contractor was injured in a fall during scaffold erection at BlueScope’s Port Kembla steelworks on 29 October. SafeWork NSW inspectors visited the site.

Ibstock issues profit warning as brick demand weakens

Ibstock has reportedly cut production and lowered its earnings expectations after third-quarter brick sales fell short of forecasts.

Four injured in Taiwan market scaffold collapse

Taipei has halted work at the old Beitou market demolition site after a scaffold collapse injured four people. Investigations are continuing.

NIE Networks tenders £4.8m scaffolding framework for power infrastructure

NIE Networks is seeking scaffolding services across Northern Ireland's electricity infrastructure through two lots, with an initial four-year term and extension options.

PHD Access joins £190m Dungeness A decommissioning team

Aureos has named PHD Access as its scaffolding partner for the removal of eight 800-tonne boilers at Dungeness A. The overall programme is worth up to £190m.

Latest news

Mobile scaffold falls three decks on offshore support vessel

Marine Safety Forum reports a three-tier scaffold collapse during repositioning, with seized wheels and no exclusion zone on the deck below.
- Advertisement -
More from

Doka details climbing systems for Burj Binghatti tower

Doka’s project update sets out the climbing and edge-protection systems being used on Burj Binghatti, with a target of 1 floor a week.

PHD Access joins £190m Dungeness A decommissioning team

Aureos has named PHD Access as its scaffolding partner for the removal of eight 800-tonne boilers at Dungeness A. The overall programme is worth up to £190m.

Shield tackles hilltop access challenge in 19-day scaffold build

Shield erected access around the 38-metre Lansdowne Monument in 19 days despite a steep, rutted route that kept vans and lorries away from the hilltop.

Tyne Bridge to close for overhead scaffold deck installation

Advanced scaffolders will work around the clock during an October half-term closure to install a protection deck ahead of main arch restoration in early 2027.
Latest articles