Ad
Saturday, December 13, 2025

PERI and K2 Scaffolding deliver refurbishment project in Belfast

ADVERTISEMENT

PERI, a global leader in scaffolding and formwork technology, teamed up with Northern Ireland-based scaffolding contractor K2 Scaffolding to provide access requirements for a refurbishment project in Belfast. 

The project involved the restoration of the Seamus Heaney Centre, a historic listed building on the outskirts of Belfast City Centre. The Seamus Heaney Centre at Queen’s University is recognised as an international centre of creative and research excellence in the field of literature.

As part of the refurbishment project, K2 Scaffolding was tasked with installing perimeter access to all floors to facilitate roof works and window replacement. 

One of the main challenges during the design and installation of the scaffolding was protecting as much of the façade as possible, including its bay windows, which would determine how and where the scaffolding would be tied into the structure. To address this challenge, PERI’s scaffolding design team proposed a tie layout that reduced the required ties, protecting the façade where possible. 

Cantilever brackets were incorporated to accommodate the bay windows and support the scaffolding deck spanning above. Brackets were also used externally to increase the width of the working platform and provide safer and seamless access to the on-site cabin.

Using the PERI UP scaffolding system was significant in the project’s success. This is the first time that the PERI UP system was used on a project in Northern Ireland, and it marked the start of a long-term partnership between PERI and K2 Scaffolding. 

K2 Scaffolding recently invested £400,000 in the PERI UP scaffolding system, which allowed them to take on larger and more complex projects. The system proved to be intuitive, making it easy for K2 Scaffolding to adapt to it quickly.

The metric grid dimensions of the PERI UP system made it more practical for workers to access the chimney structure. With 25cm increments between the length of the scaffolding decks, scaffolders were able to adapt the arrangement to ensure working platforms were as close to the chimney walls as possible. Similarly, the use of PERI UP UHA spigots allowed flexible ledger-to-ledger connections, which accommodated the chimney’s geometry with no additional fittings required.

The entire build of the scaffolding solution took just five days to erect, with 42 tonnes of PERI UP Flex erected throughout the project. 

Cathal Abram, Contracts Manager for K2 Scaffolding, noted the benefits that the PERI UP system brought to the project, including the time saved and reduced material requirements. 

“The locking and ladder decks were advantageous for both time and safety, saving a significant amount of time as the self-locking feature meant the team didn’t need to tie the decks down during windy weather. These components played a substantial role in the speed of the project, reducing the predicted project time by 50%,” he said.

Overall, the partnership between PERI and K2 Scaffolding on this project successfully met the access requirements for the refurbishment of the Seamus Heaney Centre. The PERI UP system proved to be an intuitive and flexible solution for scaffolding requirements, allowing for faster installation and reduced material requirements. 

The success of this project marks the beginning of a long-term partnership between the two companies, and they look forward to collaborating on future projects.

ADVERTISEMENT

Popular Categories

Latest news

Construction College Midlands partners with AT-PAC to expand system scaffolding training

Construction College Midlands has formed a new partnership with scaffolding manufacturer AT-PAC as part of a wider push to strengthen training provision across the...

New Construction and Scaffolding Academy launched to tackle skills shortages in Northern Ireland

A new Construction and Scaffolding Academy has been launched in Antrim and Newtownabbey to help address growing skills shortages across Northern Ireland’s construction sector....

Brogan Group and Alimak strike global partnership

Brogan Group has formed a new strategic alliance with Alimak Group’s Construction Division, bringing its CAS Common Tower and Atlas gantry systems to a...

CITB announces major funding cuts despite £79m reserves

The Construction Industry Training Board has slashed grants and capped funding from January, citing rising demand but drawing criticism over timing and available reserves. The...

Trapped load drags labourer from scaffold as firms fined £800k

A labourer suffered life-changing injuries after being pulled from scaffolding during an unplanned lifting operation on a London refurbishment project. Two companies have been...

ITP opens new Product Development and Testing Facility at Yorkshire HQ

Yorkshire-based manufacturer ITP Ltd has opened a new Product Development and Testing Facility at its Easingwold headquarters following a major strategic investment. Clive Dickin, Chief...

CISRS reforms face delay as new QAC Chair withdraws

CISRS has reopened its search for a new Chair of the Quality Assurance Committee (QAC) after the organisation confirmed that Professor David Wooff, appointed...

Connolly Scaffolding strengthens partnership with TRAD UK in £3.5m investment

Connolly Scaffolding Ltd has agreed a further £3.5 million investment in TRAD UK’s Plettac Metrix system, reinforcing a partnership that has shaped both businesses...

Benetics introduces AI voice tool to cut site paperwork

A German construction technology firm has launched an AI-powered voice assistant designed to help site teams cut paperwork and speed up reporting. Benetics, based in...

Scaffolders at Sullom Voe Terminal walk out over pay dispute

Around 60 scaffolders, painters, insulators, and supervisors at the Sullom Voe Terminal in the Shetland Islands have staged a 24-hour walkout in an escalating...

Latest news

ADVERTISEMENT

The magazine

Issue 27 | Past issues >>

Popular

Trapped load drags labourer from scaffold as firms fined £800k

A labourer suffered life-changing injuries after being pulled from...

Brogan Group and Alimak strike global partnership

Brogan Group has formed a new strategic alliance with...

CITB announces major funding cuts despite £79m reserves

The Construction Industry Training Board has slashed grants and...

ITP opens new Product Development and Testing Facility at Yorkshire HQ

Yorkshire-based manufacturer ITP Ltd has opened a new Product...

New Construction and Scaffolding Academy launched to tackle skills shortages in Northern Ireland

A new Construction and Scaffolding Academy has been launched...

Related articles

ADVERTISEMENTS

Latest topics

Construction College Midlands partners with AT-PAC to expand system scaffolding training

Construction College Midlands has formed a new partnership with...

New Construction and Scaffolding Academy launched to tackle skills shortages in Northern Ireland

A new Construction and Scaffolding Academy has been launched...

Brogan Group and Alimak strike global partnership

Brogan Group has formed a new strategic alliance with...
ADVERTISEMENTS