South Molton Scaffolding Delivers Complex Temporary Roof Project

ADVERTISEMENT

South Molton Scaffolding Ltd has successfully completed a technically challenging temporary roof and access project at Petroc College in North Devon, overcoming significant logistical and structural hurdles to deliver the scheme ahead of schedule and on budget.

The project involved the design and installation of a fully encapsulated Haki roof system over Block A of the live college site. The work was essential to allow for the safe removal and replacement of defective Reinforced Autoclaved Aerated Concrete (RAAC) within the roof structure.

Operating within a live educational environment brought unique challenges from the outset. The site was small and congested, with tight delivery windows and the requirement to maintain access to surrounding buildings, footpaths, disabled ramps, and occupied ground-floor offices.

South Molton worked closely with the project’s structural engineers and Raptor Scaffold Design & Consultancy to overcome site limitations. Key measures included:

  • Ground investigations to assess load-bearing capacity
  • Installation of compacted hardcore for kentledge
  • Redesign of beam supports due to hollow roof parapets
  • Steel RSJ installation to take the lateral load and tie back to the internal structure

Due to the client’s request to avoid disturbing the metal cladding, traditional drill-in ties were ruled out. Instead, the team adopted a combination of increased kentledge, buttresses, and band-and-plate ties at low level to the surrounding brick walls. This was further reinforced by an internal birdcage scaffold tied back to the external scaffold via opened windows, enhancing overall stability.

Safety, Speed and Sensitivity

A key driver in the project’s success was the use of the Haki system roof, which allowed 80% of the structure to be pre-built at ground level and craned into place. This greatly reduced work-at-height exposure for operatives. UK System Scaffold Hire provided materials and support for the roof system.

The team also installed a Haki staircase to reroute pedestrian traffic, and an integrated drop chute scaffold extension was constructed to accommodate 26-yard skips for demolition debris. All lifting operations were carefully scheduled at weekends to avoid public disruption.

Despite an initial two-week delay caused by design changes, South Molton’s team accelerated works on-site, ultimately completing the job four days ahead of the original 12-week programme.

Recognition for Excellence

The contract was delivered on time, within budget, and even included a number of free-of-charge client extras. Feedback from Pearce Construction and Petroc College’s head of maintenance praised the team’s professionalism, planning, and consideration throughout.

Raptor Scaffold Design, responsible for final sign-off, commented: “Overall, the scaffold has been built to a very high quality and the scaffolders should be commended for the work they have put in.” The site received 100% marks on health and safety inspections, including those conducted by the principal contractor and South Molton’s own external advisors.

Reflecting on the achievement, South Molton Scaffolding’s Director said: “My job is to understand the brief, win the work, and plan it – but it’s the guys on the ground who brought this complex project to life. 

Their professionalism and determination were key to its success.”

The project marks a standout achievement for the Devon-based contractor, showcasing both technical capability and an unwavering commitment to quality.

SM Newsdesk
SM Newsdeskhttps://www.scaffmag.com
The staff at ScaffMag.com the leading scaffolding site for a digital generation.

Most popular ↑

Scaffold firm fined £16,000 after trainee’s fatal fall

HSE found that safe zones had not been established when Michael Swales fell 5 metres from a partially erected scaffold near Ripon.

SAIA names teams for 2027 Scaffold Builders Competition

Manchester-based AK Scaffolding is on the list for Las Vegas, alongside 4 first-time entrants from the US, Lithuania, Switzerland and Canada.

NASC warns on scaffold loads and driver fatigue

NASC highlights load security, fatigue and vehicle checks as a new free Truck Driver Toolkit puts scaffolding transport risks in focus.

Taylor Wimpey scaffolders’ pay dispute moves to strike ballot

Unite says voting in the Sunderland pay dispute opened on 9 November and closes on 23 November. The dispute involves 19 scaffolders and 31 joiners.

Taylor Wimpey opens redundancy talks over local team changes

Taylor Wimpey is consulting staff over local team changes that could lead to redundancies. The number of roles affected has not been disclosed.

Latest news

Tyne Bridge teams hit 70% protection deck target

ISS prepared and delivered more than 200 tonnes of scaffolding as teams completed 70% of the Tyne Bridge protection deck during its ten-day closure.
- Advertisement -
More from

Tyne Bridge teams hit 70% protection deck target

ISS prepared and delivered more than 200 tonnes of scaffolding as teams completed 70% of the Tyne Bridge protection deck during its ten-day closure.

Doka details climbing systems for Burj Binghatti tower

Doka’s project update sets out the climbing and edge-protection systems being used on Burj Binghatti, with a target of 1 floor a week.

PHD Access joins £190m Dungeness A decommissioning team

Aureos has named PHD Access as its scaffolding partner for the removal of eight 800-tonne boilers at Dungeness A. The overall programme is worth up to £190m.

Shield tackles hilltop access challenge in 19-day scaffold build

Shield erected access around the 38-metre Lansdowne Monument in 19 days despite a steep, rutted route that kept vans and lorries away from the hilltop.
Latest articles