Guest design article: How Do Ties Work ?

ADVERTISEMENT

Image5Guest Technical Article By IDH, The Independent Design House

IDH was incorporated in July 2011 and established to provide specialist Scaffold DesignFormwork Design & general Temporary Works Design consultancy serving Sub-Contractors, Main Contractors and Client developers.

How Do Ties Work ?

To stabilise a scaffold we tie it to the adjacent building as the scaffold is erected.  Conventionally this is done by means of an anchor fixing in to the façade and then a tie tube on doubles across both standards and all within 300mm of the ledger / standard interface.  This point being a node (point of NO DE-flection).

Depending on a number of factors such as geographic location, netting, sheeting, height and load we determine in the design process what tie pattern to adopt and the frequency of ties.

Ties however, undertake more than one function. 

Firstly they prevent the scaffold from pulling away from the building – but if this is the case why not fix them at all standards, or for that matter at every 4 standards for instance.

In addition to providing this pull restraint, they also stabilise the scaffold from swaying parallel to the building and contribute to the effective length of the standard in question.

ties

Sway stability parallel to the building is provided by a combination of the tie tube and the face brace.  By installing the correct sway bracing, the outside line is prevented from moving parallel to the building.  By securing the tie tube to the building façade and the outside line we now have a tube which is prevented from movement at both ends.  When the inside line is now secured to this tube (with doubles) the inside line is now also prevented from moving parallel to the building by the bending resistance of this tie tube.  This is why inside lines are not sway braced!

In some designed circumstances it may be a requirement to tie to the inside line only or miss ties altogether.  When these scenarios occur the scaffold should be designed as we no longer have that sway restraint present and alternative measures need to be considered such as plan bracing or V-ties.

For more explanation on this and other technical scaffold design subjects visit the IDH blog: http://www.idh-design.co.uk/blog/

Author: Tim Burt on Google+

Most popular ↑

NASC updates TG30 with new birdcage system scaffold guidance

NASC has updated its TG30 system scaffolding guidance to...

Layher named Best Brand of the Year for 2026

Layher has received the PLUS X AWARD’s Best Brand...

Your complete guide to ScaffChamp 2026 in Vilnius

Everything is now in place for ScaffChamp 2026, the...

The digital foundations behind scaffolding’s next tech shift

NASC and CISRS have completed a comprehensive digital overhaul...

Researchers test two-drone system for autonomous bricklaying

Researchers have demonstrated an autonomous drone system capable of...

Latest news

ADVERTISEMENT
More from
Latest articles

Researchers test two-drone system for autonomous bricklaying

Researchers have demonstrated an autonomous drone system capable of placing bricks and applying adhesive...

NASC updates TG30 with new birdcage system scaffold guidance

NASC has updated its TG30 system scaffolding guidance to include a new range of...

Your complete guide to ScaffChamp 2026 in Vilnius

Everything is now in place for ScaffChamp 2026, the international scaffolding championship that returns...

Layher named Best Brand of the Year for 2026

Layher has received the PLUS X AWARD’s Best Brand of the Year 2026 title...

Scaffolder Conor O’Brien takes on 84km Bali ultra for children’s education

Advanced scaffolder and ultra-endurance runner Conor O’Brien is preparing to run 84km overnight across...

Charity football tournament to honour Wayne Connolly

Connolly Scaffolding is organising a charity football tournament in memory of Wayne Connolly, its...

New Bill proposes ban on retentions in construction contracts

The government is set to introduce a new Bill today that could bring major...

CITB apprenticeship support rises by 43% in latest year

CITB’s New Entrant Support Team helped 5,913 apprentices join the construction industry during the...