Layher passes examination for new student accommodation in Edinburgh

ADVERTISEMENT

The benefits of Layher scaffolding systems – particularly in terms of installation efficiency and the creation of clear walkways – has been clearly demonstrated in Edinburgh. 

Hard Rock Scaffolding Ltd. have made extensive use of the Layher Allround Lightweight system to provide multi-level façade access for main contractors, Graham Construction Ltd. for the new build student accommodation at Westfield Road in the city.

“The facility is designed to provide 396 rooms over seven floors, including ground level, and will be operated by Watkin Jones,” says Robert Hutchison, Graham Construction Project Manager.  “The facility comprises a series of façades, many of which include recesses, so the need for the scaffolding to follow this layout is paramount and is being fully met by the Layher equipment.”

Layher’s stair access systems to all levels are designed into the structure which also benefits from the use of steel decks and toe boards throughout.  Significantly, the wide choice of Layher deck designs has helped to accommodate the precise dimensions of the building, ensuring potential gaps are filled throughout.

Additionally, pedestrian walkways below on two of the adjacent main roads have been created using a combination of protective fans constructed from the Layher deck system and the company’s Protect panels to create a barrier between public access areas and the working site.

“Critically, Layher scaffolding design requires only minimal cross bracing to be installed so we have been able to include virtually clear walkways throughout,” adds George Brown, Contracts Manager at Hard Rock Scaffolding.  “This is of particular note where sizeable components, such as window frames, have to be brought onto the scaffold and then moved to the correct position for fixing.”  

“While our scaffold systems are able to meet the installation needs of a range of structures – from bridges to industrial plants – the benefits offered are always in the spotlight with façade installations,” adds Sean Pike, Layher’s UK Managing Director.

“The installation at Westfield Road in Edinburgh is a prime example and we are delighted that the team at Hard Rock Scaffolding have been able to make full use of our Allround Lightweight system to meet clear access objectives on the project.”

SM Newsdesk
SM Newsdeskhttps://www.scaffmag.com
The staff at ScaffMag.com the leading scaffolding site for a digital generation.

Most popular ↑

Two taken to hospital after Streatham scaffolding collapse

Two people were rescued before firefighters arrived after scaffolding collapsed on Streatham High Road on 25 October. Both were taken to hospital.

Two workers hospitalised after partial collapse at Banbury construction site

Two workers were taken to hospital after a partial collapse at a Banbury construction site on 21 October. HSE says it is making enquiries, according to Construction Enquirer.

Government announces paternity pay for self-employed dads

Self-employed fathers and partners are to receive two weeks of support under government plans, with payments currently worth up to £194 a week.

PHD Access announces €37.7m investment for European expansion

PHD Access has announced a €37.7m investment from MML Ireland and Goodbody to support European growth and acquisitions, subject to regulatory approval.

Belfast scaffolding firm fined after driver killed by falling board

HSENI found inadequate exclusion zone controls after Samuel Magill was struck by a falling metal scaffold board during dismantling work in Belfast.

Latest news

MPs press Government over Sizewell C’s UK supply-chain pledge

MPs want the Government to explain how Sizewell C will meet its 70% UK construction spending target, alongside six-monthly progress reports.
- Advertisement -
More from

Tyne Bridge to close for overhead scaffold deck installation

Advanced scaffolders will work around the clock during an October half-term closure to install a protection deck ahead of main arch restoration in early 2027.

86m Layher scaffold completed at Giotto’s Bell Tower

An 86-metre scaffold erected in just over four months will support a five-year restoration of the Florence landmark while keeping it open to visitors.

Golden Gate Bridge prepares temporary access platforms for seismic works

Night-time lane closures will allow crews to lower access platforms beneath the roadway as work progresses on the bridge’s final seismic retrofit phase.

PERI scaffolding supports major HS2 Birmingham dive-under works

PERI UK has supplied access scaffolding, formwork and engineering support for a 400m-long concrete dive-under being built as part of HS2’s Delta Junction near Birmingham.
Latest articles