HAKI provides a unique weather protection system in Sweden

ADVERTISEMENT

HAKI’s designers have produced new, effective, safe solutions to bridge an unusually wide span in Sweden.

When the Municipality of Gotland commenced its second largest-ever construction project, the XERVON depot and assembly personnel from Örebro provided one of Sweden’s largest weather protection systems – a 4,000 square-metre weather protection system from HAKI, covering what will be the completely new Wisby high school building, the Sävehuset.

The weather protection system, which will be 64 metres long, will be completed in August 2015. It is not only the size of the weather protection system being assembled over the Sävehuset that makes it unique. Instead of attaching the weather protection system and the scaffolding to the building in the usual way, the scaffolding is being attached around the building to specially cast concrete beams in the ground. This keeps the weather protection system and scaffolding stable, and quite separate from the building.

The weather protection system spans 44.5 metres; about 64 metres of the length of the building will be under cover during the summer. Total height to the ridge is about 20 metres, and the structure is cantilevered with double adjacent queen-post trusses, i.e. without any support in the centre. The weather protection system is being built in sections, about 10 metres at a time, and the sections, which can be rolled along, are jointed together in a so-called cap solution, making them weatherproof. This allows efficient demolition and subsequent new building of the outer walls and roof, with protection from weather and wind.

”Together with XERVON we take on some of Sweden’s most challenging weather protection system projects. These need proficient design and construction personnel, the right material, expert assembly personnel and close cooperation. With our joint solutions we contribute to efficient, safe construction workplaces,” says Kjell Sundlin, Sales Manager at HAKI in Sweden.

The Sävehuset is being rebuilt by NCC/Nybergs Entreprenad, and the total budget for the project is SEK 275 million. For XERVON’s eight assembly workers, the project started in May 2015, and it will continue to February 2016, when the walls and roof of the new building will be in place. The new high school will be finished in 2017.

”For XERVON this is yet another prestige project, together with HAKI, on behalf of NCC. Last winter we contributed all the scaffolding and a large weather protection system for the renovation of the Örebro Konserthus. In the Sävehuset project, a completely different design is used to provide weather protection and the required support. In both cases these are very large, quite unique assignments for XERVON’s expert assembly personnel,” said Jens Sjöberg, CEO of XERVON in Sweden.

Most popular ↑

Two workers killed in Spain after mast climbing platform collapse

Two workers have been killed following the collapse of...

Scottish offshore workers urged to consider scaffolding careers

The Construction Industry Training Board is targeting workers from...

Robot named Douglas begins work on Tilbury Douglas site

Tilbury Douglas has begun using a humanoid robot to...

NASC warns members over online conduct in new media policy

The National Access and Scaffolding Confederation said the new...

Latest news

HAKI provides a unique weather protection system in Sweden

ADVERTISEMENT

HAKI’s designers have produced new, effective, safe solutions to bridge an unusually wide span in Sweden.

When the Municipality of Gotland commenced its second largest-ever construction project, the XERVON depot and assembly personnel from Örebro provided one of Sweden’s largest weather protection systems – a 4,000 square-metre weather protection system from HAKI, covering what will be the completely new Wisby high school building, the Sävehuset.

The weather protection system, which will be 64 metres long, will be completed in August 2015. It is not only the size of the weather protection system being assembled over the Sävehuset that makes it unique. Instead of attaching the weather protection system and the scaffolding to the building in the usual way, the scaffolding is being attached around the building to specially cast concrete beams in the ground. This keeps the weather protection system and scaffolding stable, and quite separate from the building.

The weather protection system spans 44.5 metres; about 64 metres of the length of the building will be under cover during the summer. Total height to the ridge is about 20 metres, and the structure is cantilevered with double adjacent queen-post trusses, i.e. without any support in the centre. The weather protection system is being built in sections, about 10 metres at a time, and the sections, which can be rolled along, are jointed together in a so-called cap solution, making them weatherproof. This allows efficient demolition and subsequent new building of the outer walls and roof, with protection from weather and wind.

”Together with XERVON we take on some of Sweden’s most challenging weather protection system projects. These need proficient design and construction personnel, the right material, expert assembly personnel and close cooperation. With our joint solutions we contribute to efficient, safe construction workplaces,” says Kjell Sundlin, Sales Manager at HAKI in Sweden.

The Sävehuset is being rebuilt by NCC/Nybergs Entreprenad, and the total budget for the project is SEK 275 million. For XERVON’s eight assembly workers, the project started in May 2015, and it will continue to February 2016, when the walls and roof of the new building will be in place. The new high school will be finished in 2017.

”For XERVON this is yet another prestige project, together with HAKI, on behalf of NCC. Last winter we contributed all the scaffolding and a large weather protection system for the renovation of the Örebro Konserthus. In the Sävehuset project, a completely different design is used to provide weather protection and the required support. In both cases these are very large, quite unique assignments for XERVON’s expert assembly personnel,” said Jens Sjöberg, CEO of XERVON in Sweden.

Popular Categories

Latest posts

Scaffolding firms urged to review RIDDOR procedures as HSE consults on changes

The Health and Safety Executive has launched a consultation on proposed changes to the Reporting of Injuries, Diseases and Dangerous Occurrences Regulations 2013, known...

Scottish offshore workers urged to consider scaffolding careers

The Construction Industry Training Board is targeting workers from Scotland’s offshore energy sector as part of efforts to widen the construction talent pool and...

NASC warns members over online conduct in new media policy

The National Access and Scaffolding Confederation said the new Social Media and General Media Policy sets expectations for how its members, CISRS centres and...

Two workers killed in Spain after mast climbing platform collapse

Two workers have been killed following the collapse of a twin mast climbing work platform in Benidorm, Spain. The incident happened on Wednesday, 22 April,...

Brogan wins Manchester student accommodation access package

Brogan Group has secured the powered access package for a student accommodation building in Manchester. The access specialist will provide several passenger and goods hoists...

‘Not every scaffolder is ok’: Alan Osborn backs mental health campaign at ScaffChamp

Alan Osborn is set to shave his head at ScaffChamp 2026 as part of a campaign to raise £5,000 for men’s mental health and...

Baton opens early adopter programme for scaffolding contractors

Baton has opened applications for its Early Adopter Programme, giving scaffolding contractors early access to a software platform designed specifically for construction subcontractors. The company...

SCA joins Coriant in move to widen access and industrial services capability

Coriant has announced the acquisition of specialist contractor SCA, in a move that further expands the group’s capabilities in access, temporary containment and industrial...

Robot named Douglas begins work on Tilbury Douglas site

Tilbury Douglas has begun using a humanoid robot to carry out administrative and data-collection tasks on a live construction site. The contractor says the...

HAKI reports sharp UK sales drop as construction starts stall

The Swedish-listed scaffolding and access safety group said UK revenues fell to SEK 52 million (£4.2 million) in the three months to 31 March,...

Spring Issue #29 | Past issues >>

Latest topics

Most popular ⚡︎

Two workers killed in Spain after mast climbing platform collapse

Two workers have been killed following the collapse of...

Scottish offshore workers urged to consider scaffolding careers

The Construction Industry Training Board is targeting workers from...

Robot named Douglas begins work on Tilbury Douglas site

Tilbury Douglas has begun using a humanoid robot to...

NASC warns members over online conduct in new media policy

The National Access and Scaffolding Confederation said the new...

Related articles

ADVERTISEMENTS
More from
Latest articles

TRAD UK launches charity campaign supporting Epilepsy Action

TRAD UK has launched a new fundraising campaign in support of Epilepsy Action, the...

Scaffolding firms urged to review RIDDOR procedures as HSE consults on changes

The Health and Safety Executive has launched a consultation on proposed changes to the...

Scottish offshore workers urged to consider scaffolding careers

The Construction Industry Training Board is targeting workers from Scotland’s offshore energy sector as...

NASC warns members over online conduct in new media policy

The National Access and Scaffolding Confederation said the new Social Media and General Media...

Two workers killed in Spain after mast climbing platform collapse

Two workers have been killed following the collapse of a twin mast climbing work...

Brogan wins Manchester student accommodation access package

Brogan Group has secured the powered access package for a student accommodation building in...