Harsco Helps To Hold Back The Water At A Jersey Dam

ADVERTISEMENT

 

A project to refurbish a dam on the island of Jersey has highlighted the bespoke nature of the access equipment solutions which Harsco Infrastructure provides for its customers.

Harsco designed and installed a unique combination of suspended access platforms and a load bearing support gantry system (constructed from MkII shoring soldiers and scaffolding materials) to provide access to the entire inside face of the dam so that vital maintenance work could be completed.

First constructed in 1962, the Val de la Mare dam holds back 900 million litres of water, making it the second largest reservoir on the island. The concrete on the dam is suffering from an alkali aggregate reaction and this created the need for the inside face to be covered with a heavy-duty waterproof membrane to re-seal the dam. This will prolong the life of the dam for many years, but required the reservoir to be drained so that the inside face could be accessed.

“This was a very unusual and difficult project which is why a totally bespoke solution was required,” comments Harsco Project Manager Jon Herbert. “It is the first time the reservoir has ever been partially drained and the project had a very tight schedule as the reservoir needed to be refilled as soon as possible.

“The fact that the trades were working at height, and also above water, made this a very complex project. Access to the façade had to be from the walkway on top of the dam wall which was very narrow. This had to remain clear throughout the project to allow the waterproof membrane to be positioned and unrolled down the inner façade. This was achieved by designing a walk-though, ‘tunnel-like’ support structure from scaffolding and shoring MkII Soldier materials.”

Five suspended access cradles were suspended from the load bearing framework and four were fitted with motorised bogies which allowed them to traverse along the façade as well as up and down. This was made possible by a steel support track supported on the underside of the load-bearing framework structure. The fifth suspended access platform was a specially designed and fabricated horse-shoe shaped machine that provided access to the pump tower. This platform was specially designed with six separate winching units which were also supported by the load bearing framework structure. This arrangement of access platforms and egress to the top of the dam’s façade allowed both the team of membrane installers and concrete repair specialists complete access to the façade.

“It was a terrific piece of teamwork to get this project up and running,” comments Project Manager Nathan Clothier, of civil engineering contractor Jayen Ltd which was responsible for the refurbishment work. “We needed a real bespoke access solution to solve a difficult set of requirements. Harsco’s response was really well thought through and they were even able to build a test section of the support gantry for the project team to evaluate prior to work commencing. The schedule on this job was particularly tight so the access system had to be really effective and I’m happy to say that the suspended access platforms worked very well.”

Via: Press Release 

 

Most popular ↑

Wayne Connolly honoured as NASC opens 2026 awards entries

NASC has opened entries for the 2026 Scaffolding Excellence...

CISRS Accreditation Granted For Safety & Access Indian Training Center

  CISRS has awarded Safety & Access Ltd full overseas...

The Scaffolding Association adds free seminar on Scaffolding Ties to roadshow

Due to recent scaffold collapses from around the UK,...

GKR scaffolders help save woman’s life at London project

A GKR Scaffolding site team has been praised after...

TRAD UK launches charity campaign supporting Epilepsy Action

TRAD UK has launched a new fundraising campaign in...

Latest news

Harsco Helps To Hold Back The Water At A Jersey Dam

ADVERTISEMENT

 

A project to refurbish a dam on the island of Jersey has highlighted the bespoke nature of the access equipment solutions which Harsco Infrastructure provides for its customers.

Harsco designed and installed a unique combination of suspended access platforms and a load bearing support gantry system (constructed from MkII shoring soldiers and scaffolding materials) to provide access to the entire inside face of the dam so that vital maintenance work could be completed.

First constructed in 1962, the Val de la Mare dam holds back 900 million litres of water, making it the second largest reservoir on the island. The concrete on the dam is suffering from an alkali aggregate reaction and this created the need for the inside face to be covered with a heavy-duty waterproof membrane to re-seal the dam. This will prolong the life of the dam for many years, but required the reservoir to be drained so that the inside face could be accessed.

“This was a very unusual and difficult project which is why a totally bespoke solution was required,” comments Harsco Project Manager Jon Herbert. “It is the first time the reservoir has ever been partially drained and the project had a very tight schedule as the reservoir needed to be refilled as soon as possible.

“The fact that the trades were working at height, and also above water, made this a very complex project. Access to the façade had to be from the walkway on top of the dam wall which was very narrow. This had to remain clear throughout the project to allow the waterproof membrane to be positioned and unrolled down the inner façade. This was achieved by designing a walk-though, ‘tunnel-like’ support structure from scaffolding and shoring MkII Soldier materials.”

Five suspended access cradles were suspended from the load bearing framework and four were fitted with motorised bogies which allowed them to traverse along the façade as well as up and down. This was made possible by a steel support track supported on the underside of the load-bearing framework structure. The fifth suspended access platform was a specially designed and fabricated horse-shoe shaped machine that provided access to the pump tower. This platform was specially designed with six separate winching units which were also supported by the load bearing framework structure. This arrangement of access platforms and egress to the top of the dam’s façade allowed both the team of membrane installers and concrete repair specialists complete access to the façade.

“It was a terrific piece of teamwork to get this project up and running,” comments Project Manager Nathan Clothier, of civil engineering contractor Jayen Ltd which was responsible for the refurbishment work. “We needed a real bespoke access solution to solve a difficult set of requirements. Harsco’s response was really well thought through and they were even able to build a test section of the support gantry for the project team to evaluate prior to work commencing. The schedule on this job was particularly tight so the access system had to be really effective and I’m happy to say that the suspended access platforms worked very well.”

Via: Press Release 

 

Popular Categories

Latest posts

Staht signs US distribution deal for digital pull testing range

UK digital pull testing manufacturer Staht has appointed Diversified Fall Protection as its exclusive distributor in the United States. The agreement will see Diversified market,...

GKR scaffolders help save woman’s life at London project

A GKR Scaffolding site team has been praised after helping to save the life of a woman who collapsed outside a live London project. The...

King’s Award recognises Lee Marley Group’s training work

Lee Marley Group has received a King’s Award for Enterprise in recognition of its work to widen access to careers in construction. The large-scale construction...

Mock the Week star to host ScaffEx26 awards night

Comedian and television presenter Dara Ó Briain has been confirmed as the host of this year’s Scaffolding Excellence Awards. The awards evening will take place...

Wayne Connolly honoured as NASC opens 2026 awards entries

NASC has opened entries for the 2026 Scaffolding Excellence Awards, with this year’s apprentice category renamed in memory of former NASC president and CISRS...

TRAD UK launches charity campaign supporting Epilepsy Action

TRAD UK has launched a new fundraising campaign in support of Epilepsy Action, the national charity helping people and families affected by epilepsy. The 2026-27...

Scaffolding firms urged to review RIDDOR procedures as HSE consults on changes

The Health and Safety Executive has launched a consultation on proposed changes to the Reporting of Injuries, Diseases and Dangerous Occurrences Regulations 2013, known...

Scottish offshore workers urged to consider scaffolding careers

The Construction Industry Training Board is targeting workers from Scotland’s offshore energy sector as part of efforts to widen the construction talent pool and...

NASC warns members over online conduct in new media policy

The National Access and Scaffolding Confederation said the new Social Media and General Media Policy sets expectations for how its members, CISRS centres and...

Two workers killed in Spain after mast climbing platform collapse

Two workers have been killed following the collapse of a twin mast climbing work platform in Benidorm, Spain. The incident happened on Wednesday, 22 April,...

Spring Issue #29 | Past issues >>

Latest topics

Most popular ⚡︎

Wayne Connolly honoured as NASC opens 2026 awards entries

NASC has opened entries for the 2026 Scaffolding Excellence...

CISRS Accreditation Granted For Safety & Access Indian Training Center

  CISRS has awarded Safety & Access Ltd full overseas...

The Scaffolding Association adds free seminar on Scaffolding Ties to roadshow

Due to recent scaffold collapses from around the UK,...

GKR scaffolders help save woman’s life at London project

A GKR Scaffolding site team has been praised after...

TRAD UK launches charity campaign supporting Epilepsy Action

TRAD UK has launched a new fundraising campaign in...

Related articles

ADVERTISEMENTS
More from
Latest articles

HAKI CEO Sverker Lindberg to step down by 2027

HAKI Safety has confirmed that its President and CEO, Sverker Lindberg, will leave his...

Staht signs US distribution deal for digital pull testing range

UK digital pull testing manufacturer Staht has appointed Diversified Fall Protection as its exclusive...

GKR scaffolders help save woman’s life at London project

A GKR Scaffolding site team has been praised after helping to save the life...

King’s Award recognises Lee Marley Group’s training work

Lee Marley Group has received a King’s Award for Enterprise in recognition of its...

Mock the Week star to host ScaffEx26 awards night

Comedian and television presenter Dara Ó Briain has been confirmed as the host of...

Wayne Connolly honoured as NASC opens 2026 awards entries

NASC has opened entries for the 2026 Scaffolding Excellence Awards, with this year’s apprentice...