Harsco Helps To Hold Back The Water At A Jersey Dam

ADVERTISEMENT

 

A project to refurbish a dam on the island of Jersey has highlighted the bespoke nature of the access equipment solutions which Harsco Infrastructure provides for its customers.

Harsco designed and installed a unique combination of suspended access platforms and a load bearing support gantry system (constructed from MkII shoring soldiers and scaffolding materials) to provide access to the entire inside face of the dam so that vital maintenance work could be completed.

First constructed in 1962, the Val de la Mare dam holds back 900 million litres of water, making it the second largest reservoir on the island. The concrete on the dam is suffering from an alkali aggregate reaction and this created the need for the inside face to be covered with a heavy-duty waterproof membrane to re-seal the dam. This will prolong the life of the dam for many years, but required the reservoir to be drained so that the inside face could be accessed.

“This was a very unusual and difficult project which is why a totally bespoke solution was required,” comments Harsco Project Manager Jon Herbert. “It is the first time the reservoir has ever been partially drained and the project had a very tight schedule as the reservoir needed to be refilled as soon as possible.

“The fact that the trades were working at height, and also above water, made this a very complex project. Access to the façade had to be from the walkway on top of the dam wall which was very narrow. This had to remain clear throughout the project to allow the waterproof membrane to be positioned and unrolled down the inner façade. This was achieved by designing a walk-though, ‘tunnel-like’ support structure from scaffolding and shoring MkII Soldier materials.”

Five suspended access cradles were suspended from the load bearing framework and four were fitted with motorised bogies which allowed them to traverse along the façade as well as up and down. This was made possible by a steel support track supported on the underside of the load-bearing framework structure. The fifth suspended access platform was a specially designed and fabricated horse-shoe shaped machine that provided access to the pump tower. This platform was specially designed with six separate winching units which were also supported by the load bearing framework structure. This arrangement of access platforms and egress to the top of the dam’s façade allowed both the team of membrane installers and concrete repair specialists complete access to the façade.

“It was a terrific piece of teamwork to get this project up and running,” comments Project Manager Nathan Clothier, of civil engineering contractor Jayen Ltd which was responsible for the refurbishment work. “We needed a real bespoke access solution to solve a difficult set of requirements. Harsco’s response was really well thought through and they were even able to build a test section of the support gantry for the project team to evaluate prior to work commencing. The schedule on this job was particularly tight so the access system had to be really effective and I’m happy to say that the suspended access platforms worked very well.”

Via: Press Release 

 

Most popular ↑

Scaffolder ‘lucky to be alive’ after CCTV captures skylight fall

CCTV footage showing the moment a scaffolder fell through...

Nearly 80% of scaffold sites fail safety checks in German state

Authorities in the German state of Hesse have launched...

Layher UK brings open morning series to Livingston

Layher UK is bringing its regional open morning series...

NASC safety report shows zero member fatalities as workforce passes 20,000

NASC contractor members recorded zero operative fatalities in 2025,...

UK construction starts tipped to rise after difficult start to 2026

UK construction activity is expected to recover from 2027...

Latest news

ADVERTISEMENT
More from
Latest articles

UK construction will need 41,200 extra workers a year, CITB warns

The UK construction industry will need an average of 41,200 extra workers each year...

Tickets go on sale for 2026 Scaffolding Excellence Awards

Tickets and tables for the 2026 Scaffolding Excellence Awards are now on sale, with...

UK construction starts tipped to rise after difficult start to 2026

UK construction activity is expected to recover from 2027 after a difficult start to...

Scaffolding takes centre stage at Arc Project’s 24-hour warehouse race

Midland Scaffolding Services has helped deliver an unusual event project after building a 270...

Layher UK brings open morning series to Livingston

Layher UK is bringing its regional open morning series to Scotland later this month,...

Scaffolder ‘lucky to be alive’ after CCTV captures skylight fall

CCTV footage showing the moment a scaffolder fell through a warehouse roof skylight has...

NASC safety report shows zero member fatalities as workforce passes 20,000

NASC contractor members recorded zero operative fatalities in 2025, according to the organisation’s latest...

ScaffChamp future under review after successful Vilnius event

The future location of ScaffChamp is unclear after key figures behind the international scaffolding...