Harsco Is Hard At Work On Bridge Bearing Replacement Project

ADVERTISEMENT

 

Harsco Infrastructure has revealed details of a £710,000 contract to provide a comprehensive access solution for a major refurbishment project being carried out on the famous Forth Road Bridge in Scotland.

Harsco’s bespoke scaffolding solution is allowing work to be carried out to replace the large bearings which support each end of the structure, with no disruption to traffic using the bridge.

Harsco was selected for this contract by Balfour Beatty, on the basis of its competitive tendering and the fact that the two companies have worked together on a large number of previous successful projects.

“Despite its size we wanted to ensure we did not over complicate the project” comments Harsco Sales Director, Tony Knight. “Although we frequently design and produce new products to satisfy individual project requirements, this contract demonstrates our ability to design and construct a bespoke solution for a complex project, primarily using standard products from our range.”

The bridge spans the Firth of Forth and connects Edinburgh with Fife. While its centre section is suspended from cables, the approach sections which link this to either side of the Firth rest on large bearings that sit on top of concrete piers. These bearings allow the approach decks to move in response to traffic loading and temperature changes, and it is these that are being replaced.

“This involves the workforce having access to some of the more remote areas of the bridge structure and so our aim was to create a solution which would provide this, whilst still ensuring complete safety,” adds Tony Knight.

The project is expected to be complete in the summer of 2012.

 

Most popular ↑

New Bill proposes ban on retentions in construction contracts

The government is set to introduce a new Bill...

Charity football tournament to honour Wayne Connolly

Connolly Scaffolding is organising a charity football tournament in...

CITB apprenticeship support rises by 43% in latest year

CITB’s New Entrant Support Team helped 5,913 apprentices join...

Global access sector marks first industry awareness day

The scaffolding and access industry is today marking the...

Scaffolder Conor O’Brien takes on 84km Bali ultra for children’s education

Advanced scaffolder and ultra-endurance runner Conor O’Brien is preparing...

Latest news

ADVERTISEMENT
More from
Latest articles

Scaffolder Conor O’Brien takes on 84km Bali ultra for children’s education

Advanced scaffolder and ultra-endurance runner Conor O’Brien is preparing to run 84km overnight across...

Charity football tournament to honour Wayne Connolly

Connolly Scaffolding is organising a charity football tournament in memory of Wayne Connolly, its...

New Bill proposes ban on retentions in construction contracts

The government is set to introduce a new Bill today that could bring major...

CITB apprenticeship support rises by 43% in latest year

CITB’s New Entrant Support Team helped 5,913 apprentices join the construction industry during the...

CSCS Smart Check upgrade to improve workforce skills data

CSCS has upgraded its Smart Check platform to collect more detailed data from construction...

Scaffolder running length of Britain for children’s cancer charity

A Portsmouth scaffolder has begun an 860-mile charity run from John O’Groats to Land’s...

Global access sector marks first industry awareness day

The scaffolding and access industry is today marking the first International Scaffolding and Access...

Trade earnings lag inflation as site activity slows

Average weekly earnings for self-employed construction trades rose by just 2.3% year on year...