Demanding Project Highlights Harsco’s Customer Service Abilities

ADVERTISEMENT

H145 Uppingham College

A college refurbishment project in Rutland has thrown the spotlight onto the outstanding levels of customer service for which Harsco Infrastructure is widely recognised, and earned the company high praise from its client.

Despite the presence of asbestos and the need for frequent changes during the life of the project, Harsco was able to provide a CUPLOK® scaffolding system which allowed the windows at Uppingham Community College to be replaced in-line with an extremely demanding schedule.

“This was certainly a project which provided its fair share of difficulties, but the Erection and Dismantle team at our Birmingham branch in Tamworth was more than equal to the challenge“ explains Harsco’s Branch Manager Steve Bollans. “The scaffolding system itself was straightforward enough, but there were many other factors which made the job difficult.”

These included the fact that the school was live during the project, which required Harsco to schedule all deliveries to site outside of school hours. Limited road access also meant that delivery vehicles were halted some 70 yards away from the school. The Harsco equipment was then unloaded and transferred to site, past an adjacent nursery school, using lorry-mounted forklift trucks.

“We could only do this when there were no children in the nursery,” adds Steve. “Similarly, when we were installing the scaffolding we had to stop work every time pupils from the main school came outside at break times”  Despite this, and the fact that the decision was taken part way through to extend the project to cover the school’s second storey windows, Harsco was able to help the project meet its very demanding 10-week schedule.

“From the outset the Harsco team were extremely professional, pro-active and advisory, managing an extremely short mobilisation period with ease,” says Chris Cuthbert, Project Manager for the main contractor, Kier. “We had regular site meetings to make sure any design changes were dealt with in a timely fashion. Unfortunately one of the three main sub-contractors under-performed drastically which put a lot of pressure on the Harsco team due to late changes. With this in mind, and with the Harsco people being so pro-active and reactive, the project finished on time. Without this support I’m sure the project would have overrun.”

The fact that asbestos was being removed from the building as the windows were replaced meant that Harsco’s scaffolding design had to allow the proper protective sheeting to be installed all round the areas which were being worked on. This also involved Harsco being asked to make frequent changes to the scaffolding as the project progressed, and often at a moment’s notice.

CUPLOK®

cuplok

Harsco’s CUPLOK® is a multi-purpose steel scaffold system which is ideal for general access, shoring and vertical load support duties. A unique node point design allows up to four components to be connected in one fastening action, making CUPLOK® quick and simple to erect and strike. The fully galvanised, high grade tube is 20% lighter than conventional alternatives, has high resistance to damage and is compatible with up to 3 kN/m² platform loadings, making it strong enough for use in the most demanding applications.

 

Most popular ↑

Wayne Connolly honoured as NASC opens 2026 awards entries

NASC has opened entries for the 2026 Scaffolding Excellence...

CISRS Accreditation Granted For Safety & Access Indian Training Center

  CISRS has awarded Safety & Access Ltd full overseas...

The Scaffolding Association adds free seminar on Scaffolding Ties to roadshow

Due to recent scaffold collapses from around the UK,...

Scottish offshore workers urged to consider scaffolding careers

The Construction Industry Training Board is targeting workers from...

NASC warns members over online conduct in new media policy

The National Access and Scaffolding Confederation said the new...

Latest news

Demanding Project Highlights Harsco’s Customer Service Abilities

ADVERTISEMENT

H145 Uppingham College

A college refurbishment project in Rutland has thrown the spotlight onto the outstanding levels of customer service for which Harsco Infrastructure is widely recognised, and earned the company high praise from its client.

Despite the presence of asbestos and the need for frequent changes during the life of the project, Harsco was able to provide a CUPLOK® scaffolding system which allowed the windows at Uppingham Community College to be replaced in-line with an extremely demanding schedule.

“This was certainly a project which provided its fair share of difficulties, but the Erection and Dismantle team at our Birmingham branch in Tamworth was more than equal to the challenge“ explains Harsco’s Branch Manager Steve Bollans. “The scaffolding system itself was straightforward enough, but there were many other factors which made the job difficult.”

These included the fact that the school was live during the project, which required Harsco to schedule all deliveries to site outside of school hours. Limited road access also meant that delivery vehicles were halted some 70 yards away from the school. The Harsco equipment was then unloaded and transferred to site, past an adjacent nursery school, using lorry-mounted forklift trucks.

“We could only do this when there were no children in the nursery,” adds Steve. “Similarly, when we were installing the scaffolding we had to stop work every time pupils from the main school came outside at break times”  Despite this, and the fact that the decision was taken part way through to extend the project to cover the school’s second storey windows, Harsco was able to help the project meet its very demanding 10-week schedule.

“From the outset the Harsco team were extremely professional, pro-active and advisory, managing an extremely short mobilisation period with ease,” says Chris Cuthbert, Project Manager for the main contractor, Kier. “We had regular site meetings to make sure any design changes were dealt with in a timely fashion. Unfortunately one of the three main sub-contractors under-performed drastically which put a lot of pressure on the Harsco team due to late changes. With this in mind, and with the Harsco people being so pro-active and reactive, the project finished on time. Without this support I’m sure the project would have overrun.”

The fact that asbestos was being removed from the building as the windows were replaced meant that Harsco’s scaffolding design had to allow the proper protective sheeting to be installed all round the areas which were being worked on. This also involved Harsco being asked to make frequent changes to the scaffolding as the project progressed, and often at a moment’s notice.

CUPLOK®

cuplok

Harsco’s CUPLOK® is a multi-purpose steel scaffold system which is ideal for general access, shoring and vertical load support duties. A unique node point design allows up to four components to be connected in one fastening action, making CUPLOK® quick and simple to erect and strike. The fully galvanised, high grade tube is 20% lighter than conventional alternatives, has high resistance to damage and is compatible with up to 3 kN/m² platform loadings, making it strong enough for use in the most demanding applications.

 

Popular Categories

Latest posts

GKR scaffolders help save woman’s life at London project

A GKR Scaffolding site team has been praised after helping to save the life of a woman who collapsed outside a live London project. The...

King’s Award recognises Lee Marley Group’s training work

Lee Marley Group has received a King’s Award for Enterprise in recognition of its work to widen access to careers in construction. The large-scale construction...

Mock the Week star to host ScaffEx26 awards night

Comedian and television presenter Dara Ó Briain has been confirmed as the host of this year’s Scaffolding Excellence Awards. The awards evening will take place...

Wayne Connolly honoured as NASC opens 2026 awards entries

NASC has opened entries for the 2026 Scaffolding Excellence Awards, with this year’s apprentice category renamed in memory of former NASC president and CISRS...

TRAD UK launches charity campaign supporting Epilepsy Action

TRAD UK has launched a new fundraising campaign in support of Epilepsy Action, the national charity helping people and families affected by epilepsy. The 2026-27...

Scaffolding firms urged to review RIDDOR procedures as HSE consults on changes

The Health and Safety Executive has launched a consultation on proposed changes to the Reporting of Injuries, Diseases and Dangerous Occurrences Regulations 2013, known...

Scottish offshore workers urged to consider scaffolding careers

The Construction Industry Training Board is targeting workers from Scotland’s offshore energy sector as part of efforts to widen the construction talent pool and...

NASC warns members over online conduct in new media policy

The National Access and Scaffolding Confederation said the new Social Media and General Media Policy sets expectations for how its members, CISRS centres and...

Two workers killed in Spain after mast climbing platform collapse

Two workers have been killed following the collapse of a twin mast climbing work platform in Benidorm, Spain. The incident happened on Wednesday, 22 April,...

Brogan wins Manchester student accommodation access package

Brogan Group has secured the powered access package for a student accommodation building in Manchester. The access specialist will provide several passenger and goods hoists...

Spring Issue #29 | Past issues >>

Latest topics

Most popular ⚡︎

Wayne Connolly honoured as NASC opens 2026 awards entries

NASC has opened entries for the 2026 Scaffolding Excellence...

CISRS Accreditation Granted For Safety & Access Indian Training Center

  CISRS has awarded Safety & Access Ltd full overseas...

The Scaffolding Association adds free seminar on Scaffolding Ties to roadshow

Due to recent scaffold collapses from around the UK,...

Scottish offshore workers urged to consider scaffolding careers

The Construction Industry Training Board is targeting workers from...

NASC warns members over online conduct in new media policy

The National Access and Scaffolding Confederation said the new...

Related articles

ADVERTISEMENTS
More from
Latest articles

Staht signs US distribution deal for digital pull testing range

UK digital pull testing manufacturer Staht has appointed Diversified Fall Protection as its exclusive...

GKR scaffolders help save woman’s life at London project

A GKR Scaffolding site team has been praised after helping to save the life...

King’s Award recognises Lee Marley Group’s training work

Lee Marley Group has received a King’s Award for Enterprise in recognition of its...

Mock the Week star to host ScaffEx26 awards night

Comedian and television presenter Dara Ó Briain has been confirmed as the host of...

Wayne Connolly honoured as NASC opens 2026 awards entries

NASC has opened entries for the 2026 Scaffolding Excellence Awards, with this year’s apprentice...

TRAD UK launches charity campaign supporting Epilepsy Action

TRAD UK has launched a new fundraising campaign in support of Epilepsy Action, the...