George Roberts at Betley Court Manor

ADVERTISEMENT

Betley Court Manor House was a residential home, where 20 people lived. As the house was completely unsafe after a fire broke out, the project needed to be restored quickly and safely.

To restore the beloved grade II listed 18th-century manor house, scaffolders needed to protect the whole area from the elements, allowing the building to dry out after being drenched by 40 firefighters. Once dried, the building needed ongoing protection to allow the restoration work to be carried out unhindered. George Roberts was engaged to supply all scaffolding, access, and weather protection equipment to this important project.

Space on site was limited, meaning George Roberts drivers had to Hiab the equipment onto ground level, and to minimise impact on those who reside around the building, careful planning was required to maximise the delivery schedule.

Working closely with its customer and their design team to specify the 1.3m X Beams for the support structure, George Roberts provided full and open technical data during the design process. This helped them to act quickly and mobilise equipment to support our customer’s programme and budget.

Challenges

As the building had been completely destroyed by the fire, serious care had to be taken in order for the job to be undertaken safely. Consideration for the historical elements of the building also had to be a priority, as with any listed building restoration.

One of the complexities of the project was to design the temporary roof structure around the numerous chimneys where extra beam work was required to support the roof. The best solution for this was utilising its 1.3m deep X Beams.

George Roberts Ltd provided a full UBIX roof system and the Aluminium X Beams in both 750mm and 1300mm deep for the additional support to enable the whole structure to be covered for restoration to begin.

Stats:

  • A full UBIX Roof using 750mm X Beams, 450mm Deep Beams, 1300mm X Beams, Uniscaff StairtowersTubeFittings and Boards.
  • Our high stock holding with beams being manufactured in the UK meant we were able to react quickly and mobilise the equipment within 7 days, allowing MD to stay on track with their tight programme.
  • Scaffold Package is £600k. Overall project estimated to be appx £6m.

More here: https://georgeroberts.com/case-study/temporary-roof-project-at-betley-court-manor/

ADVERTISEMENT

Popular Categories

Latest news

Budget blowback: will tax hikes deepen construction downturn?

Construction supply chain firms are warning that potential tax increases in next week's Autumn Budget could derail the sector's fragile recovery, with material costs...

Scaffolding Association Australia expands leadership team

The Scaffolding Association Australia has appointed two non-executive board members and expanded the role of an existing director as the organisation strengthens its governance...

North Sea worker dies after incident on Valaris 121 rig

A 32-year-old worker has died following an incident on an offshore drilling rig in the North Sea. Police Scotland and the Health and Safety...

CMA approval clears the way for major HSS ProService and Speedy Hire partnership

A major shift in the UK equipment hire market has moved forward after the Competition and Markets Authority approved a new commercial agreement between...

Australia’s top scaffolding projects recognised at 2025 industry awards

Australia’s top scaffolding projects have been named at this year’s Australia’s Best Scaffolding Projects Awards. The event, held during Scaff25, drew a record thirty...

In Pictures: GKR completes major temporary roof structure at HS2 Euston

GKR Scaffolding has completed a large temporary roof structure at HS2’s Euston site. The installation sits beside the live station and supports enclosed works...

UK Construction output edges up just 0.1% in the third quarter

Construction output in Great Britain rose by only 0.1% in the third quarter of 2025, according to new figures from the Office for National...

Hong Kong launches construction safety drive after serious incidents

Hong Kong has begun a city-wide crackdown on unsafe practices in the construction sector after a series of fatal and serious accidents. The Labour Department...

4D Structures and PERI UK join forces to build one of Glasgow’s tallest towers

A 21-storey student accommodation building is rising on the banks of the River Clyde, as specialist contractor 4D Structures partners with PERI UK on...

ScaffPlan launches 3D scaffold design tool within SketchUp

ScaffPlan has unveiled a new tool that lets scaffolders design and plan scaffolding projects directly in the popular 3D modelling platform SketchUp. The software, called...

Latest news

ADVERTISEMENT

The magazine

Issue 27 | Past issues >>

Popular

North Sea worker dies after incident on Valaris 121 rig

A 32-year-old worker has died following an incident on...

In Pictures: GKR completes major temporary roof structure at HS2 Euston

GKR Scaffolding has completed a large temporary roof structure...

Australia’s top scaffolding projects recognised at 2025 industry awards

Australia’s top scaffolding projects have been named at this...

UK Construction output edges up just 0.1% in the third quarter

Construction output in Great Britain rose by only 0.1%...

CMA approval clears the way for major HSS ProService and Speedy Hire partnership

A major shift in the UK equipment hire market...

Related articles

SIMIAN marks 20-year milestone in construction safety training

Leading construction and scaffolding safety specialist SIMIAN has marked 20 years of trading since its establishment in November 2005. The Warrington-based organisation has grown from a small team of industry experts to become one...
ADVERTISEMENTS

Latest topics

SIMIAN marks 20-year milestone in construction safety training

Leading construction and scaffolding safety specialist SIMIAN has marked...

Budget blowback: will tax hikes deepen construction downturn?

Construction supply chain firms are warning that potential tax...

Scaffolding Association Australia expands leadership team

The Scaffolding Association Australia has appointed two non-executive board...

North Sea worker dies after incident on Valaris 121 rig

A 32-year-old worker has died following an incident on...
ADVERTISEMENTS