George Roberts at Betley Court Manor

ADVERTISEMENT

Betley Court Manor House was a residential home, where 20 people lived. As the house was completely unsafe after a fire broke out, the project needed to be restored quickly and safely.

To restore the beloved grade II listed 18th-century manor house, scaffolders needed to protect the whole area from the elements, allowing the building to dry out after being drenched by 40 firefighters. Once dried, the building needed ongoing protection to allow the restoration work to be carried out unhindered. George Roberts was engaged to supply all scaffolding, access, and weather protection equipment to this important project.

Space on site was limited, meaning George Roberts drivers had to Hiab the equipment onto ground level, and to minimise impact on those who reside around the building, careful planning was required to maximise the delivery schedule.

Working closely with its customer and their design team to specify the 1.3m X Beams for the support structure, George Roberts provided full and open technical data during the design process. This helped them to act quickly and mobilise equipment to support our customer’s programme and budget.

Challenges

As the building had been completely destroyed by the fire, serious care had to be taken in order for the job to be undertaken safely. Consideration for the historical elements of the building also had to be a priority, as with any listed building restoration.

One of the complexities of the project was to design the temporary roof structure around the numerous chimneys where extra beam work was required to support the roof. The best solution for this was utilising its 1.3m deep X Beams.

George Roberts Ltd provided a full UBIX roof system and the Aluminium X Beams in both 750mm and 1300mm deep for the additional support to enable the whole structure to be covered for restoration to begin.

Stats:

  • A full UBIX Roof using 750mm X Beams, 450mm Deep Beams, 1300mm X Beams, Uniscaff Stairtowers, Tube, Fittings and Boards.
  • Our high stock holding with beams being manufactured in the UK meant we were able to react quickly and mobilise the equipment within 7 days, allowing MD to stay on track with their tight programme.
  • Scaffold Package is £600k. Overall project estimated to be appx £6m.

More here: https://georgeroberts.com/case-study/temporary-roof-project-at-betley-court-manor/

SM Newsdesk
SM Newsdeskhttps://www.scaffmag.com
The staff at ScaffMag.com the leading scaffolding site for a digital generation.

Most popular ↑

CISRS says CSCS notice was served to negotiate “from a stronger position”

NASC president Sarah Klieve says CISRS served CSCS notice to negotiate from a stronger position, as Build UK says the card rules don’t block other sectors.

Scaffold collapses at Sydney site weeks after two workers seriously injured

The scaffold came down at a development on Wattle...

Adrian Chiles puts scaffolding skills shortage in national spotlight

A Guardian column has brought wider attention to recruitment pressures already affecting scaffolding contractors.

Scaffold Innovations: GapClamp™

  Since the Work at Height Regulations 2005 came into...

SG4:10 We Think The Answer Is Fast Guard™

If Carlsberg made advance guardrails.....  could this be the...

Latest news

86m Layher scaffold completed at Giotto’s Bell Tower

An 86-metre scaffold erected in just over four months will support a five-year restoration of the Florence landmark while keeping it open to visitors.
- Advertisement -
More from

86m Layher scaffold completed at Giotto’s Bell Tower

An 86-metre scaffold erected in just over four months will support a five-year restoration of the Florence landmark while keeping it open to visitors.

Golden Gate Bridge prepares temporary access platforms for seismic works

Night-time lane closures will allow crews to lower access platforms beneath the roadway as work progresses on the bridge’s final seismic retrofit phase.

PERI scaffolding supports major HS2 Birmingham dive-under works

PERI UK has supplied access scaffolding, formwork and engineering support for a 400m-long concrete dive-under being built as part of HS2’s Delta Junction near Birmingham.

Saudi firm breaks 27-year-old scaffolding world record

Saudi scaffolding firm Manar Al Omran has set a new Guinness World Record after building a 67.40m free-standing scaffold in Dammam.
Latest articles