George Roberts at Betley Court Manor

ADVERTISEMENT

Betley Court Manor House was a residential home, where 20 people lived. As the house was completely unsafe after a fire broke out, the project needed to be restored quickly and safely.

To restore the beloved grade II listed 18th-century manor house, scaffolders needed to protect the whole area from the elements, allowing the building to dry out after being drenched by 40 firefighters. Once dried, the building needed ongoing protection to allow the restoration work to be carried out unhindered. George Roberts was engaged to supply all scaffolding, access, and weather protection equipment to this important project.

Space on site was limited, meaning George Roberts drivers had to Hiab the equipment onto ground level, and to minimise impact on those who reside around the building, careful planning was required to maximise the delivery schedule.

Working closely with its customer and their design team to specify the 1.3m X Beams for the support structure, George Roberts provided full and open technical data during the design process. This helped them to act quickly and mobilise equipment to support our customer’s programme and budget.

Challenges

As the building had been completely destroyed by the fire, serious care had to be taken in order for the job to be undertaken safely. Consideration for the historical elements of the building also had to be a priority, as with any listed building restoration.

One of the complexities of the project was to design the temporary roof structure around the numerous chimneys where extra beam work was required to support the roof. The best solution for this was utilising its 1.3m deep X Beams.

George Roberts Ltd provided a full UBIX roof system and the Aluminium X Beams in both 750mm and 1300mm deep for the additional support to enable the whole structure to be covered for restoration to begin.

Stats:

  • A full UBIX Roof using 750mm X Beams, 450mm Deep Beams, 1300mm X Beams, Uniscaff Stairtowers, Tube, Fittings and Boards.
  • Our high stock holding with beams being manufactured in the UK meant we were able to react quickly and mobilise the equipment within 7 days, allowing MD to stay on track with their tight programme.
  • Scaffold Package is £600k. Overall project estimated to be appx £6m.

More here: https://georgeroberts.com/case-study/temporary-roof-project-at-betley-court-manor/

SM Newsdesk
SM Newsdeskhttps://www.scaffmag.com
The staff at ScaffMag.com the leading scaffolding site for a digital generation.

Most popular ↑

SAIA names teams for 2027 Scaffold Builders Competition

Manchester-based AK Scaffolding is on the list for Las Vegas, alongside 4 first-time entrants from the US, Lithuania, Switzerland and Canada.

Mobile scaffold falls three decks on offshore support vessel

Marine Safety Forum reports a three-tier scaffold collapse during repositioning, with seized wheels and no exclusion zone on the deck below.

Scaffold firm fined £16,000 after trainee’s fatal fall

HSE found that safe zones had not been established when Michael Swales fell 5 metres from a partially erected scaffold near Ripon.

Four injured in Taiwan market scaffold collapse

Taipei has halted work at the old Beitou market demolition site after a scaffold collapse injured four people. Investigations are continuing.

NIE Networks tenders £4.8m scaffolding framework for power infrastructure

NIE Networks is seeking scaffolding services across Northern Ireland's electricity infrastructure through two lots, with an initial four-year term and extension options.

Latest news

NZ to end public scaffold certificate register in WorkSafe handover

Employers face direct certificate checks as WorkSafe takes over New Zealand’s scaffolding CoC scheme. Existing cards will remain valid until expiry.
- Advertisement -
More from

Doka details climbing systems for Burj Binghatti tower

Doka’s project update sets out the climbing and edge-protection systems being used on Burj Binghatti, with a target of 1 floor a week.

PHD Access joins £190m Dungeness A decommissioning team

Aureos has named PHD Access as its scaffolding partner for the removal of eight 800-tonne boilers at Dungeness A. The overall programme is worth up to £190m.

Shield tackles hilltop access challenge in 19-day scaffold build

Shield erected access around the 38-metre Lansdowne Monument in 19 days despite a steep, rutted route that kept vans and lorries away from the hilltop.

Tyne Bridge to close for overhead scaffold deck installation

Advanced scaffolders will work around the clock during an October half-term closure to install a protection deck ahead of main arch restoration in early 2027.
Latest articles