George Roberts at Betley Court Manor

ADVERTISEMENT

Betley Court Manor House was a residential home, where 20 people lived. As the house was completely unsafe after a fire broke out, the project needed to be restored quickly and safely.

To restore the beloved grade II listed 18th-century manor house, scaffolders needed to protect the whole area from the elements, allowing the building to dry out after being drenched by 40 firefighters. Once dried, the building needed ongoing protection to allow the restoration work to be carried out unhindered. George Roberts was engaged to supply all scaffolding, access, and weather protection equipment to this important project.

Space on site was limited, meaning George Roberts drivers had to Hiab the equipment onto ground level, and to minimise impact on those who reside around the building, careful planning was required to maximise the delivery schedule.

Working closely with its customer and their design team to specify the 1.3m X Beams for the support structure, George Roberts provided full and open technical data during the design process. This helped them to act quickly and mobilise equipment to support our customer’s programme and budget.

Challenges

As the building had been completely destroyed by the fire, serious care had to be taken in order for the job to be undertaken safely. Consideration for the historical elements of the building also had to be a priority, as with any listed building restoration.

One of the complexities of the project was to design the temporary roof structure around the numerous chimneys where extra beam work was required to support the roof. The best solution for this was utilising its 1.3m deep X Beams.

George Roberts Ltd provided a full UBIX roof system and the Aluminium X Beams in both 750mm and 1300mm deep for the additional support to enable the whole structure to be covered for restoration to begin.

Stats:

  • A full UBIX Roof using 750mm X Beams, 450mm Deep Beams, 1300mm X Beams, Uniscaff Stairtowers, Tube, Fittings and Boards.
  • Our high stock holding with beams being manufactured in the UK meant we were able to react quickly and mobilise the equipment within 7 days, allowing MD to stay on track with their tight programme.
  • Scaffold Package is £600k. Overall project estimated to be appx £6m.

More here: https://georgeroberts.com/case-study/temporary-roof-project-at-betley-court-manor/

SM Newsdesk
SM Newsdeskhttps://www.scaffmag.com
The staff at ScaffMag.com the leading scaffolding site for a digital generation.

Most popular ↑

Government announces paternity pay for self-employed dads

Self-employed fathers and partners are to receive two weeks of support under government plans, with payments currently worth up to £194 a week.

Luton plans £11m scaffolding framework

Luton Council is preparing an estimated £11.04m scaffolding framework and will hold a supplier briefing next week ahead of a planned December tender.

Budget 2026: what it means for scaffolding firms

Fuel duty relief, higher minimum wages and apprenticeship measures feature in Budget 2026, as NASC warns investment promises must translate into construction work.

Scaffold Innovations: GapClamp™

  Since the Work at Height Regulations 2005 came into...

Shield tackles hilltop access challenge in 19-day scaffold build

Shield erected access around the 38-metre Lansdowne Monument in 19 days despite a steep, rutted route that kept vans and lorries away from the hilltop.

Latest news

Tube costs rise, but the CBAM outlook eases

In his first monthly column for Scaffmag, Trevor Inns of Tube Industries examines the forces shaping scaffold tube costs and explains why his latest estimate of January’s CBAM impact is lower than he expected in October.
- Advertisement -
More from

PHD Access joins £190m Dungeness A decommissioning team

Aureos has named PHD Access as its scaffolding partner for the removal of eight 800-tonne boilers at Dungeness A. The overall programme is worth up to £190m.

Shield tackles hilltop access challenge in 19-day scaffold build

Shield erected access around the 38-metre Lansdowne Monument in 19 days despite a steep, rutted route that kept vans and lorries away from the hilltop.

Tyne Bridge to close for overhead scaffold deck installation

Advanced scaffolders will work around the clock during an October half-term closure to install a protection deck ahead of main arch restoration in early 2027.

86m Layher scaffold completed at Giotto’s Bell Tower

An 86-metre scaffold erected in just over four months will support a five-year restoration of the Florence landmark while keeping it open to visitors.
Latest articles