PERI systems boost efficiency on £200m Walsall waste facility

ADVERTISEMENT

Specialist contractor Careys is using advanced formwork and scaffolding systems from PERI UK to construct the 40-metre reinforced concrete structure at the Walsall Energy Recovery Facility, replacing traditional methods with engineered solutions that deliver significant time and safety benefits.

The project, being built for client Encyclis with main contractor Kanadevia Inova, required innovative approaches to two critical challenges: providing safe vertical access throughout the build and forming an 880mm thick ground slab.

To solve the access issue, Careys deployed up to ten PERI UP Flex Stair Towers across the site at peak construction. The system scaffold uses a gravity lock mechanism that requires only a hammer to secure components, eliminating the time-consuming measurement and coupling work associated with traditional tube and fitting scaffolding.

“Our PERI UP system is a system scaffold, which means everything has set lengths and heights. All you need is a hammer to lock the equipment securely,” explained Gilbert Kee, sales engineer at PERI UK. “This gravity lock system is incredibly easy to erect; you literally just drop the components in, strike it with a hammer, and it’s secure.”

The system’s inherent levelness also removes the need for specialist inspectors to check every flight, saving considerable time. PERI UK provided full temporary works designs for the stair towers, transferring liability for structural stability from the contractor to the supplier.

For the ground floor, the team used the BECOSTOP permanent stop end system to segment the massive 20m x 20m concrete slab into manageable pours. The bespoke solution arrives on site ready-made, eliminating the labour-intensive cutting and propping required with traditional timber and ply methods.

“With our BECOSTOP system, erection is much quicker. Crucially, it’s left in position after the pour, unlike traditional methods where everything has to be removed,” said Kee.

William Griffith, project engineer at Careys, highlighted the safety advantages: “Due to the reinforcement detailing and the reinforcement projecting so far past the stop ends there was also a safety benefit in the use of BECOSTOP due to not having operatives getting beneath the projecting reinforcement and in some cases into the reinforcement cage to strike a typical stop end in this scenario.”

The structure, which extends from 6m below ground to 30m above, is now nearing structural completion. The concrete shell work for Careys lasted approximately 12 months.

The project demonstrates how modern, engineered systems can deliver measurable improvements in speed, safety and quality over conventional construction methods on complex industrial builds.

Most popular ↑

Avontus unveils AI platform linking scaffold design, inventory and business data

Avontus has unveiled a new artificial intelligence platform designed...

SAIA Convention gets underway with record attendance

The 2026 SAIA Annual Convention & Exposition is underway...

AT-PAC and partners deliver major weather protection scheme in Sweden

Around 700 tonnes of AT-PAC Ringlock scaffolding has been...

Australia launches national scaffolding best practice guidelines

The Scaffolding Association Australia (SAA) has launched the first...

Former boxing champion Carl Frampton joins Advanced NI Scaffolding charity golf day

Advanced NI Scaffolding has announced its first charity golf...

Latest news

ADVERTISEMENT
More from
Latest articles

Altrad to merge Generation and TRAD UK under single brand

Altrad has announced it will merge Generation Hire & Sales and TRAD UK into...

SAIA names 2026 Project Award winners at Nashville convention

The Scaffold & Access Industry Association has named the winners of its 2026 Project...

Avontus unveils AI platform linking scaffold design, inventory and business data

Avontus has unveiled a new artificial intelligence platform designed to connect scaffold design, inventory,...

SAIA Convention gets underway with record attendance

The 2026 SAIA Annual Convention & Exposition is underway in Nashville with the largest...

AT-PAC and partners deliver major weather protection scheme in Sweden

Around 700 tonnes of AT-PAC Ringlock scaffolding has been installed to support a major...

Former boxing champion Carl Frampton joins Advanced NI Scaffolding charity golf day

Advanced NI Scaffolding has announced its first charity golf day, bringing together customers, suppliers...

Australia launches national scaffolding best practice guidelines

The Scaffolding Association Australia (SAA) has launched the first version of its Australian Best...

Layher UK draws contractors to Eggborough technical open day

Layher UK welcomed scaffolding contractors, customers and industry professionals to its Eggborough depot this...