PERI systems boost efficiency on £200m Walsall waste facility

ADVERTISEMENT

Specialist contractor Careys is using advanced formwork and scaffolding systems from PERI UK to construct the 40-metre reinforced concrete structure at the Walsall Energy Recovery Facility, replacing traditional methods with engineered solutions that deliver significant time and safety benefits.

The project, being built for client Encyclis with main contractor Kanadevia Inova, required innovative approaches to two critical challenges: providing safe vertical access throughout the build and forming an 880mm thick ground slab.

To solve the access issue, Careys deployed up to ten PERI UP Flex Stair Towers across the site at peak construction. The system scaffold uses a gravity lock mechanism that requires only a hammer to secure components, eliminating the time-consuming measurement and coupling work associated with traditional tube and fitting scaffolding.

“Our PERI UP system is a system scaffold, which means everything has set lengths and heights. All you need is a hammer to lock the equipment securely,” explained Gilbert Kee, sales engineer at PERI UK. “This gravity lock system is incredibly easy to erect; you literally just drop the components in, strike it with a hammer, and it’s secure.”

The system’s inherent levelness also removes the need for specialist inspectors to check every flight, saving considerable time. PERI UK provided full temporary works designs for the stair towers, transferring liability for structural stability from the contractor to the supplier.

For the ground floor, the team used the BECOSTOP permanent stop end system to segment the massive 20m x 20m concrete slab into manageable pours. The bespoke solution arrives on site ready-made, eliminating the labour-intensive cutting and propping required with traditional timber and ply methods.

“With our BECOSTOP system, erection is much quicker. Crucially, it’s left in position after the pour, unlike traditional methods where everything has to be removed,” said Kee.

William Griffith, project engineer at Careys, highlighted the safety advantages: “Due to the reinforcement detailing and the reinforcement projecting so far past the stop ends there was also a safety benefit in the use of BECOSTOP due to not having operatives getting beneath the projecting reinforcement and in some cases into the reinforcement cage to strike a typical stop end in this scenario.”

The structure, which extends from 6m below ground to 30m above, is now nearing structural completion. The concrete shell work for Careys lasted approximately 12 months.

The project demonstrates how modern, engineered systems can deliver measurable improvements in speed, safety and quality over conventional construction methods on complex industrial builds.

SM Newsdesk
SM Newsdeskhttps://www.scaffmag.com
The staff at ScaffMag.com the leading scaffolding site for a digital generation.

Most popular ↑

PHD Access announces €37.7m investment for European expansion

PHD Access has announced a €37.7m investment from MML Ireland and Goodbody to support European growth and acquisitions, subject to regulatory approval.

Taylor Wimpey faces union challenge over notices to 19 scaffolders

Unite says 19 directly employed scaffolders and 31 joiners in the North East have received dismissal notices amid a dispute over proposed changes to pay and bonuses. Taylor Wimpey says discussions are continuing.

CISRS says CSCS notice was served to negotiate “from a stronger position”

NASC president Sarah Klieve says CISRS served CSCS notice to negotiate from a stronger position, as Build UK says the card rules don’t block other sectors.

Two workers hospitalised after partial collapse at Banbury construction site

Two workers were taken to hospital after a partial collapse at a Banbury construction site on 21 October. HSE says it is making enquiries, according to Construction Enquirer.

Scaffold Innovations: GapClamp™

  Since the Work at Height Regulations 2005 came into...

Latest news

Belfast scaffolding firm fined after driver killed by falling board

HSENI found inadequate exclusion zone controls after Samuel Magill was struck by a falling metal scaffold board during dismantling work in Belfast.
- Advertisement -
More from

Tyne Bridge to close for overhead scaffold deck installation

Advanced scaffolders will work around the clock during an October half-term closure to install a protection deck ahead of main arch restoration in early 2027.

86m Layher scaffold completed at Giotto’s Bell Tower

An 86-metre scaffold erected in just over four months will support a five-year restoration of the Florence landmark while keeping it open to visitors.

Golden Gate Bridge prepares temporary access platforms for seismic works

Night-time lane closures will allow crews to lower access platforms beneath the roadway as work progresses on the bridge’s final seismic retrofit phase.

PERI scaffolding supports major HS2 Birmingham dive-under works

PERI UK has supplied access scaffolding, formwork and engineering support for a 400m-long concrete dive-under being built as part of HS2’s Delta Junction near Birmingham.
Latest articles