PERI systems boost efficiency on £200m Walsall waste facility

ADVERTISEMENT

Specialist contractor Careys is using advanced formwork and scaffolding systems from PERI UK to construct the 40-metre reinforced concrete structure at the Walsall Energy Recovery Facility, replacing traditional methods with engineered solutions that deliver significant time and safety benefits.

The project, being built for client Encyclis with main contractor Kanadevia Inova, required innovative approaches to two critical challenges: providing safe vertical access throughout the build and forming an 880mm thick ground slab.

To solve the access issue, Careys deployed up to ten PERI UP Flex Stair Towers across the site at peak construction. The system scaffold uses a gravity lock mechanism that requires only a hammer to secure components, eliminating the time-consuming measurement and coupling work associated with traditional tube and fitting scaffolding.

“Our PERI UP system is a system scaffold, which means everything has set lengths and heights. All you need is a hammer to lock the equipment securely,” explained Gilbert Kee, sales engineer at PERI UK. “This gravity lock system is incredibly easy to erect; you literally just drop the components in, strike it with a hammer, and it’s secure.”

The system’s inherent levelness also removes the need for specialist inspectors to check every flight, saving considerable time. PERI UK provided full temporary works designs for the stair towers, transferring liability for structural stability from the contractor to the supplier.

For the ground floor, the team used the BECOSTOP permanent stop end system to segment the massive 20m x 20m concrete slab into manageable pours. The bespoke solution arrives on site ready-made, eliminating the labour-intensive cutting and propping required with traditional timber and ply methods.

“With our BECOSTOP system, erection is much quicker. Crucially, it’s left in position after the pour, unlike traditional methods where everything has to be removed,” said Kee.

William Griffith, project engineer at Careys, highlighted the safety advantages: “Due to the reinforcement detailing and the reinforcement projecting so far past the stop ends there was also a safety benefit in the use of BECOSTOP due to not having operatives getting beneath the projecting reinforcement and in some cases into the reinforcement cage to strike a typical stop end in this scenario.”

The structure, which extends from 6m below ground to 30m above, is now nearing structural completion. The concrete shell work for Careys lasted approximately 12 months.

The project demonstrates how modern, engineered systems can deliver measurable improvements in speed, safety and quality over conventional construction methods on complex industrial builds.

SM Newsdesk
SM Newsdeskhttps://www.scaffmag.com
The staff at ScaffMag.com the leading scaffolding site for a digital generation.

Most popular ↑

Saudi firm breaks 27-year-old scaffolding world record

Saudi scaffolding firm Manar Al Omran has set a new Guinness World Record after building a 67.40m free-standing scaffold in Dammam.

CSCS challenges CISRS case for leaving card scheme

CSCS has challenged the reasons for CISRS’s planned departure, while CISRS tells ScaffMag its legal advice and concerns over duplicate cards underpin the decision.

Scaffold Innovations: GapClamp™

  Since the Work at Height Regulations 2005 came into...

SG4:10 We Think The Answer Is Fast Guard™

If Carlsberg made advance guardrails.....  could this be the...

Scaffold collapses at Sydney site weeks after two workers seriously injured

The scaffold came down at a development on Wattle...

Latest news

CISRS says CSCS notice was served to negotiate “from a stronger position”

NASC president Sarah Klieve says CISRS served CSCS notice to negotiate from a stronger position, as Build UK says the card rules don’t block other sectors.
- Advertisement -
More from

Golden Gate Bridge prepares temporary access platforms for seismic works

Night-time lane closures will allow crews to lower access platforms beneath the roadway as work progresses on the bridge’s final seismic retrofit phase.

PERI scaffolding supports major HS2 Birmingham dive-under works

PERI UK has supplied access scaffolding, formwork and engineering support for a 400m-long concrete dive-under being built as part of HS2’s Delta Junction near Birmingham.

Saudi firm breaks 27-year-old scaffolding world record

Saudi scaffolding firm Manar Al Omran has set a new Guinness World Record after building a 67.40m free-standing scaffold in Dammam.

URTIM supplies scaffolding and formwork for $2bn Ceyhan petrochemical project

Turkish formwork and scaffolding manufacturer URTIM is supplying engineered temporary works systems for the major Ceyhan PDH/PP petrochemical development in southern Türkiye.
Latest articles