PERI systems boost efficiency on £200m Walsall waste facility

ADVERTISEMENT

Specialist contractor Careys is using advanced formwork and scaffolding systems from PERI UK to construct the 40-metre reinforced concrete structure at the Walsall Energy Recovery Facility, replacing traditional methods with engineered solutions that deliver significant time and safety benefits.

The project, being built for client Encyclis with main contractor Kanadevia Inova, required innovative approaches to two critical challenges: providing safe vertical access throughout the build and forming an 880mm thick ground slab.

To solve the access issue, Careys deployed up to ten PERI UP Flex Stair Towers across the site at peak construction. The system scaffold uses a gravity lock mechanism that requires only a hammer to secure components, eliminating the time-consuming measurement and coupling work associated with traditional tube and fitting scaffolding.

“Our PERI UP system is a system scaffold, which means everything has set lengths and heights. All you need is a hammer to lock the equipment securely,” explained Gilbert Kee, sales engineer at PERI UK. “This gravity lock system is incredibly easy to erect; you literally just drop the components in, strike it with a hammer, and it’s secure.”

The system’s inherent levelness also removes the need for specialist inspectors to check every flight, saving considerable time. PERI UK provided full temporary works designs for the stair towers, transferring liability for structural stability from the contractor to the supplier.

For the ground floor, the team used the BECOSTOP permanent stop end system to segment the massive 20m x 20m concrete slab into manageable pours. The bespoke solution arrives on site ready-made, eliminating the labour-intensive cutting and propping required with traditional timber and ply methods.

“With our BECOSTOP system, erection is much quicker. Crucially, it’s left in position after the pour, unlike traditional methods where everything has to be removed,” said Kee.

William Griffith, project engineer at Careys, highlighted the safety advantages: “Due to the reinforcement detailing and the reinforcement projecting so far past the stop ends there was also a safety benefit in the use of BECOSTOP due to not having operatives getting beneath the projecting reinforcement and in some cases into the reinforcement cage to strike a typical stop end in this scenario.”

The structure, which extends from 6m below ground to 30m above, is now nearing structural completion. The concrete shell work for Careys lasted approximately 12 months.

The project demonstrates how modern, engineered systems can deliver measurable improvements in speed, safety and quality over conventional construction methods on complex industrial builds.

Most popular ↑

Wayne Connolly honoured as NASC opens 2026 awards entries

NASC has opened entries for the 2026 Scaffolding Excellence...

GKR scaffolders help save woman’s life at London project

A GKR Scaffolding site team has been praised after...

Australian scaffolding body warns Kwikform collapse exposes subcontractor risks

Australia’s scaffolding trade body has said the voluntary administration...

Mock the Week star to host ScaffEx26 awards night

Comedian and television presenter Dara Ó Briain has been...

HAKI CEO Sverker Lindberg to step down by 2027

HAKI Safety has confirmed that its President and CEO,...

Latest news

PERI systems boost efficiency on £200m Walsall waste facility

ADVERTISEMENT

Specialist contractor Careys is using advanced formwork and scaffolding systems from PERI UK to construct the 40-metre reinforced concrete structure at the Walsall Energy Recovery Facility, replacing traditional methods with engineered solutions that deliver significant time and safety benefits.

The project, being built for client Encyclis with main contractor Kanadevia Inova, required innovative approaches to two critical challenges: providing safe vertical access throughout the build and forming an 880mm thick ground slab.

To solve the access issue, Careys deployed up to ten PERI UP Flex Stair Towers across the site at peak construction. The system scaffold uses a gravity lock mechanism that requires only a hammer to secure components, eliminating the time-consuming measurement and coupling work associated with traditional tube and fitting scaffolding.

“Our PERI UP system is a system scaffold, which means everything has set lengths and heights. All you need is a hammer to lock the equipment securely,” explained Gilbert Kee, sales engineer at PERI UK. “This gravity lock system is incredibly easy to erect; you literally just drop the components in, strike it with a hammer, and it’s secure.”

The system’s inherent levelness also removes the need for specialist inspectors to check every flight, saving considerable time. PERI UK provided full temporary works designs for the stair towers, transferring liability for structural stability from the contractor to the supplier.

For the ground floor, the team used the BECOSTOP permanent stop end system to segment the massive 20m x 20m concrete slab into manageable pours. The bespoke solution arrives on site ready-made, eliminating the labour-intensive cutting and propping required with traditional timber and ply methods.

“With our BECOSTOP system, erection is much quicker. Crucially, it’s left in position after the pour, unlike traditional methods where everything has to be removed,” said Kee.

William Griffith, project engineer at Careys, highlighted the safety advantages: “Due to the reinforcement detailing and the reinforcement projecting so far past the stop ends there was also a safety benefit in the use of BECOSTOP due to not having operatives getting beneath the projecting reinforcement and in some cases into the reinforcement cage to strike a typical stop end in this scenario.”

The structure, which extends from 6m below ground to 30m above, is now nearing structural completion. The concrete shell work for Careys lasted approximately 12 months.

The project demonstrates how modern, engineered systems can deliver measurable improvements in speed, safety and quality over conventional construction methods on complex industrial builds.

Popular Categories

Latest posts

ScaffChamp 2026 confirms global live stream details

ScaffChamp powered by Layher 2026 will once again be broadcast live to the global scaffolding community. The official live stream will begin on 6 June...

Australian scaffolding body warns Kwikform collapse exposes subcontractor risks

Australia’s scaffolding trade body has said the voluntary administration of the Kwikform group highlights wider concerns over subcontractor exposure and payment risk across the...

HAKI CEO Sverker Lindberg to step down by 2027

HAKI Safety has confirmed that its President and CEO, Sverker Lindberg, will leave his position no later than April 2027. The company said Lindberg has...

Staht signs US distribution deal for digital pull testing range

UK digital pull testing manufacturer Staht has appointed Diversified Fall Protection as its exclusive distributor in the United States. The agreement will see Diversified market,...

GKR scaffolders help save woman’s life at London project

A GKR Scaffolding site team has been praised after helping to save the life of a woman who collapsed outside a live London project. The...

King’s Award recognises Lee Marley Group’s training work

Lee Marley Group has received a King’s Award for Enterprise in recognition of its work to widen access to careers in construction. The large-scale construction...

Mock the Week star to host ScaffEx26 awards night

Comedian and television presenter Dara Ó Briain has been confirmed as the host of this year’s Scaffolding Excellence Awards. The awards evening will take place...

Wayne Connolly honoured as NASC opens 2026 awards entries

NASC has opened entries for the 2026 Scaffolding Excellence Awards, with this year’s apprentice category renamed in memory of former NASC president and CISRS...

TRAD UK launches charity campaign supporting Epilepsy Action

TRAD UK has launched a new fundraising campaign in support of Epilepsy Action, the national charity helping people and families affected by epilepsy. The 2026-27...

Scaffolding firms urged to review RIDDOR procedures as HSE consults on changes

The Health and Safety Executive has launched a consultation on proposed changes to the Reporting of Injuries, Diseases and Dangerous Occurrences Regulations 2013, known...

Spring Issue #29 | Past issues >>

Latest topics

Most popular ⚡︎

Wayne Connolly honoured as NASC opens 2026 awards entries

NASC has opened entries for the 2026 Scaffolding Excellence...

GKR scaffolders help save woman’s life at London project

A GKR Scaffolding site team has been praised after...

Australian scaffolding body warns Kwikform collapse exposes subcontractor risks

Australia’s scaffolding trade body has said the voluntary administration...

Mock the Week star to host ScaffEx26 awards night

Comedian and television presenter Dara Ó Briain has been...

HAKI CEO Sverker Lindberg to step down by 2027

HAKI Safety has confirmed that its President and CEO,...

Related articles

ADVERTISEMENTS
More from
Latest articles

ScaffCycle relaunches used scaffolding marketplace

ScaffCycle has relaunched its online marketplace for used scaffolding after rebuilding the platform to...

ScaffChamp 2026 confirms global live stream details

ScaffChamp powered by Layher 2026 will once again be broadcast live to the global...

Australian scaffolding body warns Kwikform collapse exposes subcontractor risks

Australia’s scaffolding trade body has said the voluntary administration of the Kwikform group highlights...

HAKI CEO Sverker Lindberg to step down by 2027

HAKI Safety has confirmed that its President and CEO, Sverker Lindberg, will leave his...

Staht signs US distribution deal for digital pull testing range

UK digital pull testing manufacturer Staht has appointed Diversified Fall Protection as its exclusive...

GKR scaffolders help save woman’s life at London project

A GKR Scaffolding site team has been praised after helping to save the life...