£21M Pay Out After Birdcage Scaffolding Deemed The Cause Of Massive Fire

ADVERTISEMENT

scaffolding

A roofing contractor has been ordered to pay more than £21 million in damages after a flick of a switch caused a catastrophic fire at a West Midlands factory.

The blaze, which tore through Mueller Europe Ltd’s copper tubing factory in Bilston in the early hours of  November 9, 2008, was caused by gas heaters which ignited a scaffolding deck put up by contractors carrying out re-roofing work.

Central Roofing (South Wales) Ltd had been working on the roof as the factory continued to operate below, London’s High Court heard.

Scaffolding was boarded and sheeted as a “birdcage” structure using flammable materials.

It enclosed two heaters that were used to warm the factory.

When the heaters were switched on the fire began.

The factory was left a smoking ruin, with part of its roof collapsed and massive damage caused to its contents.

The blaze led to a legal battle where a top judge ruled Central Roofing liable to pay Mueller a total of £21,357,889.

Mr Justice Stuart-Smith said: “The birdcage scaffold enclosed the heaters so that they were only a short distance above the surface of the scaffold’s floor.

“Once enclosed by the combustible materials of the completed birdcage scaffold, the heaters were an obvious fire hazard, which should have been appreciated by anyone who turned their mind to the question.”

The judge said that the “immediate trigger” for the fire was the inadvertent turning on of a switch and that was “the foreseeable, even predictable, consequence of the systemic failings on both sides that had preceded it.”

Although Mueller should have made sure the enclosed heaters were switched off, Central bore the primary responsibility to carry out the work safely and to point out the obvious hazard.

There had been three previous incidents when heaters were switched on when they should not have been, said the judge, who added: “Central continued to take no steps to carry out the works safely when they knew that Mueller was not routinely isolating and the failure to isolate had already caused ‘near misses’.”

Finding the Bridgend-based roofing company liable to compensate Mueller for the damage to the factory, its contents, equipment and interruption of its business, the judge said Central Roofing’s breaches of contract “were an effective or dominant cause of the fire”.

Mueller’s lawyers had argued that the scaffold deck was less than a metre away from the heaters and that a fire was “all but inevitable” if they were switched on.

Story Via: birminghammail.co.uk

Most popular ↑

Scaffolder ‘lucky to be alive’ after CCTV captures skylight fall

CCTV footage showing the moment a scaffolder fell through...

UK construction starts tipped to rise after difficult start to 2026

UK construction activity is expected to recover from 2027...

Amber heat alert puts scaffolding site welfare in focus

Scaffolding firms are being urged to review hot-weather controls...

Scaffolding takes centre stage at Arc Project’s 24-hour warehouse race

Midland Scaffolding Services has helped deliver an unusual event...

Nearly 80% of scaffold sites fail safety checks in German state

Authorities in the German state of Hesse have launched...

Latest news

ADVERTISEMENT
More from
Latest articles

Amber heat alert puts scaffolding site welfare in focus

Scaffolding firms are being urged to review hot-weather controls as an amber heat-health alert...

AT-PAC opens Darwin branch to support northern Australia projects

AT-PAC has opened a new branch in Darwin, Northern Territory, giving contractors in northern...

JR Scaffold Services leads access project at Glasgow Royal Infirmary

JR Scaffold Services has completed a specialist scaffold and temporary roof project at the...

UK construction will need 41,200 extra workers a year, CITB warns

The UK construction industry will need an average of 41,200 extra workers each year...

Tickets go on sale for 2026 Scaffolding Excellence Awards

Tickets and tables for the 2026 Scaffolding Excellence Awards are now on sale, with...

UK construction starts tipped to rise after difficult start to 2026

UK construction activity is expected to recover from 2027 after a difficult start to...

Scaffolding takes centre stage at Arc Project’s 24-hour warehouse race

Midland Scaffolding Services has helped deliver an unusual event project after building a 270...

Layher UK brings open morning series to Livingston

Layher UK is bringing its regional open morning series to Scotland later this month,...