HARSCO is on display at new Bordeaux theatre

ADVERTISEMENT

A project to create a new, 1,500-seat theatre building on a site with a restricted footprint and limited access has highlighted the industry knowledge, expertise and value which Harsco Infrastructure brings to construction projects. Harsco was able to design and construct an innovative, bespoke support girder system which overcame the restrictions of the site and allowed the construction of a number of key structural elements of the new building.

The new theatre in Bordeaux, France, is being built on a site surrounded by existing buildings. Harsco was asked to provide a support system to carry formwork for the construction of a number of 6 ft wide, 7 ft high, 105 ft long in-situ concrete beams. These beams needed to span the stage area and also support a further 5 floors of apartments and office accommodation being built above. The girder systems supplied by Harsco were to vary in length – with the longest being 30.90m – which needed to be lowered, relocated, and in some cases altered in length before work on the next beam could begin.

Working on behalf of Portuguese contractor BUILDIN, Harsco was able to draw on its wealth of technical expertise and devise a bespoke H33 braced truss-girder system which was sufficiently flexible and reliable to satisfy this demand. The Harsco H33 beam system offers a flexible, robust and reliable solution with the high load-bearing capacity needed for this type of project. Its excellent weight-to-capacity ratio made it ideal for the long spans involved, while the easy to assemble nature of the system components ensured rapid construction of the girders required.

This proved to be a faster, more cost-effective and practical solution than other alternatives which might have been used. However a severe lack of working space on the site meant that Harsco also had to adapt the traditional methods used to construct such a system.

“We actually did much of the construction work on the girders about 10km away from the site itself,” explains Harsco’s Ingo Schnelting. “This meant that we could prefabricate the girder sections under more controlled conditions, which made it far easier to ensure that they complied fully with the drawings. That way we were able to avoid any unexpected problems on site and be confident that the girders would fit neatly into place.”

Harsco was then able to partially dismantle the girders for transportation and deliver them to site. This also minimised the disruption to other trades that would have been caused by fabricating the units on the site itself. Lack of on-site storage space meant that Harsco had to adopt a just-in-time schedule for these deliveries and also co-ordinate this with special permission from the city authorities to operate extended length transport vehicles.

“We had to remain flexible in our approach to every aspect of this project,” adds Ingo Schnelting. “The different lengths of concrete beam that the building required meant that we sometimes had to remove the girders from the building and transport them the 10 km back to the construction area. There we were then able to re-configure their length before delivering them back to site and using hydraulic jacks to raise them into place, ready to support the formwork required to make the next beam.

 

“This was an excellent example of Harsco’s ‘Insight onsite’ philosophy in action and illustrates the way we are able to develop bespoke solutions that are tailored to the specific requirements of individual projects,” adds Ingo. “The end result of this approach is that we can deliver the highest standards of reliability, cost-effectiveness and safety and that was certainly the case on this project.”

For more information please call. 01372 381 300 or visit www.harsco-i.co.uk

Via: Harsco Press Release

Most popular ↑

Wayne Connolly honoured as NASC opens 2026 awards entries

NASC has opened entries for the 2026 Scaffolding Excellence...

GKR scaffolders help save woman’s life at London project

A GKR Scaffolding site team has been praised after...

Mock the Week star to host ScaffEx26 awards night

Comedian and television presenter Dara Ó Briain has been...

TRAD UK launches charity campaign supporting Epilepsy Action

TRAD UK has launched a new fundraising campaign in...

CISRS Accreditation Granted For Safety & Access Indian Training Center

  CISRS has awarded Safety & Access Ltd full overseas...

Latest news

HARSCO is on display at new Bordeaux theatre

ADVERTISEMENT

A project to create a new, 1,500-seat theatre building on a site with a restricted footprint and limited access has highlighted the industry knowledge, expertise and value which Harsco Infrastructure brings to construction projects. Harsco was able to design and construct an innovative, bespoke support girder system which overcame the restrictions of the site and allowed the construction of a number of key structural elements of the new building.

The new theatre in Bordeaux, France, is being built on a site surrounded by existing buildings. Harsco was asked to provide a support system to carry formwork for the construction of a number of 6 ft wide, 7 ft high, 105 ft long in-situ concrete beams. These beams needed to span the stage area and also support a further 5 floors of apartments and office accommodation being built above. The girder systems supplied by Harsco were to vary in length – with the longest being 30.90m – which needed to be lowered, relocated, and in some cases altered in length before work on the next beam could begin.

Working on behalf of Portuguese contractor BUILDIN, Harsco was able to draw on its wealth of technical expertise and devise a bespoke H33 braced truss-girder system which was sufficiently flexible and reliable to satisfy this demand. The Harsco H33 beam system offers a flexible, robust and reliable solution with the high load-bearing capacity needed for this type of project. Its excellent weight-to-capacity ratio made it ideal for the long spans involved, while the easy to assemble nature of the system components ensured rapid construction of the girders required.

This proved to be a faster, more cost-effective and practical solution than other alternatives which might have been used. However a severe lack of working space on the site meant that Harsco also had to adapt the traditional methods used to construct such a system.

“We actually did much of the construction work on the girders about 10km away from the site itself,” explains Harsco’s Ingo Schnelting. “This meant that we could prefabricate the girder sections under more controlled conditions, which made it far easier to ensure that they complied fully with the drawings. That way we were able to avoid any unexpected problems on site and be confident that the girders would fit neatly into place.”

Harsco was then able to partially dismantle the girders for transportation and deliver them to site. This also minimised the disruption to other trades that would have been caused by fabricating the units on the site itself. Lack of on-site storage space meant that Harsco had to adopt a just-in-time schedule for these deliveries and also co-ordinate this with special permission from the city authorities to operate extended length transport vehicles.

“We had to remain flexible in our approach to every aspect of this project,” adds Ingo Schnelting. “The different lengths of concrete beam that the building required meant that we sometimes had to remove the girders from the building and transport them the 10 km back to the construction area. There we were then able to re-configure their length before delivering them back to site and using hydraulic jacks to raise them into place, ready to support the formwork required to make the next beam.

 

“This was an excellent example of Harsco’s ‘Insight onsite’ philosophy in action and illustrates the way we are able to develop bespoke solutions that are tailored to the specific requirements of individual projects,” adds Ingo. “The end result of this approach is that we can deliver the highest standards of reliability, cost-effectiveness and safety and that was certainly the case on this project.”

For more information please call. 01372 381 300 or visit www.harsco-i.co.uk

Via: Harsco Press Release

Popular Categories

Latest posts

HAKI CEO Sverker Lindberg to step down by 2027

HAKI Safety has confirmed that its President and CEO, Sverker Lindberg, will leave his position no later than April 2027. The company said Lindberg has...

Staht signs US distribution deal for digital pull testing range

UK digital pull testing manufacturer Staht has appointed Diversified Fall Protection as its exclusive distributor in the United States. The agreement will see Diversified market,...

GKR scaffolders help save woman’s life at London project

A GKR Scaffolding site team has been praised after helping to save the life of a woman who collapsed outside a live London project. The...

King’s Award recognises Lee Marley Group’s training work

Lee Marley Group has received a King’s Award for Enterprise in recognition of its work to widen access to careers in construction. The large-scale construction...

Mock the Week star to host ScaffEx26 awards night

Comedian and television presenter Dara Ó Briain has been confirmed as the host of this year’s Scaffolding Excellence Awards. The awards evening will take place...

Wayne Connolly honoured as NASC opens 2026 awards entries

NASC has opened entries for the 2026 Scaffolding Excellence Awards, with this year’s apprentice category renamed in memory of former NASC president and CISRS...

TRAD UK launches charity campaign supporting Epilepsy Action

TRAD UK has launched a new fundraising campaign in support of Epilepsy Action, the national charity helping people and families affected by epilepsy. The 2026-27...

Scaffolding firms urged to review RIDDOR procedures as HSE consults on changes

The Health and Safety Executive has launched a consultation on proposed changes to the Reporting of Injuries, Diseases and Dangerous Occurrences Regulations 2013, known...

Scottish offshore workers urged to consider scaffolding careers

The Construction Industry Training Board is targeting workers from Scotland’s offshore energy sector as part of efforts to widen the construction talent pool and...

NASC warns members over online conduct in new media policy

The National Access and Scaffolding Confederation said the new Social Media and General Media Policy sets expectations for how its members, CISRS centres and...

Spring Issue #29 | Past issues >>

Latest topics

Most popular ⚡︎

Wayne Connolly honoured as NASC opens 2026 awards entries

NASC has opened entries for the 2026 Scaffolding Excellence...

GKR scaffolders help save woman’s life at London project

A GKR Scaffolding site team has been praised after...

Mock the Week star to host ScaffEx26 awards night

Comedian and television presenter Dara Ó Briain has been...

TRAD UK launches charity campaign supporting Epilepsy Action

TRAD UK has launched a new fundraising campaign in...

CISRS Accreditation Granted For Safety & Access Indian Training Center

  CISRS has awarded Safety & Access Ltd full overseas...

Related articles

ADVERTISEMENTS
More from
Latest articles

Australian scaffolding body warns Kwikform collapse exposes subcontractor risks

Australia’s scaffolding trade body has said the voluntary administration of the Kwikform group highlights...

HAKI CEO Sverker Lindberg to step down by 2027

HAKI Safety has confirmed that its President and CEO, Sverker Lindberg, will leave his...

Staht signs US distribution deal for digital pull testing range

UK digital pull testing manufacturer Staht has appointed Diversified Fall Protection as its exclusive...

GKR scaffolders help save woman’s life at London project

A GKR Scaffolding site team has been praised after helping to save the life...

King’s Award recognises Lee Marley Group’s training work

Lee Marley Group has received a King’s Award for Enterprise in recognition of its...

Mock the Week star to host ScaffEx26 awards night

Comedian and television presenter Dara Ó Briain has been confirmed as the host of...