Ad
Thursday, November 6, 2025

The UK’s Largest Temporary Roof installation made possible by the X factor

ADVERTISEMENT

The Tidworth and Bulford infrastructure framework, worth in excess of £15bn, were part of a much larger plan to uplift capacities and improve overall facilities at a number of key MOD sites across England. This project provided high quality, fully serviced and purpose-built living and working accommodation for our returning soldiers.

In the UK, there is strong commitment to maintaining the overall health and wellbeing of service personnel, even after they have left the services. This project was to improve facilities at two army camps, meaning soldiers returning from demanding operations will receive the quality accommodation they deserve.

To ensure the building remains weather-proof and to enhance its whole-life performance, the entire exterior of the roof and the interior ceiling tiles were replaced. George Roberts Ltd were engaged to support the scaffolding contractor, Ideal Scaffolding Southern Ltd.

To allow unhindered renewal of the old roof along with access for internal works to replace the ceiling in the main building, a large scale bespoke temporary roof was provided along with some large internal scaffolds.

Negating the need of 450T of ballast – or 18 truck loads

During the first stage, the goal was to erect the internal birdcage measuring 37m long x 18m wide x 12m high using over 250 tonnes of scaffolding, within 3 weeks. The work was being undertaken during the first Covid-19 lockdown in the UK, therefore, care had to be taken to observe the Government’s Covid-19 guidelines. This proved challenging in maintaining social distancing, in particular when working at heights.

The second phase of the project was to erect a temporary roof measuring 52m long x 42m wide with additional buttresses for an unsupported span of 38.5m in the centre section of the roof.

A unique ‘Platypus’ percussion anchor point system was used to secure the free-standing structure at ground level.  This unique lightweight and corrosion resistant anchor shaved weeks off the build programme, which otherwise would have required around 450 tonnes of ballast at the base of the scaffolding around the perimeter.

Due to the sheer size of the truss beams, the roof bays had to be skilfully assembled at ground level on special rigs by Ideal Scaffolding Southern Ltd, then lifted into position on top of the support scaffold by a crane.  This meant the roof was assembled, lifted into position (over a 3-lift programme) and fully sheeted in situ over a staggered 4-week period to maximise safety and productivity.

The Keder roofing sheets supplied by George Roberts was manufactured exactly to size for best fit using a 610g/m flame retardant PVC material providing a watertight barrier, meaning roofing works would continue throughout the project, regardless of weather conditions.

the UK's largest bespoke temporary roof

The X Factor

For most temporary roof applications, our standard 0.75m beam is more than sufficient, but because of the very large span requirement (42m) on this project, we needed to specify the heavier duty 1.3m deep X Beam – a first for George Roberts and Ideal Scaffolding.  This also allowed productivity to be maintained using 3.07m & 2.57m bay widths throughout. Without having X Beams in our offering, this project simply wouldn’t have been possible.

“The project was supported by George Roberts Ltd, who provided an invaluable service to supply all temporary roofing and scaffolding equipment needed. The flexibility & professionalism that the team of George Roberts demonstrated during the planning and execution of the project, proved to be a key component in its success.  At the time of the project, the temporary roof was one of the largest in the country.”  Darren Lee, the owner at Ideal Scaffolding Southern Ltd.

Challenges

The main challenges for George Roberts Ltd were around the rapid supply of over 250 tonnes of equipment, 200 miles from our Liverpool depot over multiple loads.

There were also engineering challenges due to the size of the building and roof span required, and also, tying into the structure was not permitted, meaning all supporting scaffolds needed to be free-standing.

The scheme was expertly engineered by Optima Scaffold Designs in Bristol.  Due to the very large span required, the UBIX temporary roof was designed utilising 1.3m deep aluminium X Beams. The roof was staggered in section to follow the natural plan size of the building which ranged in overall cover width from 34m to 44m.

For this project George Roberts Ltd had to call on the services of Alan White Design and our licensed beam manufacturers Apollo to expertly engineer a brand new 18-degree Ridge Beam to form the main duo-pitch roof truss structure, along with the design of a bespoke aluminium diagonal brace and tension bar system to suit this gigantic free-standing structure.

This represents a significant investment which will ensure Service personnel continue to have access to high quality sports facilities on the defence estate.

At the time of this project in 2020 the external scaffolding at Tidworth boasted the biggest unsupported span within a temporary roof standing anywhere in the UK.

Stats

Project comprised with earthworks, groundworks, drainage, reinforced concrete works for foundation slabs and external works to various types of accommodation blocks. Associated external works include access roads, footpaths, car parks, hardstanding, street furniture and lighting, bin stores, cycle racks and areas of hard and soft landscaping.

  • The overall plan cover size provided for this project on time and on budget was in excess of 2000m²
  • The building was over 40 metres in width and all supporting scaffolding had to be completely free standing.
  • Temporary roof covering a whopping 52m long x 42m wide.
  • Each of the 19 trusses weighed up to 2.6 tonnes.
  • Delivered over 250 tonnes of scaffolding equipment to site.
  • The structure was fully weather contained in situ using our popular 610g/m² Flame Retardant PVC sheeting material that was tailored exactly to length to provide an exact fit.
  • Tidworth project was one of the UK’s largest free-standing Temporary Roof structures.
  • Project valued in excess of £15 billion

Equipment and Types of Scaffolding Supplied

George Roberts supplied scaffolding tubes, fittings, timber boards, Uniscaff Stair Tower & Loading Tower, flame retardant Power clad sheeting, aluminium X Beams and our UBIX temporary roof system.

 

ADVERTISEMENT

Popular Categories

Latest news

PERI UK’s Terry Hall recognised as ‘Unsung Hero’ for driving formwork safety reform

Terry Hall, Field Services Manager at PERI UK, has been honoured with the ‘Unsung Hero’ award at this year’s CONSTRUCT Day for his work...

Scaffolders urged to tighten safety as climate change brings fiercer storms

Extreme weather is exposing poor practices across the scaffolding industry, as insurance specialists urge contractors to tighten safety procedures in response to increasingly severe...

Connolly Scaffolding unveils major new Salford base as part of multi-million-pound expansion

Connolly Scaffolding has completed a major expansion with the opening of a new 26,000 sq ft warehouse and yard in Salford – a move...

Surge in construction apprenticeships as CITB support drives 61% rise

The Construction Industry Training Board (CITB) has reported a sharp rise in apprenticeship starts, with more than 1,500 new apprentices supported by its New...

URTIM powers Turkey’s first floating gas platform

Turkey has taken a major step towards energy independence with the completion of its first floating natural gas production platform, the Osman Gazi. At the...

CISRS announces suite of new safety and inspection courses

The Construction Industry Scaffolders Record Scheme (CISRS) has announced a series of new and updated training courses aimed at improving safety, technical standards, and...

House-building recovery delayed until 2029, industry warns

The Construction Products Association warns UK house-building will not recover to pre-pandemic levels until 2029 or 2030, urging government support for first-time buyers to prevent further insolvencies and job losses.

Staht secures largest ever distribution deal with Leach’s

One of the UK’s leading testing technology firms, Staht, has announced its largest ever distribution agreement after joining forces with Leach’s. The partnership will expand...

Avontus to host free webinars on digital scaffold management this November

Avontus Software has announced a series of free, live webinars in November designed to help contractors overcome the everyday challenges of tracking and managing...

Scaff25 announces global line-up of industry leaders for Sydney conference

The Scaffolding Association Australia (SAA) has revealed an impressive line-up of international speakers for its upcoming Scaff25 Annual Conference & Awards Night, set to...

Latest news

ADVERTISEMENT

The magazine

Issue 27 | Past issues >>

Popular

CISRS announces suite of new safety and inspection courses

The Construction Industry Scaffolders Record Scheme (CISRS) has announced...

House-building recovery delayed until 2029, industry warns

The Construction Products Association warns UK house-building will not recover to pre-pandemic levels until 2029 or 2030, urging government support for first-time buyers to prevent further insolvencies and job losses.

URTIM powers Turkey’s first floating gas platform

Turkey has taken a major step towards energy independence...

Connolly Scaffolding unveils major new Salford base as part of multi-million-pound expansion

Connolly Scaffolding has completed a major expansion with the...

ScaffChamp 2025: Teams Gather in Vilnius for Opening Day

The international scaffolding competition ScaffChamp 2025 has officially begun,...

Related articles

Major Midlands Hotel A Perfect Host for Sky Scaffolding

A prestigious Birmingham hotel has been reaching for the sky in search of the perfect safe access scaffolding solution. Now, the Clayton Hotel in the city centre has a rooftop extension to be proud...
ADVERTISEMENTS

Latest topics

ULMA Construction eyes UK expansion with Des Moore leading setup

European scaffolding and formwork giant ULMA Construction is preparing...

Scaffolders urged to tighten safety as climate change brings fiercer storms

Extreme weather is exposing poor practices across the scaffolding...

Connolly Scaffolding unveils major new Salford base as part of multi-million-pound expansion

Connolly Scaffolding has completed a major expansion with the...
ADVERTISEMENTS