The UK’s Largest Temporary Roof installation made possible by the X factor

ADVERTISEMENT

The Tidworth and Bulford infrastructure framework, worth in excess of £15bn, were part of a much larger plan to uplift capacities and improve overall facilities at a number of key MOD sites across England. This project provided high quality, fully serviced and purpose-built living and working accommodation for our returning soldiers.

In the UK, there is strong commitment to maintaining the overall health and wellbeing of service personnel, even after they have left the services. This project was to improve facilities at two army camps, meaning soldiers returning from demanding operations will receive the quality accommodation they deserve.

To ensure the building remains weather-proof and to enhance its whole-life performance, the entire exterior of the roof and the interior ceiling tiles were replaced. George Roberts Ltd were engaged to support the scaffolding contractor, Ideal Scaffolding Southern Ltd.

To allow unhindered renewal of the old roof along with access for internal works to replace the ceiling in the main building, a large scale bespoke temporary roof was provided along with some large internal scaffolds.

Negating the need of 450T of ballast – or 18 truck loads

During the first stage, the goal was to erect the internal birdcage measuring 37m long x 18m wide x 12m high using over 250 tonnes of scaffolding, within 3 weeks. The work was being undertaken during the first Covid-19 lockdown in the UK, therefore, care had to be taken to observe the Government’s Covid-19 guidelines. This proved challenging in maintaining social distancing, in particular when working at heights.

The second phase of the project was to erect a temporary roof measuring 52m long x 42m wide with additional buttresses for an unsupported span of 38.5m in the centre section of the roof.

A unique ‘Platypus’ percussion anchor point system was used to secure the free-standing structure at ground level.  This unique lightweight and corrosion resistant anchor shaved weeks off the build programme, which otherwise would have required around 450 tonnes of ballast at the base of the scaffolding around the perimeter.

Due to the sheer size of the truss beams, the roof bays had to be skilfully assembled at ground level on special rigs by Ideal Scaffolding Southern Ltd, then lifted into position on top of the support scaffold by a crane.  This meant the roof was assembled, lifted into position (over a 3-lift programme) and fully sheeted in situ over a staggered 4-week period to maximise safety and productivity.

The Keder roofing sheets supplied by George Roberts was manufactured exactly to size for best fit using a 610g/m flame retardant PVC material providing a watertight barrier, meaning roofing works would continue throughout the project, regardless of weather conditions.

the UK's largest bespoke temporary roof

The X Factor

For most temporary roof applications, our standard 0.75m beam is more than sufficient, but because of the very large span requirement (42m) on this project, we needed to specify the heavier duty 1.3m deep X Beam – a first for George Roberts and Ideal Scaffolding.  This also allowed productivity to be maintained using 3.07m & 2.57m bay widths throughout. Without having X Beams in our offering, this project simply wouldn’t have been possible.

“The project was supported by George Roberts Ltd, who provided an invaluable service to supply all temporary roofing and scaffolding equipment needed. The flexibility & professionalism that the team of George Roberts demonstrated during the planning and execution of the project, proved to be a key component in its success.  At the time of the project, the temporary roof was one of the largest in the country.”  Darren Lee, the owner at Ideal Scaffolding Southern Ltd.

Challenges

The main challenges for George Roberts Ltd were around the rapid supply of over 250 tonnes of equipment, 200 miles from our Liverpool depot over multiple loads.

There were also engineering challenges due to the size of the building and roof span required, and also, tying into the structure was not permitted, meaning all supporting scaffolds needed to be free-standing.

The scheme was expertly engineered by Optima Scaffold Designs in Bristol.  Due to the very large span required, the UBIX temporary roof was designed utilising 1.3m deep aluminium X Beams. The roof was staggered in section to follow the natural plan size of the building which ranged in overall cover width from 34m to 44m.

For this project George Roberts Ltd had to call on the services of Alan White Design and our licensed beam manufacturers Apollo to expertly engineer a brand new 18-degree Ridge Beam to form the main duo-pitch roof truss structure, along with the design of a bespoke aluminium diagonal brace and tension bar system to suit this gigantic free-standing structure.

This represents a significant investment which will ensure Service personnel continue to have access to high quality sports facilities on the defence estate.

At the time of this project in 2020 the external scaffolding at Tidworth boasted the biggest unsupported span within a temporary roof standing anywhere in the UK.

Stats

Project comprised with earthworks, groundworks, drainage, reinforced concrete works for foundation slabs and external works to various types of accommodation blocks. Associated external works include access roads, footpaths, car parks, hardstanding, street furniture and lighting, bin stores, cycle racks and areas of hard and soft landscaping.

  • The overall plan cover size provided for this project on time and on budget was in excess of 2000m²
  • The building was over 40 metres in width and all supporting scaffolding had to be completely free standing.
  • Temporary roof covering a whopping 52m long x 42m wide.
  • Each of the 19 trusses weighed up to 2.6 tonnes.
  • Delivered over 250 tonnes of scaffolding equipment to site.
  • The structure was fully weather contained in situ using our popular 610g/m² Flame Retardant PVC sheeting material that was tailored exactly to length to provide an exact fit.
  • Tidworth project was one of the UK’s largest free-standing Temporary Roof structures.
  • Project valued in excess of £15 billion

Equipment and Types of Scaffolding Supplied

George Roberts supplied scaffolding tubes, fittings, timber boards, Uniscaff Stair Tower & Loading Tower, flame retardant Power clad sheeting, aluminium X Beams and our UBIX temporary roof system.

 

Most popular ↑

Wayne Connolly honoured as NASC opens 2026 awards entries

NASC has opened entries for the 2026 Scaffolding Excellence...

CISRS Accreditation Granted For Safety & Access Indian Training Center

  CISRS has awarded Safety & Access Ltd full overseas...

The Scaffolding Association adds free seminar on Scaffolding Ties to roadshow

Due to recent scaffold collapses from around the UK,...

GKR scaffolders help save woman’s life at London project

A GKR Scaffolding site team has been praised after...

TRAD UK launches charity campaign supporting Epilepsy Action

TRAD UK has launched a new fundraising campaign in...

Latest news

The UK’s Largest Temporary Roof installation made possible by the X factor

ADVERTISEMENT

The Tidworth and Bulford infrastructure framework, worth in excess of £15bn, were part of a much larger plan to uplift capacities and improve overall facilities at a number of key MOD sites across England. This project provided high quality, fully serviced and purpose-built living and working accommodation for our returning soldiers.

In the UK, there is strong commitment to maintaining the overall health and wellbeing of service personnel, even after they have left the services. This project was to improve facilities at two army camps, meaning soldiers returning from demanding operations will receive the quality accommodation they deserve.

To ensure the building remains weather-proof and to enhance its whole-life performance, the entire exterior of the roof and the interior ceiling tiles were replaced. George Roberts Ltd were engaged to support the scaffolding contractor, Ideal Scaffolding Southern Ltd.

To allow unhindered renewal of the old roof along with access for internal works to replace the ceiling in the main building, a large scale bespoke temporary roof was provided along with some large internal scaffolds.

Negating the need of 450T of ballast – or 18 truck loads

During the first stage, the goal was to erect the internal birdcage measuring 37m long x 18m wide x 12m high using over 250 tonnes of scaffolding, within 3 weeks. The work was being undertaken during the first Covid-19 lockdown in the UK, therefore, care had to be taken to observe the Government’s Covid-19 guidelines. This proved challenging in maintaining social distancing, in particular when working at heights.

The second phase of the project was to erect a temporary roof measuring 52m long x 42m wide with additional buttresses for an unsupported span of 38.5m in the centre section of the roof.

A unique ‘Platypus’ percussion anchor point system was used to secure the free-standing structure at ground level.  This unique lightweight and corrosion resistant anchor shaved weeks off the build programme, which otherwise would have required around 450 tonnes of ballast at the base of the scaffolding around the perimeter.

Due to the sheer size of the truss beams, the roof bays had to be skilfully assembled at ground level on special rigs by Ideal Scaffolding Southern Ltd, then lifted into position on top of the support scaffold by a crane.  This meant the roof was assembled, lifted into position (over a 3-lift programme) and fully sheeted in situ over a staggered 4-week period to maximise safety and productivity.

The Keder roofing sheets supplied by George Roberts was manufactured exactly to size for best fit using a 610g/m flame retardant PVC material providing a watertight barrier, meaning roofing works would continue throughout the project, regardless of weather conditions.

the UK's largest bespoke temporary roof

The X Factor

For most temporary roof applications, our standard 0.75m beam is more than sufficient, but because of the very large span requirement (42m) on this project, we needed to specify the heavier duty 1.3m deep X Beam – a first for George Roberts and Ideal Scaffolding.  This also allowed productivity to be maintained using 3.07m & 2.57m bay widths throughout. Without having X Beams in our offering, this project simply wouldn’t have been possible.

“The project was supported by George Roberts Ltd, who provided an invaluable service to supply all temporary roofing and scaffolding equipment needed. The flexibility & professionalism that the team of George Roberts demonstrated during the planning and execution of the project, proved to be a key component in its success.  At the time of the project, the temporary roof was one of the largest in the country.”  Darren Lee, the owner at Ideal Scaffolding Southern Ltd.

Challenges

The main challenges for George Roberts Ltd were around the rapid supply of over 250 tonnes of equipment, 200 miles from our Liverpool depot over multiple loads.

There were also engineering challenges due to the size of the building and roof span required, and also, tying into the structure was not permitted, meaning all supporting scaffolds needed to be free-standing.

The scheme was expertly engineered by Optima Scaffold Designs in Bristol.  Due to the very large span required, the UBIX temporary roof was designed utilising 1.3m deep aluminium X Beams. The roof was staggered in section to follow the natural plan size of the building which ranged in overall cover width from 34m to 44m.

For this project George Roberts Ltd had to call on the services of Alan White Design and our licensed beam manufacturers Apollo to expertly engineer a brand new 18-degree Ridge Beam to form the main duo-pitch roof truss structure, along with the design of a bespoke aluminium diagonal brace and tension bar system to suit this gigantic free-standing structure.

This represents a significant investment which will ensure Service personnel continue to have access to high quality sports facilities on the defence estate.

At the time of this project in 2020 the external scaffolding at Tidworth boasted the biggest unsupported span within a temporary roof standing anywhere in the UK.

Stats

Project comprised with earthworks, groundworks, drainage, reinforced concrete works for foundation slabs and external works to various types of accommodation blocks. Associated external works include access roads, footpaths, car parks, hardstanding, street furniture and lighting, bin stores, cycle racks and areas of hard and soft landscaping.

  • The overall plan cover size provided for this project on time and on budget was in excess of 2000m²
  • The building was over 40 metres in width and all supporting scaffolding had to be completely free standing.
  • Temporary roof covering a whopping 52m long x 42m wide.
  • Each of the 19 trusses weighed up to 2.6 tonnes.
  • Delivered over 250 tonnes of scaffolding equipment to site.
  • The structure was fully weather contained in situ using our popular 610g/m² Flame Retardant PVC sheeting material that was tailored exactly to length to provide an exact fit.
  • Tidworth project was one of the UK’s largest free-standing Temporary Roof structures.
  • Project valued in excess of £15 billion

Equipment and Types of Scaffolding Supplied

George Roberts supplied scaffolding tubes, fittings, timber boards, Uniscaff Stair Tower & Loading Tower, flame retardant Power clad sheeting, aluminium X Beams and our UBIX temporary roof system.

 

Popular Categories

Latest posts

Staht signs US distribution deal for digital pull testing range

UK digital pull testing manufacturer Staht has appointed Diversified Fall Protection as its exclusive distributor in the United States. The agreement will see Diversified market,...

GKR scaffolders help save woman’s life at London project

A GKR Scaffolding site team has been praised after helping to save the life of a woman who collapsed outside a live London project. The...

King’s Award recognises Lee Marley Group’s training work

Lee Marley Group has received a King’s Award for Enterprise in recognition of its work to widen access to careers in construction. The large-scale construction...

Mock the Week star to host ScaffEx26 awards night

Comedian and television presenter Dara Ó Briain has been confirmed as the host of this year’s Scaffolding Excellence Awards. The awards evening will take place...

Wayne Connolly honoured as NASC opens 2026 awards entries

NASC has opened entries for the 2026 Scaffolding Excellence Awards, with this year’s apprentice category renamed in memory of former NASC president and CISRS...

TRAD UK launches charity campaign supporting Epilepsy Action

TRAD UK has launched a new fundraising campaign in support of Epilepsy Action, the national charity helping people and families affected by epilepsy. The 2026-27...

Scaffolding firms urged to review RIDDOR procedures as HSE consults on changes

The Health and Safety Executive has launched a consultation on proposed changes to the Reporting of Injuries, Diseases and Dangerous Occurrences Regulations 2013, known...

Scottish offshore workers urged to consider scaffolding careers

The Construction Industry Training Board is targeting workers from Scotland’s offshore energy sector as part of efforts to widen the construction talent pool and...

NASC warns members over online conduct in new media policy

The National Access and Scaffolding Confederation said the new Social Media and General Media Policy sets expectations for how its members, CISRS centres and...

Two workers killed in Spain after mast climbing platform collapse

Two workers have been killed following the collapse of a twin mast climbing work platform in Benidorm, Spain. The incident happened on Wednesday, 22 April,...

Spring Issue #29 | Past issues >>

Latest topics

Most popular ⚡︎

Wayne Connolly honoured as NASC opens 2026 awards entries

NASC has opened entries for the 2026 Scaffolding Excellence...

CISRS Accreditation Granted For Safety & Access Indian Training Center

  CISRS has awarded Safety & Access Ltd full overseas...

The Scaffolding Association adds free seminar on Scaffolding Ties to roadshow

Due to recent scaffold collapses from around the UK,...

GKR scaffolders help save woman’s life at London project

A GKR Scaffolding site team has been praised after...

TRAD UK launches charity campaign supporting Epilepsy Action

TRAD UK has launched a new fundraising campaign in...

Related articles

ADVERTISEMENTS
More from
Latest articles

HAKI CEO Sverker Lindberg to step down by 2027

HAKI Safety has confirmed that its President and CEO, Sverker Lindberg, will leave his...

Staht signs US distribution deal for digital pull testing range

UK digital pull testing manufacturer Staht has appointed Diversified Fall Protection as its exclusive...

GKR scaffolders help save woman’s life at London project

A GKR Scaffolding site team has been praised after helping to save the life...

King’s Award recognises Lee Marley Group’s training work

Lee Marley Group has received a King’s Award for Enterprise in recognition of its...

Mock the Week star to host ScaffEx26 awards night

Comedian and television presenter Dara Ó Briain has been confirmed as the host of...

Wayne Connolly honoured as NASC opens 2026 awards entries

NASC has opened entries for the 2026 Scaffolding Excellence Awards, with this year’s apprentice...