George Roberts at Betley Court Manor

- Advertisement -

Betley Court Manor House was a residential home, where 20 people lived. As the house was completely unsafe after a fire broke out, the project needed to be restored quickly and safely.

To restore the beloved grade II listed 18th-century manor house, scaffolders needed to protect the whole area from the elements, allowing the building to dry out after being drenched by 40 firefighters. Once dried, the building needed ongoing protection to allow the restoration work to be carried out unhindered. George Roberts was engaged to supply all scaffolding, access, and weather protection equipment to this important project.

Space on site was limited, meaning George Roberts drivers had to Hiab the equipment onto ground level, and to minimise impact on those who reside around the building, careful planning was required to maximise the delivery schedule.

Working closely with its customer and their design team to specify the 1.3m X Beams for the support structure, George Roberts provided full and open technical data during the design process. This helped them to act quickly and mobilise equipment to support our customer’s programme and budget.

Challenges

As the building had been completely destroyed by the fire, serious care had to be taken in order for the job to be undertaken safely. Consideration for the historical elements of the building also had to be a priority, as with any listed building restoration.

One of the complexities of the project was to design the temporary roof structure around the numerous chimneys where extra beam work was required to support the roof. The best solution for this was utilising its 1.3m deep X Beams.

George Roberts Ltd provided a full UBIX roof system and the Aluminium X Beams in both 750mm and 1300mm deep for the additional support to enable the whole structure to be covered for restoration to begin.

Stats:

  • A full UBIX Roof using 750mm X Beams, 450mm Deep Beams, 1300mm X Beams, Uniscaff StairtowersTubeFittings and Boards.
  • Our high stock holding with beams being manufactured in the UK meant we were able to react quickly and mobilise the equipment within 7 days, allowing MD to stay on track with their tight programme.
  • Scaffold Package is £600k. Overall project estimated to be appx £6m.

More here: https://georgeroberts.com/case-study/temporary-roof-project-at-betley-court-manor/

- Advertisement -

Popular Categories

Latest Magazine

Most Read This Week

Scaffolding work pipeline shrinks as construction starts drop 22%

Construction project starts have collapsed 22% with contract awards...

AT-PAC accelerates European expansion with strategic German launch

Scaffolding specialist establishes key operations in Germany as part...

Scaffolding industry celebrates at Manchester awards night

The UK scaffolding and access industry gathered in Manchester...

ScaffEx25 sets new attendance record in Manchester

ScaffEx25 has smashed previous records, drawing nearly 2,400 visitors...

Scottish scaffolding apprentices to compete at ScaffChamp 2026

A team of young scaffolders from Scotland and Northern...

Related Articles

Scaffolders voted UK’s toughest trade

Scaffolders have been crowned the UK’s toughest trade by their fellow workers, according to new research – although the public believes roofers deserve the title. The nationwide study, commissioned by TROJAN workwear, polled tradespeople...
- Advertisements -

Latest Topics

Scaffolders voted UK’s toughest trade

Scaffolders have been crowned the UK’s toughest trade by...

Company fined after worker dies in six-foot scaffold fall

A Lancashire sign-fitting company and its director have been...

ScaffEx25 sets new attendance record in Manchester

ScaffEx25 has smashed previous records, drawing nearly 2,400 visitors...

Scaffolding makes historic debut at WorldSkills Ireland 2025

Young scaffolders showcase their expertise as the trade is...
- Advertisement -