Harsco Helps To Hold Back The Water At A Jersey Dam

- Advertisement -

 

A project to refurbish a dam on the island of Jersey has highlighted the bespoke nature of the access equipment solutions which Harsco Infrastructure provides for its customers.

Harsco designed and installed a unique combination of suspended access platforms and a load bearing support gantry system (constructed from MkII shoring soldiers and scaffolding materials) to provide access to the entire inside face of the dam so that vital maintenance work could be completed.

First constructed in 1962, the Val de la Mare dam holds back 900 million litres of water, making it the second largest reservoir on the island. The concrete on the dam is suffering from an alkali aggregate reaction and this created the need for the inside face to be covered with a heavy-duty waterproof membrane to re-seal the dam. This will prolong the life of the dam for many years, but required the reservoir to be drained so that the inside face could be accessed.

“This was a very unusual and difficult project which is why a totally bespoke solution was required,” comments Harsco Project Manager Jon Herbert. “It is the first time the reservoir has ever been partially drained and the project had a very tight schedule as the reservoir needed to be refilled as soon as possible.

“The fact that the trades were working at height, and also above water, made this a very complex project. Access to the façade had to be from the walkway on top of the dam wall which was very narrow. This had to remain clear throughout the project to allow the waterproof membrane to be positioned and unrolled down the inner façade. This was achieved by designing a walk-though, ‘tunnel-like’ support structure from scaffolding and shoring MkII Soldier materials.”

Five suspended access cradles were suspended from the load bearing framework and four were fitted with motorised bogies which allowed them to traverse along the façade as well as up and down. This was made possible by a steel support track supported on the underside of the load-bearing framework structure. The fifth suspended access platform was a specially designed and fabricated horse-shoe shaped machine that provided access to the pump tower. This platform was specially designed with six separate winching units which were also supported by the load bearing framework structure. This arrangement of access platforms and egress to the top of the dam’s façade allowed both the team of membrane installers and concrete repair specialists complete access to the façade.

“It was a terrific piece of teamwork to get this project up and running,” comments Project Manager Nathan Clothier, of civil engineering contractor Jayen Ltd which was responsible for the refurbishment work. “We needed a real bespoke access solution to solve a difficult set of requirements. Harsco’s response was really well thought through and they were even able to build a test section of the support gantry for the project team to evaluate prior to work commencing. The schedule on this job was particularly tight so the access system had to be really effective and I’m happy to say that the suspended access platforms worked very well.”

Via: Press Release 

 

- Advertisement -

Popular Categories

Latest Magazine

Most Read This Week

ScaffChamp 2025: Teams Gather in Vilnius for Opening Day

The international scaffolding competition ScaffChamp 2025 has officially begun,...

Scaffolders voted UK’s toughest trade

Scaffolders have been crowned the UK’s toughest trade by...

Company fined after worker dies in six-foot scaffold fall

A Lancashire sign-fitting company and its director have been...

ScaffEx25 sets new attendance record in Manchester

ScaffEx25 has smashed previous records, drawing nearly 2,400 visitors...

AK Scaffolding to represent UK at Las Vegas scaffold competition

AK Scaffolding will represent the UK at the 2026...

Related Articles

Scaffolding makes historic debut at WorldSkills Ireland 2025

Young scaffolders showcase their expertise as the trade is included in the prestigious competition for the first time Scaffolding has been included in WorldSkills Ireland for the first time, marking a significant milestone for...
- Advertisements -

Latest Topics

Scaffolders urged to check skin for melanoma signs

Campaign uses striking imagery to promote early detection among...

ScaffChamp 2026 dates confirmed as registration prepares to open

Registration set to open for prestigious competition as organisers...

AK Scaffolding to represent UK at Las Vegas scaffold competition

AK Scaffolding will represent the UK at the 2026...

Scaffolders voted UK’s toughest trade

Scaffolders have been crowned the UK’s toughest trade by...
- Advertisement -