Ad
Wednesday, March 18, 2026

Harsco completes one of Europe’s largest scaffolding projects

ADVERTISEMENT
Getting your Trinity Audio player ready...

Harsco Infrastructure has announced the successful completion of what was, at the time it began, one of the largest scaffolding projects of its type in Europe.

The 3-year, £35M project has enabled a major programme of cleaning and refurbishment work to be completed on the roof at London’s Victoria Station, while allowing the station to retain its normal schedule of operations.

As a Grade Two listed building. the roof itself is widely recognised as an engineering masterpiece which dates back to 1865 and had undergone a series of ad-hoc repair works over the years. Along with the fact that the project was far more complex than originally envisaged, this presented Harsco with a series of unique challenges.

“The listed nature of the building and the fact that the station had to remain operational meant that we had to work in very close collaboration with both May Gurney, who were the main contractor, and also with Network Rail,” comments Harsco’s Project Engineering Manager, Brendan Fox.

“We erected three temporary roof structures, one in each roof barrel and concourse. These were multi-functional and provided a weatherproof, dustproof, acoustic structure which also gave support for the access scaffold above, so that blasting, painting and glazing works could be carried out during normal working hours. In the Eastern barrel a 31.4m mansard roof structure spanning four platforms was built during the day, above a construction gantry. At night this was then pushed out over the platforms in 24-metre sections. These ran on steel tracks which were supported on steel grillages and towers over the platforms.

In the Western barrel a part-mobile and part-static mono-pitch temporary roof structure was built. The static section was supported at one end on specially designed gallows brackets bolted to the West wall and this allowed the shops, bars and restaurants below to carry on business as usual. The spans were maximised wherever appropriate so that as much platform space as possible was retained for the full operational use of the station. This helped Harsco meet the challenge of maximising pedestrian footfall and passenger access to maintain the rain service.

“There were many challenges that arose from working in a live environment, “ adds Brendan Fox. “These included having very limited storage facilities and only being able to complete certain works at night. However with careful and detailed planning, plus the use of innovative solutions to the various challenges that arose, we succeeded in completing the project to everyone’s satisfaction and with no impact on train services.”

ADVERTISEMENT

Popular Categories

Latest posts

Barking Riverside expansion approved to deliver up to 20,000 homes

Revised outline plans for the Barking Riverside development in east London have been approved by the London Borough of Barking & Dagenham, enabling a...

Beyond the Hype: Where AI Actually Delivers Value for a Scaffold Business

AI can draft a site report in seconds, but it cannot plumb a standard or assume legal accountability. Scaffold businesses operate in a world...

New data shows construction workforce becoming younger and more skilled

New data from the Construction Skills Certification Scheme (CSCS) suggests the profile of the UK construction workforce is changing, with more young people entering...

Teen in coma after scaffolding accident on Fife housing project

A teenager remains in a coma after being seriously injured by falling scaffolding material while working at a housing block in Kirkcaldy. Brodie Thomson, 16,...

NASC gains formal role in CITB levy consensus process

The National Access and Scaffolding Confederation (NASC) has been granted Prescribed Organisation status by the Construction Industry Training Board (CITB), giving the trade body...

New platform aims to bring instant scaffolding quotes to UK market

A London-based roofing contractor has launched a new digital platform designed to simplify how scaffolding is sourced and booked. The platform, called ScaffLink, allows homeowners...

Inflatable tent system installed at height during £38m Bolton hospital project

Robertson Construction has installed a series of inflatable roofing tents as part of a major redevelopment programme at the Royal Bolton Hospital. The air-filled structures...

PepsiCo begins £3.6m rooftop solar project at Leicester distribution centre

PepsiCo UK has begun construction of a £3.6 million rooftop solar installation at its Southern Region Distribution Centre in Leicester. The project will see solar...

Cardiff clears path for Wales’ tallest tower

Plans for a landmark 178-metre tower next to Cardiff Central Station and the Principality Stadium have secured planning approval, paving the way for what...

Speller Metcalfe appointed for £28m Atherstone leisure centre redevelopment

North Warwickshire Borough Council has appointed construction firm Speller Metcalfe as the principal contractor for a £28 million redevelopment of the leisure centre in...

Latest news

Magazine

Spring Issue #29 | Past issues >>

Trending now ⚡︎

Teen in coma after scaffolding accident on Fife housing project

A teenager remains in a coma after being seriously...

Second chances and scaffolding: the man giving ex-offenders a route back into work

When Aaron King talks about turning points, he does...

New platform aims to bring instant scaffolding quotes to UK market

A London-based roofing contractor has launched a new digital...

Scaffold supplier TRAD UK flags potential price adjustments as global tensions rise

TRAD UK has warned customers that external market pressures...

Young workers least likely to discuss mental health, research shows

More than one in three UK tradespeople say their...

Related articles

Latest topics

Pay gap pushing scaffolders from New Zealand to Australia

Construction firms in New Zealand are facing a growing...

Barking Riverside expansion approved to deliver up to 20,000 homes

Revised outline plans for the Barking Riverside development in...

New data shows construction workforce becoming younger and more skilled

New data from the Construction Skills Certification Scheme (CSCS)...
ADVERTISEMENTS