Harsco completes one of Europe’s largest scaffolding projects

ADVERTISEMENT

Harsco Infrastructure has announced the successful completion of what was, at the time it began, one of the largest scaffolding projects of its type in Europe.

The 3-year, £35M project has enabled a major programme of cleaning and refurbishment work to be completed on the roof at London’s Victoria Station, while allowing the station to retain its normal schedule of operations.

As a Grade Two listed building. the roof itself is widely recognised as an engineering masterpiece which dates back to 1865 and had undergone a series of ad-hoc repair works over the years. Along with the fact that the project was far more complex than originally envisaged, this presented Harsco with a series of unique challenges.

“The listed nature of the building and the fact that the station had to remain operational meant that we had to work in very close collaboration with both May Gurney, who were the main contractor, and also with Network Rail,” comments Harsco’s Project Engineering Manager, Brendan Fox.

“We erected three temporary roof structures, one in each roof barrel and concourse. These were multi-functional and provided a weatherproof, dustproof, acoustic structure which also gave support for the access scaffold above, so that blasting, painting and glazing works could be carried out during normal working hours. In the Eastern barrel a 31.4m mansard roof structure spanning four platforms was built during the day, above a construction gantry. At night this was then pushed out over the platforms in 24-metre sections. These ran on steel tracks which were supported on steel grillages and towers over the platforms.

In the Western barrel a part-mobile and part-static mono-pitch temporary roof structure was built. The static section was supported at one end on specially designed gallows brackets bolted to the West wall and this allowed the shops, bars and restaurants below to carry on business as usual. The spans were maximised wherever appropriate so that as much platform space as possible was retained for the full operational use of the station. This helped Harsco meet the challenge of maximising pedestrian footfall and passenger access to maintain the rain service.

“There were many challenges that arose from working in a live environment, “ adds Brendan Fox. “These included having very limited storage facilities and only being able to complete certain works at night. However with careful and detailed planning, plus the use of innovative solutions to the various challenges that arose, we succeeded in completing the project to everyone’s satisfaction and with no impact on train services.”

SM Newsdesk
SM Newsdeskhttps://www.scaffmag.com
The staff at ScaffMag.com the leading scaffolding site for a digital generation.

Most popular ↑

Two taken to hospital after Streatham scaffolding collapse

Two people were rescued before firefighters arrived after scaffolding collapsed on Streatham High Road on 25 October. Both were taken to hospital.

Government announces paternity pay for self-employed dads

Self-employed fathers and partners are to receive two weeks of support under government plans, with payments currently worth up to £194 a week.

Two workers hospitalised after partial collapse at Banbury construction site

Two workers were taken to hospital after a partial collapse at a Banbury construction site on 21 October. HSE says it is making enquiries, according to Construction Enquirer.

PHD Access announces €37.7m investment for European expansion

PHD Access has announced a €37.7m investment from MML Ireland and Goodbody to support European growth and acquisitions, subject to regulatory approval.

Belfast scaffolding firm fined after driver killed by falling board

HSENI found inadequate exclusion zone controls after Samuel Magill was struck by a falling metal scaffold board during dismantling work in Belfast.

Latest news

Budget 2026: what it means for scaffolding firms

Fuel duty relief, higher minimum wages and apprenticeship measures feature in Budget 2026, as NASC warns investment promises must translate into construction work.
- Advertisement -
More from

Budget 2026: what it means for scaffolding firms

Fuel duty relief, higher minimum wages and apprenticeship measures feature in Budget 2026, as NASC warns investment promises must translate into construction work.

Alimak targets £6m savings as construction profits fall

Alimak sets out SEK80m (about £6m) annual savings target as construction profits fall, while reporting positive UK parts and service demand.

Storm Austen brings amber wind warning for south-west England

An amber wind warning runs from 01:00 to 10:00 BST on Friday 23 October, with gusts around 80mph possible on exposed headlands.

HAKI scaffolding earnings fall as UK demand stays weak

HAKI Safety reports lower Q3 scaffolding earnings as UK demand stays soft, delayed orders affect sales and Combisafe integration weighs on the group.
Latest articles