Ad
Friday, November 14, 2025

Harsco completes one of Europe’s largest scaffolding projects

ADVERTISEMENT

Harsco Infrastructure has announced the successful completion of what was, at the time it began, one of the largest scaffolding projects of its type in Europe.

The 3-year, £35M project has enabled a major programme of cleaning and refurbishment work to be completed on the roof at London’s Victoria Station, while allowing the station to retain its normal schedule of operations.

As a Grade Two listed building. the roof itself is widely recognised as an engineering masterpiece which dates back to 1865 and had undergone a series of ad-hoc repair works over the years. Along with the fact that the project was far more complex than originally envisaged, this presented Harsco with a series of unique challenges.

“The listed nature of the building and the fact that the station had to remain operational meant that we had to work in very close collaboration with both May Gurney, who were the main contractor, and also with Network Rail,” comments Harsco’s Project Engineering Manager, Brendan Fox.

“We erected three temporary roof structures, one in each roof barrel and concourse. These were multi-functional and provided a weatherproof, dustproof, acoustic structure which also gave support for the access scaffold above, so that blasting, painting and glazing works could be carried out during normal working hours. In the Eastern barrel a 31.4m mansard roof structure spanning four platforms was built during the day, above a construction gantry. At night this was then pushed out over the platforms in 24-metre sections. These ran on steel tracks which were supported on steel grillages and towers over the platforms.

In the Western barrel a part-mobile and part-static mono-pitch temporary roof structure was built. The static section was supported at one end on specially designed gallows brackets bolted to the West wall and this allowed the shops, bars and restaurants below to carry on business as usual. The spans were maximised wherever appropriate so that as much platform space as possible was retained for the full operational use of the station. This helped Harsco meet the challenge of maximising pedestrian footfall and passenger access to maintain the rain service.

“There were many challenges that arose from working in a live environment, “ adds Brendan Fox. “These included having very limited storage facilities and only being able to complete certain works at night. However with careful and detailed planning, plus the use of innovative solutions to the various challenges that arose, we succeeded in completing the project to everyone’s satisfaction and with no impact on train services.”

ADVERTISEMENT

Popular Categories

Latest news

Construction output edges up just 0.1% in the third quarter

Construction output in Great Britain rose by only 0.1% in the third quarter of 2025, according to new figures from the Office for National...

Hong Kong launches construction safety drive after serious incidents

Hong Kong has begun a city-wide crackdown on unsafe practices in the construction sector after a series of fatal and serious accidents. The Labour Department...

4D Structures and PERI UK join forces to build one of Glasgow’s tallest towers

A 21-storey student accommodation building is rising on the banks of the River Clyde, as specialist contractor 4D Structures partners with PERI UK on...

ScaffPlan launches 3D scaffold design tool within SketchUp

ScaffPlan has unveiled a new tool that lets scaffolders design and plan scaffolding projects directly in the popular 3D modelling platform SketchUp. The software, called...

Scaffolding contractors boost profits with building wrap partnership programme

Scaffolding contractors are adding a new revenue stream to their businesses through a partnership programme that allows them to profit from building wraps without...

Equinor awards £1.25bn scaffolding and maintenance contracts for onshore plants

Equinor has signed new long-term framework agreements for insulation, scaffolding, and surface treatment (ISS) services across its six onshore plants in Norway. The contracts, worth...

Scaffolders’ tough day as runaway lorry crashes into house

A lorry loaded with scaffolding has collided with a house near Bristol, damaging two cars before coming to rest against the property. The incident happened...

Kirtanlal and Al Masaood partnership set to reshape the Middle East scaffolding sector

Kirtanlal Scaffolding & Formwork has announced a new strategic partnership with Abu Dhabi-based Al Masaood Group, one of the UAE’s most established and respected...

ULMA Construction eyes UK expansion with Des Moore leading setup

European scaffolding and formwork giant ULMA Construction is preparing to enter the UK market, with industry leader Des Moore steering the launch phase. The Spanish-based...

PERI UK’s Terry Hall recognised as ‘Unsung Hero’ for driving formwork safety reform

Terry Hall, Field Services Manager at PERI UK, has been honoured with the ‘Unsung Hero’ award at this year’s CONSTRUCT Day for his work...

Latest news

ADVERTISEMENT

The magazine

Issue 27 | Past issues >>

Popular

Equinor awards £1.25bn scaffolding and maintenance contracts for onshore plants

Equinor has signed new long-term framework agreements for insulation,...

ScaffPlan launches 3D scaffold design tool within SketchUp

ScaffPlan has unveiled a new tool that lets scaffolders...

Kirtanlal and Al Masaood partnership set to reshape the Middle East scaffolding sector

Kirtanlal Scaffolding & Formwork has announced a new strategic...

Scaffolders’ tough day as runaway lorry crashes into house

A lorry loaded with scaffolding has collided with a...

Scaffolding contractors boost profits with building wrap partnership programme

Scaffolding contractors are adding a new revenue stream to...

Related articles

Scaffolding Collapses Onto Van in North London

A large section of scaffolding collapsed onto a van on Stoke Newington Church Street in north London on Wednesday morning, trapping a driver underneath. The incident happened at around 07:30 am on April 16...
ADVERTISEMENTS

Latest topics

In Pictures: GKR completes major temporary roof structure at HS2 Euston

GKR Scaffolding has completed a large temporary roof structure...

Construction output edges up just 0.1% in the third quarter

Construction output in Great Britain rose by only 0.1%...

Hong Kong launches construction safety drive after serious incidents

Hong Kong has begun a city-wide crackdown on unsafe...

4D Structures and PERI UK join forces to build one of Glasgow’s tallest towers

A 21-storey student accommodation building is rising on the...
ADVERTISEMENTS