Ad
Saturday, November 8, 2025

Chris Sedgeman Scaffolding Ltd completes challenging Cornish Viaduct project. 

ADVERTISEMENT

The Hayle Viaduct

The Hayle Railway, opened in 1837, it was situated in front of the magnificent viaduct, built in 1852 by the West Cornwall Railway to I. K. Brunel’s design. The original viaduct, which was made of wooden trestle, stood for 34 years before being rebuilt in granite in 1886. Hayle viaduct is very unique due to having three roads that run under it.

Infrastructure contractors Dyer & Butler enlisted Chris Sedgeman Scaffolding Ltd to erect a 300m long x 12m wide x 12m high scaffold for major refurbishment works on the viaduct. Approximately 1,000 life expired deck timbers, old track, ballast, 4,500 rivets and existing handrail needed to be replaced within a challenging 6 week period.

Work Commenced

NASC registered scaffolding contractors Chris Sedgeman Scaffolding Ltd commenced works with the main access scaffold which was 300m long x 12m wide x 12m high. Using the time saving Plettac Contur scaffold system the scaffold was erected to the outside face of the viaduct plus in-between each of it’s 37 piers.

250 x 780mm deep beams were used to bridge under the viaduct, in total over 10,000 system components, 5,500 short boards and a 1000 sheets of ply-wood were used. Six access staircases and a secondary birdcage came together to complete this impressive structure.

Eight highly skilled scaffolding professionals from Chris Sedgeman Scaffolding Ltd were given the task to erect the main scaffold working twelve hour day shifts completing the structure in five weeks. Once railway line closures were in-place four men were on day shifts and four on nights.

A rolling temporary roof was also erected as Dyer & Butler had only 16 days to complete the works. The roof was to enable the client to remove and renew approximately 1000 sleepers, old track and ballast. Chris Sedgeman Scaffolding Ltd were rolling on average 25m a shift and the roof was erected and dismantled in 6 days.

Chris Sedgeman Scaffolding Ltd

Once the line re-opened, scaffolders then shrink-wrapped the underside of the track and the sides of the viaduct for replacing steel work and repainting the whole viaduct. These works are still on going.

Project Challenges

  • Timescales in which to erect the scaffolding.
  • The viaduct curved for 10m over the length of the viaduct.
  • Access to the site was very restricted and difficult to deliver scaffolding equipment.
  • Working over public roads had to allow for traffic with stop go boards.

Do you have an interesting project you would like to share ? Drop us an email 


ADVERTISEMENT

Popular Categories

Latest news

ULMA Construction eyes UK expansion with Des Moore leading setup

European scaffolding and formwork giant ULMA Construction is preparing to enter the UK market, with industry leader Des Moore steering the launch phase. The Spanish-based...

PERI UK’s Terry Hall recognised as ‘Unsung Hero’ for driving formwork safety reform

Terry Hall, Field Services Manager at PERI UK, has been honoured with the ‘Unsung Hero’ award at this year’s CONSTRUCT Day for his work...

Scaffolders urged to tighten safety as climate change brings fiercer storms

Extreme weather is exposing poor practices across the scaffolding industry, as insurance specialists urge contractors to tighten safety procedures in response to increasingly severe...

Connolly Scaffolding unveils major new Salford base as part of multi-million-pound expansion

Connolly Scaffolding has completed a major expansion with the opening of a new 26,000 sq ft warehouse and yard in Salford – a move...

Surge in construction apprenticeships as CITB support drives 61% rise

The Construction Industry Training Board (CITB) has reported a sharp rise in apprenticeship starts, with more than 1,500 new apprentices supported by its New...

URTIM powers Turkey’s first floating gas platform

Turkey has taken a major step towards energy independence with the completion of its first floating natural gas production platform, the Osman Gazi. At the...

CISRS announces suite of new safety and inspection courses

The Construction Industry Scaffolders Record Scheme (CISRS) has announced a series of new and updated training courses aimed at improving safety, technical standards, and...

House-building recovery delayed until 2029, industry warns

The Construction Products Association warns UK house-building will not recover to pre-pandemic levels until 2029 or 2030, urging government support for first-time buyers to prevent further insolvencies and job losses.

Staht secures largest ever distribution deal with Leach’s

One of the UK’s leading testing technology firms, Staht, has announced its largest ever distribution agreement after joining forces with Leach’s. The partnership will expand...

Avontus to host free webinars on digital scaffold management this November

Avontus Software has announced a series of free, live webinars in November designed to help contractors overcome the everyday challenges of tracking and managing...

Latest news

ADVERTISEMENT

The magazine

Issue 27 | Past issues >>

Popular

CISRS announces suite of new safety and inspection courses

The Construction Industry Scaffolders Record Scheme (CISRS) has announced...

URTIM powers Turkey’s first floating gas platform

Turkey has taken a major step towards energy independence...

Connolly Scaffolding unveils major new Salford base as part of multi-million-pound expansion

Connolly Scaffolding has completed a major expansion with the...

House-building recovery delayed until 2029, industry warns

The Construction Products Association warns UK house-building will not recover to pre-pandemic levels until 2029 or 2030, urging government support for first-time buyers to prevent further insolvencies and job losses.

Scaffolders urged to tighten safety as climate change brings fiercer storms

Extreme weather is exposing poor practices across the scaffolding...

Related articles

ITP Appoints New Sales Director to Propel Growth Strategy

Industrial Textiles and Plastics (ITP) Ltd, a leading manufacturer of scaffold sheeting and related materials, has announced the appointment of Matt Thompson as Sales Director.  The move comes as part of ITP's strategic plan...
ADVERTISEMENTS

Latest topics

Kirtanlal and Al Masaood partnership set to reshape the Middle East scaffolding sector

Kirtanlal Scaffolding & Formwork has announced a new strategic...

ULMA Construction eyes UK expansion with Des Moore leading setup

European scaffolding and formwork giant ULMA Construction is preparing...

Scaffolders urged to tighten safety as climate change brings fiercer storms

Extreme weather is exposing poor practices across the scaffolding...
ADVERTISEMENTS