Chris Sedgeman Scaffolding Ltd completes challenging Cornish Viaduct project. 

ADVERTISEMENT

The Hayle Viaduct

The Hayle Railway, opened in 1837, it was situated in front of the magnificent viaduct, built in 1852 by the West Cornwall Railway to I. K. Brunel’s design. The original viaduct, which was made of wooden trestle, stood for 34 years before being rebuilt in granite in 1886. Hayle viaduct is very unique due to having three roads that run under it.

Infrastructure contractors Dyer & Butler enlisted Chris Sedgeman Scaffolding Ltd to erect a 300m long x 12m wide x 12m high scaffold for major refurbishment works on the viaduct. Approximately 1,000 life expired deck timbers, old track, ballast, 4,500 rivets and existing handrail needed to be replaced within a challenging 6 week period.

Work Commenced

NASC registered scaffolding contractors Chris Sedgeman Scaffolding Ltd commenced works with the main access scaffold which was 300m long x 12m wide x 12m high. Using the time saving Plettac Contur scaffold system the scaffold was erected to the outside face of the viaduct plus in-between each of it’s 37 piers.

250 x 780mm deep beams were used to bridge under the viaduct, in total over 10,000 system components, 5,500 short boards and a 1000 sheets of ply-wood were used. Six access staircases and a secondary birdcage came together to complete this impressive structure.

Eight highly skilled scaffolding professionals from Chris Sedgeman Scaffolding Ltd were given the task to erect the main scaffold working twelve hour day shifts completing the structure in five weeks. Once railway line closures were in-place four men were on day shifts and four on nights.

A rolling temporary roof was also erected as Dyer & Butler had only 16 days to complete the works. The roof was to enable the client to remove and renew approximately 1000 sleepers, old track and ballast. Chris Sedgeman Scaffolding Ltd were rolling on average 25m a shift and the roof was erected and dismantled in 6 days.

Chris Sedgeman Scaffolding Ltd

Once the line re-opened, scaffolders then shrink-wrapped the underside of the track and the sides of the viaduct for replacing steel work and repainting the whole viaduct. These works are still on going.

Project Challenges

  • Timescales in which to erect the scaffolding.
  • The viaduct curved for 10m over the length of the viaduct.
  • Access to the site was very restricted and difficult to deliver scaffolding equipment.
  • Working over public roads had to allow for traffic with stop go boards.

Do you have an interesting project you would like to share ? Drop us an email 


Most popular ↑

WorkSafe to strip SARNZ of scaffolding certification role after 20 years

New Zealand's workplace safety regulator will take control of...

Two construction workers killed in falls on successive days

Fatal incidents at construction sites in London and Birmingham have prompted separate investigations involving police and the Health and Safety Executive.

Falls from height account for quarter of all work deaths, HSE says

Falls from height caused 31 worker deaths in Great...

Two seriously injured after scaffold tower topples on busy London street

A London construction company and its sole director have been fined after a mobile scaffold tower overturned on Putney High Street, seriously injuring two members of the public.

Construction output falls again in May as repair and maintenance work drops

Monthly construction output in Great Britain fell by 0.8%...

Latest news

ADVERTISEMENT
More from
Latest articles

Scaffold and access industry heads to Nashville for SAIA Convention

The Scaffold & Access Industry Association will hold its annual convention at the JW...

Police appeal after ladder falls from scaffolding truck

Jersey Police are appealing for witnesses after the incident on Grande Route de la...

Alimak agrees $142m deal for Canadian access specialist Pro-Bel

The Canadian manufacturer of building maintenance units, suspended platforms and fall protection systems will...

SAA to publish free Australian scaffolding best practice guidelines

The Scaffolding Association Australia (SAA) will launch its Australian Best Practice Guidelines for Scaffolding...

WorkSafe to strip SARNZ of scaffolding certification role after 20 years

New Zealand's workplace safety regulator will take control of scaffolding Certificates of Competence from...

Falls from height account for quarter of all work deaths, HSE says

Falls from height caused 31 worker deaths in Great Britain in 2025/26, around a...

Construction output falls again in May as repair and maintenance work drops

Monthly construction output in Great Britain fell by 0.8% in May 2026, according to...

Two construction workers killed in falls on successive days

Fatal incidents at construction sites in London and Birmingham have prompted separate investigations involving police and the Health and Safety Executive.