Ad
Wednesday, September 17, 2025
18.6 C
London

The Voice of Scaffolding Since 2008  U.K. Edition

Chris Sedgeman Scaffolding Ltd completes challenging Cornish Viaduct project. 

- Advertisement -

The Hayle Viaduct

The Hayle Railway, opened in 1837, it was situated in front of the magnificent viaduct, built in 1852 by the West Cornwall Railway to I. K. Brunel’s design. The original viaduct, which was made of wooden trestle, stood for 34 years before being rebuilt in granite in 1886. Hayle viaduct is very unique due to having three roads that run under it.

Infrastructure contractors Dyer & Butler enlisted Chris Sedgeman Scaffolding Ltd to erect a 300m long x 12m wide x 12m high scaffold for major refurbishment works on the viaduct. Approximately 1,000 life expired deck timbers, old track, ballast, 4,500 rivets and existing handrail needed to be replaced within a challenging 6 week period.

Work Commenced

NASC registered scaffolding contractors Chris Sedgeman Scaffolding Ltd commenced works with the main access scaffold which was 300m long x 12m wide x 12m high. Using the time saving Plettac Contur scaffold system the scaffold was erected to the outside face of the viaduct plus in-between each of it’s 37 piers.

250 x 780mm deep beams were used to bridge under the viaduct, in total over 10,000 system components, 5,500 short boards and a 1000 sheets of ply-wood were used. Six access staircases and a secondary birdcage came together to complete this impressive structure.

Eight highly skilled scaffolding professionals from Chris Sedgeman Scaffolding Ltd were given the task to erect the main scaffold working twelve hour day shifts completing the structure in five weeks. Once railway line closures were in-place four men were on day shifts and four on nights.

A rolling temporary roof was also erected as Dyer & Butler had only 16 days to complete the works. The roof was to enable the client to remove and renew approximately 1000 sleepers, old track and ballast. Chris Sedgeman Scaffolding Ltd were rolling on average 25m a shift and the roof was erected and dismantled in 6 days.

Chris Sedgeman Scaffolding Ltd

Once the line re-opened, scaffolders then shrink-wrapped the underside of the track and the sides of the viaduct for replacing steel work and repainting the whole viaduct. These works are still on going.

Project Challenges

  • Timescales in which to erect the scaffolding.
  • The viaduct curved for 10m over the length of the viaduct.
  • Access to the site was very restricted and difficult to deliver scaffolding equipment.
  • Working over public roads had to allow for traffic with stop go boards.

Do you have an interesting project you would like to share ? Drop us an email 


- Advertisement -
Daniel Norton
Daniel Nortonhttps://www.scaffmag.com
Dan our Editor looks after Scaffmag's daily news service, he started his career as a scaffolder before creating and founding Scaffmag in 2008. Dan now spends his days visiting projects and writing about the scaffolding and access industry.

Popular Categories

Most Read This Week

Scaffolding industry celebrates at Manchester awards night

The UK scaffolding and access industry gathered in Manchester...

BBC Breakfast broadcasts live from ScaffEx25

BBC Breakfast was on air from Manchester this morning...

Global scaffolding industry unites with launch of IASA

One of the most significant international developments in the...

Scaffolding reaches Tyne Bridge parapets ahead of repainting works

The Tyne Bridge restoration project has reached a new...

Scaffolding industry set for landmark gathering at ScaffEx25

The scaffolding industry’s only dedicated trade exhibition opens its...

Related Articles

ITP Appoints New Sales Director to Propel Growth Strategy

Industrial Textiles and Plastics (ITP) Ltd, a leading manufacturer of scaffold sheeting and related materials, has announced the appointment of Matt Thompson as Sales Director.  The move comes as part of ITP's strategic plan...
- Advertisements -

Latest Topics

Scottish scaffolding apprentices to compete at ScaffChamp 2026

A team of young scaffolders from Scotland and Northern...

Pontefract scaffolding director hit with £100k Covid loan repayment order

A West Yorkshire scaffolding contractor has been ordered to...

Scaffolding boss raises £35k with sports auction

A charity auction of rare sports memorabilia has raised...

Pilosio announces UK partnership with JMAC Group and Creator at ScaffEx25

Pilosio UK has announced a new partnership with JMAC...
- Advertisement -