Ad
Saturday, November 15, 2025

Chris Sedgeman Scaffolding Ltd completes challenging Cornish Viaduct project. 

ADVERTISEMENT

The Hayle Viaduct

The Hayle Railway, opened in 1837, it was situated in front of the magnificent viaduct, built in 1852 by the West Cornwall Railway to I. K. Brunel’s design. The original viaduct, which was made of wooden trestle, stood for 34 years before being rebuilt in granite in 1886. Hayle viaduct is very unique due to having three roads that run under it.

Infrastructure contractors Dyer & Butler enlisted Chris Sedgeman Scaffolding Ltd to erect a 300m long x 12m wide x 12m high scaffold for major refurbishment works on the viaduct. Approximately 1,000 life expired deck timbers, old track, ballast, 4,500 rivets and existing handrail needed to be replaced within a challenging 6 week period.

Work Commenced

NASC registered scaffolding contractors Chris Sedgeman Scaffolding Ltd commenced works with the main access scaffold which was 300m long x 12m wide x 12m high. Using the time saving Plettac Contur scaffold system the scaffold was erected to the outside face of the viaduct plus in-between each of it’s 37 piers.

250 x 780mm deep beams were used to bridge under the viaduct, in total over 10,000 system components, 5,500 short boards and a 1000 sheets of ply-wood were used. Six access staircases and a secondary birdcage came together to complete this impressive structure.

Eight highly skilled scaffolding professionals from Chris Sedgeman Scaffolding Ltd were given the task to erect the main scaffold working twelve hour day shifts completing the structure in five weeks. Once railway line closures were in-place four men were on day shifts and four on nights.

A rolling temporary roof was also erected as Dyer & Butler had only 16 days to complete the works. The roof was to enable the client to remove and renew approximately 1000 sleepers, old track and ballast. Chris Sedgeman Scaffolding Ltd were rolling on average 25m a shift and the roof was erected and dismantled in 6 days.

Chris Sedgeman Scaffolding Ltd

Once the line re-opened, scaffolders then shrink-wrapped the underside of the track and the sides of the viaduct for replacing steel work and repainting the whole viaduct. These works are still on going.

Project Challenges

  • Timescales in which to erect the scaffolding.
  • The viaduct curved for 10m over the length of the viaduct.
  • Access to the site was very restricted and difficult to deliver scaffolding equipment.
  • Working over public roads had to allow for traffic with stop go boards.

Do you have an interesting project you would like to share ? Drop us an email 


ADVERTISEMENT

Popular Categories

Latest news

Construction output edges up just 0.1% in the third quarter

Construction output in Great Britain rose by only 0.1% in the third quarter of 2025, according to new figures from the Office for National...

Hong Kong launches construction safety drive after serious incidents

Hong Kong has begun a city-wide crackdown on unsafe practices in the construction sector after a series of fatal and serious accidents. The Labour Department...

4D Structures and PERI UK join forces to build one of Glasgow’s tallest towers

A 21-storey student accommodation building is rising on the banks of the River Clyde, as specialist contractor 4D Structures partners with PERI UK on...

ScaffPlan launches 3D scaffold design tool within SketchUp

ScaffPlan has unveiled a new tool that lets scaffolders design and plan scaffolding projects directly in the popular 3D modelling platform SketchUp. The software, called...

Scaffolding contractors boost profits with building wrap partnership programme

Scaffolding contractors are adding a new revenue stream to their businesses through a partnership programme that allows them to profit from building wraps without...

Equinor awards £1.25bn scaffolding and maintenance contracts for onshore plants

Equinor has signed new long-term framework agreements for insulation, scaffolding, and surface treatment (ISS) services across its six onshore plants in Norway. The contracts, worth...

Scaffolders’ tough day as runaway lorry crashes into house

A lorry loaded with scaffolding has collided with a house near Bristol, damaging two cars before coming to rest against the property. The incident happened...

Kirtanlal and Al Masaood partnership set to reshape the Middle East scaffolding sector

Kirtanlal Scaffolding & Formwork has announced a new strategic partnership with Abu Dhabi-based Al Masaood Group, one of the UAE’s most established and respected...

ULMA Construction eyes UK expansion with Des Moore leading setup

European scaffolding and formwork giant ULMA Construction is preparing to enter the UK market, with industry leader Des Moore steering the launch phase. The Spanish-based...

PERI UK’s Terry Hall recognised as ‘Unsung Hero’ for driving formwork safety reform

Terry Hall, Field Services Manager at PERI UK, has been honoured with the ‘Unsung Hero’ award at this year’s CONSTRUCT Day for his work...

Latest news

ADVERTISEMENT

The magazine

Issue 27 | Past issues >>

Popular

Equinor awards £1.25bn scaffolding and maintenance contracts for onshore plants

Equinor has signed new long-term framework agreements for insulation,...

ScaffPlan launches 3D scaffold design tool within SketchUp

ScaffPlan has unveiled a new tool that lets scaffolders...

Scaffolders’ tough day as runaway lorry crashes into house

A lorry loaded with scaffolding has collided with a...

Scaffolding contractors boost profits with building wrap partnership programme

Scaffolding contractors are adding a new revenue stream to...

4D Structures and PERI UK join forces to build one of Glasgow’s tallest towers

A 21-storey student accommodation building is rising on the...

Related articles

ITP Appoints New Sales Director to Propel Growth Strategy

Industrial Textiles and Plastics (ITP) Ltd, a leading manufacturer of scaffold sheeting and related materials, has announced the appointment of Matt Thompson as Sales Director.  The move comes as part of ITP's strategic plan...
ADVERTISEMENTS

Latest topics

In Pictures: GKR completes major temporary roof structure at HS2 Euston

GKR Scaffolding has completed a large temporary roof structure...

Construction output edges up just 0.1% in the third quarter

Construction output in Great Britain rose by only 0.1%...

Hong Kong launches construction safety drive after serious incidents

Hong Kong has begun a city-wide crackdown on unsafe...

4D Structures and PERI UK join forces to build one of Glasgow’s tallest towers

A 21-storey student accommodation building is rising on the...
ADVERTISEMENTS