Ad
Friday, December 12, 2025

Chris Sedgeman Scaffolding Ltd completes challenging Cornish Viaduct project. 

ADVERTISEMENT

The Hayle Viaduct

The Hayle Railway, opened in 1837, it was situated in front of the magnificent viaduct, built in 1852 by the West Cornwall Railway to I. K. Brunel’s design. The original viaduct, which was made of wooden trestle, stood for 34 years before being rebuilt in granite in 1886. Hayle viaduct is very unique due to having three roads that run under it.

Infrastructure contractors Dyer & Butler enlisted Chris Sedgeman Scaffolding Ltd to erect a 300m long x 12m wide x 12m high scaffold for major refurbishment works on the viaduct. Approximately 1,000 life expired deck timbers, old track, ballast, 4,500 rivets and existing handrail needed to be replaced within a challenging 6 week period.

Work Commenced

NASC registered scaffolding contractors Chris Sedgeman Scaffolding Ltd commenced works with the main access scaffold which was 300m long x 12m wide x 12m high. Using the time saving Plettac Contur scaffold system the scaffold was erected to the outside face of the viaduct plus in-between each of it’s 37 piers.

250 x 780mm deep beams were used to bridge under the viaduct, in total over 10,000 system components, 5,500 short boards and a 1000 sheets of ply-wood were used. Six access staircases and a secondary birdcage came together to complete this impressive structure.

Eight highly skilled scaffolding professionals from Chris Sedgeman Scaffolding Ltd were given the task to erect the main scaffold working twelve hour day shifts completing the structure in five weeks. Once railway line closures were in-place four men were on day shifts and four on nights.

A rolling temporary roof was also erected as Dyer & Butler had only 16 days to complete the works. The roof was to enable the client to remove and renew approximately 1000 sleepers, old track and ballast. Chris Sedgeman Scaffolding Ltd were rolling on average 25m a shift and the roof was erected and dismantled in 6 days.

Chris Sedgeman Scaffolding Ltd

Once the line re-opened, scaffolders then shrink-wrapped the underside of the track and the sides of the viaduct for replacing steel work and repainting the whole viaduct. These works are still on going.

Project Challenges

  • Timescales in which to erect the scaffolding.
  • The viaduct curved for 10m over the length of the viaduct.
  • Access to the site was very restricted and difficult to deliver scaffolding equipment.
  • Working over public roads had to allow for traffic with stop go boards.

Do you have an interesting project you would like to share ? Drop us an email 


ADVERTISEMENT

Popular Categories

Latest news

Brogan Group and Alimak strike global partnership

Brogan Group has formed a new strategic alliance with Alimak Group’s Construction Division, bringing its CAS Common Tower and Atlas gantry systems to a...

CITB announces major funding cuts despite £79m reserves

The Construction Industry Training Board has slashed grants and capped funding from January, citing rising demand but drawing criticism over timing and available reserves. The...

Trapped load drags labourer from scaffold as firms fined £800k

A labourer suffered life-changing injuries after being pulled from scaffolding during an unplanned lifting operation on a London refurbishment project. Two companies have been...

ITP opens new Product Development and Testing Facility at Yorkshire HQ

Yorkshire-based manufacturer ITP Ltd has opened a new Product Development and Testing Facility at its Easingwold headquarters following a major strategic investment. Clive Dickin, Chief...

CISRS reforms face delay as new QAC Chair withdraws

CISRS has reopened its search for a new Chair of the Quality Assurance Committee (QAC) after the organisation confirmed that Professor David Wooff, appointed...

Connolly Scaffolding strengthens partnership with TRAD UK in £3.5m investment

Connolly Scaffolding Ltd has agreed a further £3.5 million investment in TRAD UK’s Plettac Metrix system, reinforcing a partnership that has shaped both businesses...

Benetics introduces AI voice tool to cut site paperwork

A German construction technology firm has launched an AI-powered voice assistant designed to help site teams cut paperwork and speed up reporting. Benetics, based in...

Scaffolders at Sullom Voe Terminal walk out over pay dispute

Around 60 scaffolders, painters, insulators, and supervisors at the Sullom Voe Terminal in the Shetland Islands have staged a 24-hour walkout in an escalating...

Hong Kong contractors ‘hid unsafe scaffolding netting’ as tower fire toll rises to 151

Investigators in Hong Kong say contractors used unsafe scaffolding netting at the housing estate destroyed by last week’s deadly fire, and then tried to...

Costs climb again on Manchester Town Hall project as delays worsen

The cost of restoring Manchester Town Hall has risen by a further £95m, with completion now pushed back to spring 2027. The Grade I-listed...

Latest news

ADVERTISEMENT

The magazine

Issue 27 | Past issues >>

Popular

Trapped load drags labourer from scaffold as firms fined £800k

A labourer suffered life-changing injuries after being pulled from...

Brogan Group and Alimak strike global partnership

Brogan Group has formed a new strategic alliance with...

CISRS reforms face delay as new QAC Chair withdraws

CISRS has reopened its search for a new Chair...

CITB announces major funding cuts despite £79m reserves

The Construction Industry Training Board has slashed grants and...

ITP opens new Product Development and Testing Facility at Yorkshire HQ

Yorkshire-based manufacturer ITP Ltd has opened a new Product...

Related articles

ADVERTISEMENTS

Latest topics

New Construction and Scaffolding Academy launched to tackle skills shortages in Northern Ireland

A new Construction and Scaffolding Academy has been launched...

Brogan Group and Alimak strike global partnership

Brogan Group has formed a new strategic alliance with...

CITB announces major funding cuts despite £79m reserves

The Construction Industry Training Board has slashed grants and...

Trapped load drags labourer from scaffold as firms fined £800k

A labourer suffered life-changing injuries after being pulled from...
ADVERTISEMENTS