Chris Sedgeman Scaffolding Ltd completes challenging Cornish Viaduct project. 

ADVERTISEMENT

The Hayle Viaduct

The Hayle Railway, opened in 1837, it was situated in front of the magnificent viaduct, built in 1852 by the West Cornwall Railway to I. K. Brunel’s design. The original viaduct, which was made of wooden trestle, stood for 34 years before being rebuilt in granite in 1886. Hayle viaduct is very unique due to having three roads that run under it.

Infrastructure contractors Dyer & Butler enlisted Chris Sedgeman Scaffolding Ltd to erect a 300m long x 12m wide x 12m high scaffold for major refurbishment works on the viaduct. Approximately 1,000 life expired deck timbers, old track, ballast, 4,500 rivets and existing handrail needed to be replaced within a challenging 6 week period.

Work Commenced

NASC registered scaffolding contractors Chris Sedgeman Scaffolding Ltd commenced works with the main access scaffold which was 300m long x 12m wide x 12m high. Using the time saving Plettac Contur scaffold system the scaffold was erected to the outside face of the viaduct plus in-between each of it’s 37 piers.

250 x 780mm deep beams were used to bridge under the viaduct, in total over 10,000 system components, 5,500 short boards and a 1000 sheets of ply-wood were used. Six access staircases and a secondary birdcage came together to complete this impressive structure.

Eight highly skilled scaffolding professionals from Chris Sedgeman Scaffolding Ltd were given the task to erect the main scaffold working twelve hour day shifts completing the structure in five weeks. Once railway line closures were in-place four men were on day shifts and four on nights.

A rolling temporary roof was also erected as Dyer & Butler had only 16 days to complete the works. The roof was to enable the client to remove and renew approximately 1000 sleepers, old track and ballast. Chris Sedgeman Scaffolding Ltd were rolling on average 25m a shift and the roof was erected and dismantled in 6 days.

Chris Sedgeman Scaffolding Ltd

Once the line re-opened, scaffolders then shrink-wrapped the underside of the track and the sides of the viaduct for replacing steel work and repainting the whole viaduct. These works are still on going.

Project Challenges

  • Timescales in which to erect the scaffolding.
  • The viaduct curved for 10m over the length of the viaduct.
  • Access to the site was very restricted and difficult to deliver scaffolding equipment.
  • Working over public roads had to allow for traffic with stop go boards.

Do you have an interesting project you would like to share ? Drop us an email 


ADVERTISEMENT

Popular Categories

Latest posts

Robot named Douglas begins work on Tilbury Douglas site

Tilbury Douglas has begun using a humanoid robot to carry out administrative and data-collection tasks on a live construction site. The contractor says the...

HAKI reports sharp UK sales drop as construction starts stall

The Swedish-listed scaffolding and access safety group said UK revenues fell to SEK 52 million (£4.2 million) in the three months to 31 March,...

CISRS appoints Kathryn Bowe after delay to quality committee reforms

CISRS has appointed Kathryn Bowe as full-time Chair of its Quality Assurance Committee, months after the organisation was forced to restart recruitment for the...

NASC throws support behind first International Scaffolding and Access Day

NASC has thrown its support behind the first International Scaffolding and Access Day, as the UK industry prepares to join a new annual campaign...

Women completing construction apprenticeships triple since 2018, says CITB

The number of women completing construction apprenticeships has more than tripled since 2018, according to new figures from the Construction Industry Training Board (CITB). CITB...

Pilosio brings UK scaffolding safety model into Italian conference spotlight

Pilosio is set to use its presence at GIC Piacenza, a major construction trade event in northern Italy, this week to push a broader...

CISRS proposes single global scaffolding training standard by 2028

CISRS has set out plans to reform its Overseas Scaffolder Training Scheme, with proposals that would lead to a single global baseline training standard...

Scaffolder died nine months after building site fall, inquest told

A four-day inquest has opened into the death of a scaffolder who died nine months after falling more than three metres while working on...

Scaffolding industry backs all-apprentice team for ScaffChamp 2026

A team of seven apprentices from Scotland and Northern Ireland will compete at ScaffChamp 2026 in Vilnius this summer, after securing full backing from...

NASC chief to take on charity ride in tribute to former president

Clive Dickin, Group CEO of NASC and CISRS, is set to take part in the British Heart Foundation London to Brighton Bike Ride on...

Latest news

Spring Issue #29 | Past issues >>

Latest topics

Most popular ⚡︎

Scaffolder died nine months after building site fall, inquest told

A four-day inquest has opened into the death of...

Pilosio brings UK scaffolding safety model into Italian conference spotlight

Pilosio is set to use its presence at GIC...

CISRS proposes single global scaffolding training standard by 2028

CISRS has set out plans to reform its Overseas...

Women completing construction apprenticeships triple since 2018, says CITB

The number of women completing construction apprenticeships has more...

Robot named Douglas begins work on Tilbury Douglas site

Tilbury Douglas has begun using a humanoid robot to...

Related articles

ADVERTISEMENTS