Chris Sedgeman Scaffolding Ltd completes challenging Cornish Viaduct project. 

ADVERTISEMENT

The Hayle Viaduct

The Hayle Railway, opened in 1837, it was situated in front of the magnificent viaduct, built in 1852 by the West Cornwall Railway to I. K. Brunel’s design. The original viaduct, which was made of wooden trestle, stood for 34 years before being rebuilt in granite in 1886. Hayle viaduct is very unique due to having three roads that run under it.

Infrastructure contractors Dyer & Butler enlisted Chris Sedgeman Scaffolding Ltd to erect a 300m long x 12m wide x 12m high scaffold for major refurbishment works on the viaduct. Approximately 1,000 life expired deck timbers, old track, ballast, 4,500 rivets and existing handrail needed to be replaced within a challenging 6 week period.

Work Commenced

NASC registered scaffolding contractors Chris Sedgeman Scaffolding Ltd commenced works with the main access scaffold which was 300m long x 12m wide x 12m high. Using the time saving Plettac Contur scaffold system the scaffold was erected to the outside face of the viaduct plus in-between each of it’s 37 piers.

250 x 780mm deep beams were used to bridge under the viaduct, in total over 10,000 system components, 5,500 short boards and a 1000 sheets of ply-wood were used. Six access staircases and a secondary birdcage came together to complete this impressive structure.

Eight highly skilled scaffolding professionals from Chris Sedgeman Scaffolding Ltd were given the task to erect the main scaffold working twelve hour day shifts completing the structure in five weeks. Once railway line closures were in-place four men were on day shifts and four on nights.

A rolling temporary roof was also erected as Dyer & Butler had only 16 days to complete the works. The roof was to enable the client to remove and renew approximately 1000 sleepers, old track and ballast. Chris Sedgeman Scaffolding Ltd were rolling on average 25m a shift and the roof was erected and dismantled in 6 days.

Chris Sedgeman Scaffolding Ltd

Once the line re-opened, scaffolders then shrink-wrapped the underside of the track and the sides of the viaduct for replacing steel work and repainting the whole viaduct. These works are still on going.

Project Challenges

  • Timescales in which to erect the scaffolding.
  • The viaduct curved for 10m over the length of the viaduct.
  • Access to the site was very restricted and difficult to deliver scaffolding equipment.
  • Working over public roads had to allow for traffic with stop go boards.

Do you have an interesting project you would like to share ? Drop us an email 


ADVERTISEMENT

Popular Categories

Latest posts

Women completing construction apprenticeships triple since 2018, says CITB

The number of women completing construction apprenticeships has more than tripled since 2018, according to new figures from the Construction Industry Training Board (CITB). CITB...

Pilosio brings UK scaffolding safety model into Italian conference spotlight

Pilosio is set to use its presence at GIC Piacenza, a major construction trade event in northern Italy, this week to push a broader...

CISRS proposes single global scaffolding training standard by 2028

CISRS has set out plans to reform its Overseas Scaffolder Training Scheme, with proposals that would lead to a single global baseline training standard...

Scaffolder died nine months after building site fall, inquest told

A four-day inquest has opened into the death of a scaffolder who died nine months after falling more than three metres while working on...

Scaffolding industry backs all-apprentice team for ScaffChamp 2026

A team of seven apprentices from Scotland and Northern Ireland will compete at ScaffChamp 2026 in Vilnius this summer, after securing full backing from...

NASC chief to take on charity ride in tribute to former president

Clive Dickin, Group CEO of NASC and CISRS, is set to take part in the British Heart Foundation London to Brighton Bike Ride on...

Australian scaffolding group enters administration with over 650 jobs at risk

A group of companies linked to one of Australia’s largest scaffolding and formwork providers has entered voluntary administration, placing more than 650 jobs at...

Brogan Group expands scaffolding operations across Midlands and North

Brogan Group has expanded its scaffolding operations across the Midlands and North of England, extending its regional coverage to support projects in cities including...

Layher UK draws strong turnout at latest ‘Sizzle & Learn’ event

Layher UK has reported a strong turnout at its latest ‘Sizzle & Learn’ open morning, with attendees engaging closely with both product demonstrations and...

Fraud gang jailed for helping candidates cheat CITB safety tests

Three men have been sentenced for their role in a construction test fraud scheme that allowed more than 70 candidates to cheat health and...

Latest news

Spring Issue #29 | Past issues >>

Latest topics

Most popular ⚡︎

Scaffolder died nine months after building site fall, inquest told

A four-day inquest has opened into the death of...

CISRS proposes single global scaffolding training standard by 2028

CISRS has set out plans to reform its Overseas...

Scaffolding industry backs all-apprentice team for ScaffChamp 2026

A team of seven apprentices from Scotland and Northern...

Brogan Group expands scaffolding operations across Midlands and North

Brogan Group has expanded its scaffolding operations across the...

Fraud gang jailed for helping candidates cheat CITB safety tests

Three men have been sentenced for their role in...

Related articles

ADVERTISEMENTS