300-tonne scaffold installation enables refurb of Army’s top tactical trainer

ADVERTISEMENT

The recent refurbishment of one of the Army’s most significant training assets was made possible thanks to a team of fast-working scaffolders.

The Combined Arms Tactical Trainer (CATT), which is based at Warminster and uses networked simulators to enable soldiers to train in a virtual environment, underwent a major £1.9m upgrade over August and September.

The project was funded by Aspire Defence Limited (ADL), with on-site works managed by KBR-owned Aspire Defence Services Limited (ADSL), on behalf of the Defence Infrastructure Organisation (DIO). Aspire Defence is contracted by the MOD under Project Allenby/Connaught to build and maintain soldiers’ living and working accommodation at military garrisons across Salisbury Plain and at Aldershot.

The CATT refurb required the installation of the largest volume of scaffolding in the shortest possible timeframe for any Aspire life cycle project.

To enable access to the high ceiling within the CATT, around 324 tonnes of scaffolding were erected by contractors Ideal Scaffolding (Southern) Ltd and S&K Scaffolding Ltd – that’s over 14 miles of scaffold boards and more than 20,000 metres of tubing. In addition, four lorry loads of plywood timber were delivered to the site, so that each state-of-the-art simulator could be boarded up and protected during works. The wood has since been donated to the Ghurkhas for reuse.

Richard Pearce, Strategic Asset Manager (Aspire Defence Limited) and Brian Martin, Programme Manager (Aspire Defence Services Limited) on the scaffolding platform inside the CATT

Brian Martin, Programme Manager for ADSL Warminster & Larkhill Garrison, explained: “The scaffolders were exemplary. This was the largest internal job they had ever taken on and, in just one week, they completed an installation that would normally take a month. We had around forty contractors on site in a highly-controlled working environment, with excellent collaboration and productivity.”

Every simulator now has an individual fire alarm and air-conditioning controls, enhancing the safety and comfort of soldiers during training. The installation of over 600 energy-efficient LEDs (totalling 21 miles of cable) will also create substantial savings, dramatically reducing the power bill for the building.

Richard Pearce, Strategic Asset Manager for ADL, said: “Our customer will notice a huge difference, thanks to improved lighting levels and ventilation throughout the facility. This significant investment will ensure that the CATT remains a safe, compliant and economical asset for the Army, where soldiers can continue to gain vital operational skills.”

SM Newsdesk
SM Newsdeskhttps://www.scaffmag.com
The staff at ScaffMag.com the leading scaffolding site for a digital generation.

Most popular ↑

Contractor injured in fall during Port Kembla scaffold erection

ABC reports that a contractor was injured in a fall during scaffold erection at BlueScope’s Port Kembla steelworks on 29 October. SafeWork NSW inspectors visited the site.

Ibstock issues profit warning as brick demand weakens

Ibstock has reportedly cut production and lowered its earnings expectations after third-quarter brick sales fell short of forecasts.

Four injured in Taiwan market scaffold collapse

Taipei has halted work at the old Beitou market demolition site after a scaffold collapse injured four people. Investigations are continuing.

NIE Networks tenders £4.8m scaffolding framework for power infrastructure

NIE Networks is seeking scaffolding services across Northern Ireland's electricity infrastructure through two lots, with an initial four-year term and extension options.

PHD Access joins £190m Dungeness A decommissioning team

Aureos has named PHD Access as its scaffolding partner for the removal of eight 800-tonne boilers at Dungeness A. The overall programme is worth up to £190m.

Latest news

Scaffold firm fined £16,000 after trainee’s fatal fall

HSE found that safe zones had not been established when Michael Swales fell 5 metres from a partially erected scaffold near Ripon.
- Advertisement -
More from

Doka details climbing systems for Burj Binghatti tower

Doka’s project update sets out the climbing and edge-protection systems being used on Burj Binghatti, with a target of 1 floor a week.

PHD Access joins £190m Dungeness A decommissioning team

Aureos has named PHD Access as its scaffolding partner for the removal of eight 800-tonne boilers at Dungeness A. The overall programme is worth up to £190m.

Shield tackles hilltop access challenge in 19-day scaffold build

Shield erected access around the 38-metre Lansdowne Monument in 19 days despite a steep, rutted route that kept vans and lorries away from the hilltop.

Tyne Bridge to close for overhead scaffold deck installation

Advanced scaffolders will work around the clock during an October half-term closure to install a protection deck ahead of main arch restoration in early 2027.
Latest articles