JR Scaffold supports major refurbishment at remote Scottish Water site

ADVERTISEMENT

A remote water treatment site in Stirlingshire has undergone essential refurbishment work with the help of specialist scaffolding firm JR Scaffold.

The project at the Touch Water Treatment Works near Cambusbarron involved the installation of complex scaffolding structures around two elevated pipe bridges. The temporary works supported a 10-week programme of repairs to the bridges’ paintwork and structural fabric.

Commissioned by civil engineering contractor George Leslie on behalf of Scottish Water, the works took place at a challenging hillside location near the Touch Reservoirs. George Leslie constructed new roads to access the remote site, allowing materials and equipment to reach the high-ground facility.

Scaffolding was erected by a small team of experienced scaffolders, with each bridge taking around two weeks to complete. JR Scaffold’s Contracts Director, John Jack, led the operation.

“This was a fascinating project due to the remote location and the unusual shape of the pipe bridges,” said Mr Jack. “It’s the kind of complex job we’ve developed real expertise in, and we’re proud to have delivered it successfully alongside our long-standing partners at George Leslie.”

One of the bridges spans over water, requiring the use of a floating pontoon supplied by Coastworks to act as a stable working platform. This enabled scaffolders to install beam work beneath the structure. The second bridge was accessed from a nearby embankment, allowing scaffolding to be installed more conventionally.

The works are part of Scottish Water’s ongoing commitment to maintaining and upgrading key infrastructure across the country.

A spokesperson for George Leslie said the successful delivery of the project was made possible through close collaboration and logistical planning between all parties involved.

SM Newsdesk
SM Newsdeskhttps://www.scaffmag.com
The staff at ScaffMag.com the leading scaffolding site for a digital generation.

Most popular ↑

CISRS says CSCS notice was served to negotiate “from a stronger position”

NASC president Sarah Klieve says CISRS served CSCS notice to negotiate from a stronger position, as Build UK says the card rules don’t block other sectors.

86m Layher scaffold completed at Giotto’s Bell Tower

An 86-metre scaffold erected in just over four months will support a five-year restoration of the Florence landmark while keeping it open to visitors.

WorkSafe targets fall risks on New Zealand residential sites

WorkSafe New Zealand is inspecting residential sites from October to December, with falls from height accounting for 70% of construction prohibition notices.

Scaffold Innovations: GapClamp™

  Since the Work at Height Regulations 2005 came into...

Scottish scaffolding apprentices to compete at ScaffChamp 2026

A team of young scaffolders from Scotland and Northern...

Latest news

Lee Marley turnover hits £95.4m as profit falls

The masonry and scaffolding contractor invested £2.99m in scaffold and other fixed assets and entered 2026 with £131m of secured work.
- Advertisement -
More from

Tyne Bridge to close for overhead scaffold deck installation

Advanced scaffolders will work around the clock during an October half-term closure to install a protection deck ahead of main arch restoration in early 2027.

86m Layher scaffold completed at Giotto’s Bell Tower

An 86-metre scaffold erected in just over four months will support a five-year restoration of the Florence landmark while keeping it open to visitors.

Golden Gate Bridge prepares temporary access platforms for seismic works

Night-time lane closures will allow crews to lower access platforms beneath the roadway as work progresses on the bridge’s final seismic retrofit phase.

PERI scaffolding supports major HS2 Birmingham dive-under works

PERI UK has supplied access scaffolding, formwork and engineering support for a 400m-long concrete dive-under being built as part of HS2’s Delta Junction near Birmingham.
Latest articles