Harsco completes one of Europe’s largest scaffolding projects

ADVERTISEMENT

Harsco Infrastructure has announced the successful completion of what was, at the time it began, one of the largest scaffolding projects of its type in Europe.

The 3-year, £35M project has enabled a major programme of cleaning and refurbishment work to be completed on the roof at London’s Victoria Station, while allowing the station to retain its normal schedule of operations.

As a Grade Two listed building. the roof itself is widely recognised as an engineering masterpiece which dates back to 1865 and had undergone a series of ad-hoc repair works over the years. Along with the fact that the project was far more complex than originally envisaged, this presented Harsco with a series of unique challenges.

“The listed nature of the building and the fact that the station had to remain operational meant that we had to work in very close collaboration with both May Gurney, who were the main contractor, and also with Network Rail,” comments Harsco’s Project Engineering Manager, Brendan Fox.

“We erected three temporary roof structures, one in each roof barrel and concourse. These were multi-functional and provided a weatherproof, dustproof, acoustic structure which also gave support for the access scaffold above, so that blasting, painting and glazing works could be carried out during normal working hours. In the Eastern barrel a 31.4m mansard roof structure spanning four platforms was built during the day, above a construction gantry. At night this was then pushed out over the platforms in 24-metre sections. These ran on steel tracks which were supported on steel grillages and towers over the platforms.

In the Western barrel a part-mobile and part-static mono-pitch temporary roof structure was built. The static section was supported at one end on specially designed gallows brackets bolted to the West wall and this allowed the shops, bars and restaurants below to carry on business as usual. The spans were maximised wherever appropriate so that as much platform space as possible was retained for the full operational use of the station. This helped Harsco meet the challenge of maximising pedestrian footfall and passenger access to maintain the rain service.

“There were many challenges that arose from working in a live environment, “ adds Brendan Fox. “These included having very limited storage facilities and only being able to complete certain works at night. However with careful and detailed planning, plus the use of innovative solutions to the various challenges that arose, we succeeded in completing the project to everyone’s satisfaction and with no impact on train services.”

ADVERTISEMENT

Popular Categories

Latest posts

Pilosio brings UK scaffolding safety model into Italian conference spotlight

Pilosio is set to use its presence at GIC Piacenza, a major construction trade event in northern Italy, this week to push a broader...

CISRS proposes single global scaffolding training standard by 2028

CISRS has set out plans to reform its Overseas Scaffolder Training Scheme, with proposals that would lead to a single global baseline training standard...

Scaffolder died nine months after building site fall, inquest told

A four-day inquest has opened into the death of a scaffolder who died nine months after falling more than three metres while working on...

Scaffolding industry backs all-apprentice team for ScaffChamp 2026

A team of seven apprentices from Scotland and Northern Ireland will compete at ScaffChamp 2026 in Vilnius this summer, after securing full backing from...

NASC chief to take on charity ride in tribute to former president

Clive Dickin, Group CEO of NASC and CISRS, is set to take part in the British Heart Foundation London to Brighton Bike Ride on...

Australian scaffolding group enters administration with over 650 jobs at risk

A group of companies linked to one of Australia’s largest scaffolding and formwork providers has entered voluntary administration, placing more than 650 jobs at...

Brogan Group expands scaffolding operations across Midlands and North

Brogan Group has expanded its scaffolding operations across the Midlands and North of England, extending its regional coverage to support projects in cities including...

Layher UK draws strong turnout at latest ‘Sizzle & Learn’ event

Layher UK has reported a strong turnout at its latest ‘Sizzle & Learn’ open morning, with attendees engaging closely with both product demonstrations and...

Fraud gang jailed for helping candidates cheat CITB safety tests

Three men have been sentenced for their role in a construction test fraud scheme that allowed more than 70 candidates to cheat health and...

Scaffolding sector joins April Fools’ Day with wave of industry jokes

Scaffolding companies and industry figures have taken to social media to mark April Fools’ Day, with a wide range of posts blending humour with...

Latest news

Magazine

Spring Issue #29 | Past issues >>

Trending now ⚡︎

Brogan Group expands scaffolding operations across Midlands and North

Brogan Group has expanded its scaffolding operations across the...

Fraud gang jailed for helping candidates cheat CITB safety tests

Three men have been sentenced for their role in...

Australian scaffolding group enters administration with over 650 jobs at risk

A group of companies linked to one of Australia’s...

Scaffolder died nine months after building site fall, inquest told

A four-day inquest has opened into the death of...

Layher UK draws strong turnout at latest ‘Sizzle & Learn’ event

Layher UK has reported a strong turnout at its...

Related articles

Latest topics

Women completing construction apprenticeships triple since 2018, says CITB

The number of women completing construction apprenticeships has more...

CISRS proposes single global scaffolding training standard by 2028

CISRS has set out plans to reform its Overseas...

Scaffolder died nine months after building site fall, inquest told

A four-day inquest has opened into the death of...
ADVERTISEMENTS