Costs climb again on Manchester Town Hall project as delays worsen

ADVERTISEMENT

The cost of restoring Manchester Town Hall has risen by a further £95m, with completion now pushed back to spring 2027. The Grade I-listed project was originally due to finish in summer 2024.

Manchester City Council confirmed that the overall budget has increased to £524.8m. This is 59 per cent higher than the initial £330m allocation set when work began.

The council said the scheme had been affected by a “unique combination” of pressures. These include a shortage of specialist heritage labour, continued materials and labour cost inflation, and a series of subcontractor collapses.

Three unnamed subcontractors working on key packages have entered administration in the past six months. The council said the complexity of the 148-year-old building meant delays to one element of work often caused wider disruption across the programme.

Lendlease was appointed as main contractor in 2019. The job is now being delivered under the revived Bovis name after Lendlease’s UK construction arm was sold to Atlas Holdings.

Deputy council leader Garry Bridges said the project had “navigated a stream of challenges”. He acknowledged frustration over rising costs but argued that failing to intervene would have risked the building becoming “unusable and obsolete”.

The council reported last year that costs had already grown by nearly £100m due to hyperinflation, subcontractor claims and unexpected conservation work, including the presence of nesting falcons.

The latest funding increase will need approval from the council’s executive committee on 10 December. The additional money will be met through borrowing.

Bridges said the project was now on a “confident path” to completion in 2027 and would be ready for the 150th anniversary of the town hall’s original opening. He added that the restored building would serve the city “for the next 100 years”.

ADVERTISEMENT

Popular Categories

Latest news

David Brown returns as President and Chair of NASC and CISRS

Redaction notice An earlier version of this article referred to “interim” leadership arrangements at NASC and CISRS. This was incorrect. David Brown has formally resumed the...

The story behind Scaffolder’s Day, and how it became an industry fixture

Each year on 14 January, the scaffolding industry marks Scaffolder’s Day. There is no formal programme, no governing body and no official endorsement. Yet...

Safety & Access adds CITB Site Safety Plus courses

Safety & Access has added CITB Site Safety Plus (SSP) courses to its training portfolio, extending its offer to include site safety and management...

Embrace Building Wraps marks climate milestone with 20,500 trees planted

Embrace Building Wraps has begun 2026 by confirming that it has helped plant more than 20,500 trees as part of a long-running climate commitment...

Scaffolding project manager convicted after temporary bridge collapse

A Finnish court has handed a suspended prison sentence to a scaffolding firm project manager over the collapse of a temporary pedestrian bridge in...

Funeral details confirmed as NASC publishes tribute to Wayne Connolly

The National Access & Scaffolding Confederation has published a detailed obituary for its President and Chair, Wayne Connolly, alongside confirmation of funeral arrangements following...

The real value of competition in scaffolding

Anyone who’s ever worked in a management or sales position in scaffolding will tell you that competitors are always on your mind. Perhaps you...

Engineering excellence in the Alps: Pilosio’s Olympic challenge

When the iconic Zuel ski jump in Cortina d'Ampezzo needed renovation ahead of the 2026 Winter Olympics, the project demanded more than standard scaffolding...

Layher Allround supports complex heritage restoration at Royal Victoria Country Park

Layher UK has worked in close partnership with Skill Scaffolding on a demanding heritage restoration project at the Abbey in Royal Victoria Country Park,...

GEDA transport system supports renovation of Augsburg landmark

Renovation work is continuing at the Perlachturm in Augsburg, a historic city in the German state of Bavaria, close to the Austrian border. The tower,...

Latest news

ADVERTISEMENT

Magazine

Winter Issue #28 | Past issues >>

Popular

Scaffolding project manager convicted after temporary bridge collapse

A Finnish court has handed a suspended prison sentence...

Funeral details confirmed as NASC publishes tribute to Wayne Connolly

The National Access & Scaffolding Confederation has published a...

The story behind Scaffolder’s Day, and how it became an industry fixture

Each year on 14 January, the scaffolding industry marks...

The real value of competition in scaffolding

Anyone who’s ever worked in a management or sales...

Embrace Building Wraps marks climate milestone with 20,500 trees planted

Embrace Building Wraps has begun 2026 by confirming that...

Related articles

ADVERTISEMENTS

Latest topics

POP UP Products marks 20 years in business

Access equipment manufacturer POP UP Products is marking its...

David Brown returns as President and Chair of NASC and CISRS

Redaction notice An earlier version of this article referred to...

The story behind Scaffolder’s Day, and how it became an industry fixture

Each year on 14 January, the scaffolding industry marks...

Safety & Access adds CITB Site Safety Plus courses

Safety & Access has added CITB Site Safety Plus...
ADVERTISEMENTS