Costs climb again on Manchester Town Hall project as delays worsen

ADVERTISEMENT

The cost of restoring Manchester Town Hall has risen by a further £95m, with completion now pushed back to spring 2027. The Grade I-listed project was originally due to finish in summer 2024.

Manchester City Council confirmed that the overall budget has increased to £524.8m. This is 59 per cent higher than the initial £330m allocation set when work began.

The council said the scheme had been affected by a “unique combination” of pressures. These include a shortage of specialist heritage labour, continued materials and labour cost inflation, and a series of subcontractor collapses.

Three unnamed subcontractors working on key packages have entered administration in the past six months. The council said the complexity of the 148-year-old building meant delays to one element of work often caused wider disruption across the programme.

Lendlease was appointed as main contractor in 2019. The job is now being delivered under the revived Bovis name after Lendlease’s UK construction arm was sold to Atlas Holdings.

Deputy council leader Garry Bridges said the project had “navigated a stream of challenges”. He acknowledged frustration over rising costs but argued that failing to intervene would have risked the building becoming “unusable and obsolete”.

The council reported last year that costs had already grown by nearly £100m due to hyperinflation, subcontractor claims and unexpected conservation work, including the presence of nesting falcons.

The latest funding increase will need approval from the council’s executive committee on 10 December. The additional money will be met through borrowing.

Bridges said the project was now on a “confident path” to completion in 2027 and would be ready for the 150th anniversary of the town hall’s original opening. He added that the restored building would serve the city “for the next 100 years”.

ADVERTISEMENT

Popular Categories

Latest posts

Baton opens early adopter programme for scaffolding contractors

Baton has opened applications for its Early Adopter Programme, giving scaffolding contractors early access to a software platform designed specifically for construction subcontractors. The company...

SCA joins Coriant in move to widen access and industrial services capability

Coriant has announced the acquisition of specialist contractor SCA, in a move that further expands the group’s capabilities in access, temporary containment and industrial...

Robot named Douglas begins work on Tilbury Douglas site

Tilbury Douglas has begun using a humanoid robot to carry out administrative and data-collection tasks on a live construction site. The contractor says the...

HAKI reports sharp UK sales drop as construction starts stall

The Swedish-listed scaffolding and access safety group said UK revenues fell to SEK 52 million (£4.2 million) in the three months to 31 March,...

CISRS appoints Kathryn Bowe after delay to quality committee reforms

CISRS has appointed Kathryn Bowe as full-time Chair of its Quality Assurance Committee, months after the organisation was forced to restart recruitment for the...

NASC throws support behind first International Scaffolding and Access Day

NASC has thrown its support behind the first International Scaffolding and Access Day, as the UK industry prepares to join a new annual campaign...

Women completing construction apprenticeships triple since 2018, says CITB

The number of women completing construction apprenticeships has more than tripled since 2018, according to new figures from the Construction Industry Training Board (CITB). CITB...

Pilosio brings UK scaffolding safety model into Italian conference spotlight

Pilosio is set to use its presence at GIC Piacenza, a major construction trade event in northern Italy, this week to push a broader...

CISRS proposes single global scaffolding training standard by 2028

CISRS has set out plans to reform its Overseas Scaffolder Training Scheme, with proposals that would lead to a single global baseline training standard...

Scaffolder died nine months after building site fall, inquest told

A four-day inquest has opened into the death of a scaffolder who died nine months after falling more than three metres while working on...

Latest news

Spring Issue #29 | Past issues >>

Latest topics

Most popular ⚡︎

Robot named Douglas begins work on Tilbury Douglas site

Tilbury Douglas has begun using a humanoid robot to...

Scaffolder died nine months after building site fall, inquest told

A four-day inquest has opened into the death of...

SCA joins Coriant in move to widen access and industrial services capability

Coriant has announced the acquisition of specialist contractor SCA,...

CISRS proposes single global scaffolding training standard by 2028

CISRS has set out plans to reform its Overseas...

Pilosio brings UK scaffolding safety model into Italian conference spotlight

Pilosio is set to use its presence at GIC...

Related articles

ADVERTISEMENTS