Ad
Friday, November 7, 2025

The Importance of Installing and Checking Scaffold Ties

ADVERTISEMENT

The recent high winds from storm Ciara and Dennis have highlighted the potential damage and destruction that can be caused by improper scaffold installation. Jonathan Craig from Hydrajaws guides us on the importance of installing and checking scaffold ties.

Scaffold Ties

A scaffold tie is an important connection that fastens the scaffolding to a solid building or body to prevent it from collapse. When installed properly in a system they enable a resistance to forces trying to pull the scaffold away from the structure, such as high winds. From the initial design of the scaffold structure, the predictable loads of the scaffold on the main structure will be identified. 

Why Test Anchor Ties?

There are a variety of anchor ties that a scaffold designer can specify. Each have their strengths and weaknesses, either in terms of achievable loads or suitability in base materials. The designer of the scaffold may initially specify the required anchor ties to be used to ensure that the scaffolding does not collapse away from the main structure. However, if the anchor ties are installed incorrectly, or even installed correctly into a weak material they will be compromised and potentially fail. That is why testing on-site in the actual working conditions is so important. 

BS 8539:2012, Code of Practice

In BS 8539:2012, Code of Practice for the selection and installation of post-installed anchors in concrete and masonry, there are two types of site testing to be considered with scaffolding, Preliminary Test and Proof Tests:

Preliminary Tests

As the names would suggest, preliminary tests are performed on anchors before the scaffold is erected at a site. This is normally required when tying into masonry or other base materials where the anchor manufacturer cannot provide characteristic load data. This generally involves installing anchors into the masonry and pull testing the anchors to a required load. A minimum of 5 tests per base material is required.

It is strongly suggested to avoid pull testing these anchors to failure, as this is likely to cause unwanted damage to the building. When preliminary tests are carried out at site, it is important that the results of these tests are communicated effectively to the scaffolding designer. 

At this point, the scaffolding designer may wish to increase the number of anchor ties, or use a different anchor tie. It is important to note that should a different anchor tie be used, that preliminary testing of the new tie is performed.

Proof Tests 

On all jobs, proof tests of scaffold ties are required. These proof tests are not designed to be a check on the manufacturer’s load test data, but a check that the anchors have been installed correctly (to the manufacturer’s recommendations) and that the substrate is capable of taking 1.25 times the working load of each anchor. Proof testing to 1.25 times the working load rather than just the working load gives a ‘safety factor’ to the installation of the anchor tie in the substrate.

A minimum of three anchors or 5% of the anchors installed (whichever is the greater number) are to be tested per scaffold. It is best practice to spread these tests around the scaffold, in particular if different anchors have been used in different sections or if these anchors have been installed by different teams. Should a scaffold tie fail a pull test, then the frequency of anchor testing doubles.

The frequency doubles again should a second anchor fails. Should more than two anchors fail, then 100% of the anchors require proof testing. It is advisable that the anchor used and the installation method are re-visited. Should this be required, then it is important to use a reputable anchor company with a strong technical department.

 The Importance of Recording the Test Data

In line with BS 8539, the results of the pull tests need to be formally recorded and retained with the site documentation relating to the scaffold structure. Traditionally, these results were recorded manually, noting down the load achieved. As with many aspects of inspections and testing, a recent development is a digital way to record the results of these tests.

This digital method enables whoever performed the pull tests to show that they have complied with the testing element of BS 8539, not only in the load applied, but that the load was held for the specified length of time and collates the data into a site test report. These records are to be retained for the lifetime of the scaffold, not just the erection phase.

Keeping full records for on-site tie testing the lifetime of the scaffold as part of a Technical File on-site is not only good practice, but demonstrates that you as a scaffold company are professional, methodical and takes safety very seriously.

This article was first published in the ScaffMag Magazine Issue 9

ADVERTISEMENT

Popular Categories

Latest news

ULMA Construction eyes UK expansion with Des Moore leading setup

European scaffolding and formwork giant ULMA Construction is preparing to enter the UK market, with industry leader Des Moore steering the launch phase. The Spanish-based...

PERI UK’s Terry Hall recognised as ‘Unsung Hero’ for driving formwork safety reform

Terry Hall, Field Services Manager at PERI UK, has been honoured with the ‘Unsung Hero’ award at this year’s CONSTRUCT Day for his work...

Scaffolders urged to tighten safety as climate change brings fiercer storms

Extreme weather is exposing poor practices across the scaffolding industry, as insurance specialists urge contractors to tighten safety procedures in response to increasingly severe...

Connolly Scaffolding unveils major new Salford base as part of multi-million-pound expansion

Connolly Scaffolding has completed a major expansion with the opening of a new 26,000 sq ft warehouse and yard in Salford – a move...

Surge in construction apprenticeships as CITB support drives 61% rise

The Construction Industry Training Board (CITB) has reported a sharp rise in apprenticeship starts, with more than 1,500 new apprentices supported by its New...

URTIM powers Turkey’s first floating gas platform

Turkey has taken a major step towards energy independence with the completion of its first floating natural gas production platform, the Osman Gazi. At the...

CISRS announces suite of new safety and inspection courses

The Construction Industry Scaffolders Record Scheme (CISRS) has announced a series of new and updated training courses aimed at improving safety, technical standards, and...

House-building recovery delayed until 2029, industry warns

The Construction Products Association warns UK house-building will not recover to pre-pandemic levels until 2029 or 2030, urging government support for first-time buyers to prevent further insolvencies and job losses.

Staht secures largest ever distribution deal with Leach’s

One of the UK’s leading testing technology firms, Staht, has announced its largest ever distribution agreement after joining forces with Leach’s. The partnership will expand...

Avontus to host free webinars on digital scaffold management this November

Avontus Software has announced a series of free, live webinars in November designed to help contractors overcome the everyday challenges of tracking and managing...

Latest news

ADVERTISEMENT

The magazine

Issue 27 | Past issues >>

Popular

CISRS announces suite of new safety and inspection courses

The Construction Industry Scaffolders Record Scheme (CISRS) has announced...

URTIM powers Turkey’s first floating gas platform

Turkey has taken a major step towards energy independence...

Connolly Scaffolding unveils major new Salford base as part of multi-million-pound expansion

Connolly Scaffolding has completed a major expansion with the...

House-building recovery delayed until 2029, industry warns

The Construction Products Association warns UK house-building will not recover to pre-pandemic levels until 2029 or 2030, urging government support for first-time buyers to prevent further insolvencies and job losses.

Staht secures largest ever distribution deal with Leach’s

One of the UK’s leading testing technology firms, Staht,...

Related articles

ADVERTISEMENTS

Latest topics

Kirtanlal and Al Masaood partnership set to reshape the Middle East scaffolding sector

Kirtanlal Scaffolding & Formwork has announced a new strategic...

ULMA Construction eyes UK expansion with Des Moore leading setup

European scaffolding and formwork giant ULMA Construction is preparing...

Scaffolders urged to tighten safety as climate change brings fiercer storms

Extreme weather is exposing poor practices across the scaffolding...
ADVERTISEMENTS