The Queen’s Tower: A Majestic Restoration

ADVERTISEMENT

JDC Scaffolding Ltd, RDG Engineering and Russell Cawberry Ltd. have come together to create an engineering masterpiece to restore the iconic landmark that is The Queen’s Tower, Daniel Norton reports.

The Queen’s Tower, the last remaining structure of the Imperial Institute, stands as a testament to history in the heart of Imperial College, South Kensington, London. As the 287-foot iconic tower undergoes extensive restoration, Hertfordshire-based JDC Scaffolding Ltd has been entrusted with providing complex, safe and efficient scaffolding solutions for the project in collaboration with Russell Cawberry Ltd, the main contractor.

“The tower represents a significant part of Imperial College’s history, and we are honoured to be a part of this prestigious project,” said Phil Welham, Business Development Director at JDC Scaffolding. “Our design process began in late 2020, with ongoing collaboration with Imperial College and RDG Engineering to provide a safe and innovative scaffolding system for the restoration works.”

The initial design included a 2-tonne Passenger/Goods Hoist, a full-height Haki Staircase, and a suspended access scaffold that followed the profile of the copper dome that tops the tower. However, due to concerns about the tower’s fragility, RDG Engineering was tasked with creating a freestanding structure, an external “Exoskeleton” scaffold, to surround the tower.

“Developing the exoskeleton was a unique challenge,” explained Welham. “It needed to be designed to minimise the impact on the tower itself and provide the necessary support for the independent scaffold, hoist, and staircase.”

The exoskeleton includes triple standards to the 30.00m level, double standards to the 50.00m level and single standards to the 87.00m level. Every pair of standards is ledger braced, each horizontal bay plan braced, and every vertical bay sway braced to both the internal and external faces.

Credit: Gary Britton Photography Ltd

The design and planning process included a series of collaborative Teams meetings with Imperial College’s independent consulting engineer, RDG Engineering, and JDC Scaffolding to ensure all stakeholders were aligned in their understanding of the project’s complexities and requirements.

After several iterations, the final design incorporated a temporary circular roof, back propping in the vaults, and a full-height hoist run-off with staggered exits. The scaffold’s required equipment amounted to an incredible 300,000 feet of tube and around 92,000 fittings.

Russell Cawberry Ltd, who have worked with the Imperial College across all their campus and sites for over twenty years, were awarded the Queen’s Tower contract in August 2022. Having never worked with JDC Scaffolding Ltd before, Russell Cawberry Ltd were convinced of JDC’s expertise and experience after a series of negotiations, due diligence, and their long-standing knowledge of the project.

The project has had its fair share of challenges, including protecting the York Stone steps surrounding the tower and navigating the complexities of working on a live college campus. “Our priority is to maintain the highest standards of safety and minimise disruption to the college community,” said Welham. “Prior to commencement, there were discussions about basing the scaffold on the existing York Stone steps. One option was to take up the paving, this option was dismissed, and we were asked to cover the steps completely with a protection system made up of Dow Floormate 700 sandwiched between two layers of ply.”

Credit: Gary Britton Photography Ltd

As the scaffold erection progresses, JDC Scaffolding have been working closely with Russell Cawberry Ltd and Imperial College to address any unforeseen challenges and to ensure smooth communication between all parties involved. This collaborative approach has proven to be a key factor in the project’s success thus far.

The team at JDC Scaffolding are now looking forward to tackling the challenges associated with restoring the copper dome that tops the tower and providing temporary roof protection. The back propping works in the basement, which were carried out under confined space restrictions, have been successfully completed, paving the way for the scaffold’s continued erection.

Upon completion, the revitalised Queen’s Tower will stand as a beacon of Imperial College’s illustrious history, exemplifying progress, innovation, and the unyielding pursuit of knowledge. With the combined expertise of JDC Scaffolding, RDG Engineering and Russell Cawberry Ltd, this ambitious project promises to breathe new life into a cherished landmark, ensuring that it continues to inspire future generations of scholars and visitors alike.

And as the restoration journey unfolds, the collaborative efforts of all parties involved will stand as a testament to the power of teamwork, engineering prowess, and a shared commitment to preserving our rich cultural heritage.

This article was originally published in Issue 19 of the ScaffMag magazine.

ADVERTISEMENT

Popular Categories

Latest news

Sheffield scaffolder to walk 1,200 miles for suicide prevention charity

A scaffolder from Sheffield is set to walk 1,200 miles from Land’s End to John o’ Groats in support of suicide prevention charity Andy’s...

CITB reshapes training funding with new large employer fund

The Construction Industry Training Board (CITB) has announced changes to how training funding will be distributed to employers from 1 April 2026. The update introduces...

Scaffmag Issue 29 released with focus on technology, skills and industry change

Scaffmag has released Issue 29, bringing together interviews, analysis and project stories from across the scaffolding and access industry. The new edition for Spring 2026...

Young workers least likely to discuss mental health, research shows

More than one in three UK tradespeople say their job is harming their mental health, with young workers among the least likely to seek...

NASC warns scaffolding skills gap could leave 40,000 roles to fill

NASC has warned the UK scaffolding and access sector could need around 40,000 roles filled, as it published its Skills Gap Report 2026 based...

Construction industry says Spring Statement lacked measures to boost building

Construction leaders have offered a mixed response to Chancellor Rachel Reeves’ Spring Statement, with industry bodies warning that the government missed an opportunity to...

ScaffPlan partners with Leach’s to expand access to scaffold design software

ScaffPlan has formed a strategic partnership with Leach’s, the UK’s largest supplier of scaffolding consumables and equipment, in a move designed to widen access...

Training provider reports disruption as Gulf tensions escalate

The escalating conflict in the Middle East is beginning to affect construction and safety training activity, with early disruption reported to training schedules in...

Subcontractors stay upbeat despite seven-year low in project volumes

Subcontractors across the UK and Ireland remain optimistic about the year ahead despite a tightening construction pipeline, according to a new annual report from...

Doka supports Denmark’s Storstrøm Bridge as 3.8km crossing nears completion

Denmark’s new Storstrøm Bridge is entering its final construction phase, with the 3.8km crossing set to become the country’s third-longest bridge when it opens...

Latest news

Magazine

Spring Issue #29 | Past issues >>

Popular

NASC warns scaffolding skills gap could leave 40,000 roles to fill

NASC has warned the UK scaffolding and access sector...

ScaffPlan partners with Leach’s to expand access to scaffold design software

ScaffPlan has formed a strategic partnership with Leach’s, the...

Young workers least likely to discuss mental health, research shows

More than one in three UK tradespeople say their...

Construction industry says Spring Statement lacked measures to boost building

Construction leaders have offered a mixed response to Chancellor...

CITB reshapes training funding with new large employer fund

The Construction Industry Training Board (CITB) has announced changes...

Related articles

Latest topics

Layher system scaffold supports Prestwich Travel Hub regeneration project

Rose System Scaffolding has completed the scaffolding package for...

Sheffield scaffolder to walk 1,200 miles for suicide prevention charity

A scaffolder from Sheffield is set to walk 1,200...

CITB reshapes training funding with new large employer fund

The Construction Industry Training Board (CITB) has announced changes...

Scaffmag Issue 29 released with focus on technology, skills and industry change

Scaffmag has released Issue 29, bringing together interviews, analysis...
ADVERTISEMENTS