Ad
Thursday, October 30, 2025

Companies Fined after Scaffolder Crushed by Two-Tonne Weight

ADVERTISEMENT

EDF and Trillium Flow Services Ltd have been handed fines totalling £633,333 after a scaffolder was seriously injured by a falling two-tonne counterweight at the Dungeness B power station in Kent.

The incident, which occurred on June 13, 2022, left 62-year-old scaffolder Colin Dell with severe injuries, including broken and amputated toes, and has since rendered him unable to return to work. Dell has also been diagnosed with post-traumatic stress disorder following the life-changing accident.

A Preventable Tragedy

Dell was working near the main cooling water discharge valves when a heavy counterweight, unsupported due to a missing hydraulic actuator (or “ram”), suddenly fell. The counterweight struck Dell’s hand and foot, leaving him trapped. Emergency services transported him to the hospital, where he spent four days undergoing treatment for his injuries.

The Office for Nuclear Regulation (ONR) investigation revealed that the accident was “wholly avoidable,” citing failures in the sequence for re-fitting a critical valve. Both EDF, the plant’s operator, and Trillium Flow Services Ltd, responsible for maintenance at the site, were found guilty of safety breaches at Folkestone Magistrates’ Court.

District Judge Stephen Leake fined EDF £533,333 and Trillium Flow Services Ltd £100,000. Both companies were also ordered to pay prosecution costs of £15,034 each.

Missed Opportunities

Dan Hasted, Director of Regulation for ONR’s Operating Facilities Directorate, said: “We welcome the outcome which recognises that EDF and Trillium Flow Services Ltd failed in their duty to protect a worker from a known risk.

This accident was wholly avoidable. Nobody should go to work and not come home in a fit and healthy state.”

Hasted emphasised that the investigation uncovered “several missed opportunities” to prevent the incident, including failing to follow established safety procedures.

Dungeness B, which ceased power generation in June 2021 and is currently undergoing defueling, relies on four main cooling water pumps to provide seawater to its condensers. Each pump is equipped with a discharge valve, one of which was involved in the incident.

The malfunctioning valve and the subsequent omission of a hydraulic actuator allowed the counterweight to fall, leading to the tragic injuries sustained by Dell.

ADVERTISEMENT

Popular Categories

Latest news

Staht secures largest ever distribution deal with Leach’s

One of the UK’s leading testing technology firms, Staht, has announced its largest ever distribution agreement after joining forces with Leach’s. The partnership will expand...

Avontus to host free webinars on digital scaffold management this November

Avontus Software has announced a series of free, live webinars in November designed to help contractors overcome the everyday challenges of tracking and managing...

Scaff25 announces global line-up of industry leaders for Sydney conference

The Scaffolding Association Australia (SAA) has revealed an impressive line-up of international speakers for its upcoming Scaff25 Annual Conference & Awards Night, set to...

Demolition firm issues statement following Manchester building and scaffolding collapse

Manchester-based demolition contractor P.P. O’Connor has released an official statement following Friday’s partial collapse of a building surrounded by scaffolding in the city centre. The...

Building and scaffolding partially collapses in Manchester city centre

A building in Manchester city centre has partially collapsed during demolition work, with scaffolding and debris seen falling into the nearby River Irwell. Emergency services...

Benchmark Scaffolding wins Silver at national awards

Benchmark Scaffolding has been recognised with the Silver Award in the Specialist Contractor of the Year category at the 2025 National Building and Construction...

Construction leaders unite against government plan to shorten apprenticeships

More than 20 construction organisations, including the NASC, have signed an open letter to Prime Minister Keir Starmer warning that plans to cut apprenticeships to eight months risk undermining skills, safety, and confidence in training.

HSE launches major construction site safety inspections in Manchester

The Health and Safety Executive (HSE) is carrying out a series of unannounced inspections at construction sites across Manchester city centre this week. Twelve inspectors...

JR Scaffold honoured with Ministry of Defence Silver Award

Paisley-based JR Scaffold has been recognised among a select group of leading Scottish businesses to receive the prestigious Silver Award from the Ministry of...

Brogan Group acquires Sunbelt Rentals UK hoist division

Brogan Group has announced the acquisition of Sunbelt Rentals UK’s hoist division in a deal that significantly expands its operations and fleet across the...

Latest news

ADVERTISEMENT

The magazine

Issue 27 | Past issues >>

Popular

Building and scaffolding partially collapses in Manchester city centre

A building in Manchester city centre has partially collapsed...

Demolition firm issues statement following Manchester building and scaffolding collapse

Manchester-based demolition contractor P.P. O’Connor has released an official...

ScaffChamp 2025: Teams Gather in Vilnius for Opening Day

The international scaffolding competition ScaffChamp 2025 has officially begun,...

Scaff25 announces global line-up of industry leaders for Sydney conference

The Scaffolding Association Australia (SAA) has revealed an impressive...

Benchmark Scaffolding wins Silver at national awards

Benchmark Scaffolding has been recognised with the Silver Award...

Related articles

Scaffolder’s Epic Munro Challenge Captured in BBC Documentary

Scotland — A Scottish scaffolder has captured national attention after the BBC aired a documentary following his extraordinary eight-year mission to descend all 282 of Scotland’s Munros — with his mountain bike. Sean Green,...
ADVERTISEMENTS

Latest topics

House-building recovery delayed until 2029, industry warns

The Construction Products Association warns UK house-building will not recover to pre-pandemic levels until 2029 or 2030, urging government support for first-time buyers to prevent further insolvencies and job losses.

Staht secures largest ever distribution deal with Leach’s

One of the UK’s leading testing technology firms, Staht,...

Avontus to host free webinars on digital scaffold management this November

Avontus Software has announced a series of free, live...

Scaff25 announces global line-up of industry leaders for Sydney conference

The Scaffolding Association Australia (SAA) has revealed an impressive...
ADVERTISEMENTS