Ad
Thursday, December 11, 2025

Demanding Project Highlights Harsco’s Customer Service Abilities

ADVERTISEMENT

H145 Uppingham College

A college refurbishment project in Rutland has thrown the spotlight onto the outstanding levels of customer service for which Harsco Infrastructure is widely recognised, and earned the company high praise from its client.

Despite the presence of asbestos and the need for frequent changes during the life of the project, Harsco was able to provide a CUPLOK® scaffolding system which allowed the windows at Uppingham Community College to be replaced in-line with an extremely demanding schedule.

“This was certainly a project which provided its fair share of difficulties, but the Erection and Dismantle team at our Birmingham branch in Tamworth was more than equal to the challenge“ explains Harsco’s Branch Manager Steve Bollans. “The scaffolding system itself was straightforward enough, but there were many other factors which made the job difficult.”

These included the fact that the school was live during the project, which required Harsco to schedule all deliveries to site outside of school hours. Limited road access also meant that delivery vehicles were halted some 70 yards away from the school. The Harsco equipment was then unloaded and transferred to site, past an adjacent nursery school, using lorry-mounted forklift trucks.

“We could only do this when there were no children in the nursery,” adds Steve. “Similarly, when we were installing the scaffolding we had to stop work every time pupils from the main school came outside at break times”  Despite this, and the fact that the decision was taken part way through to extend the project to cover the school’s second storey windows, Harsco was able to help the project meet its very demanding 10-week schedule.

“From the outset the Harsco team were extremely professional, pro-active and advisory, managing an extremely short mobilisation period with ease,” says Chris Cuthbert, Project Manager for the main contractor, Kier. “We had regular site meetings to make sure any design changes were dealt with in a timely fashion. Unfortunately one of the three main sub-contractors under-performed drastically which put a lot of pressure on the Harsco team due to late changes. With this in mind, and with the Harsco people being so pro-active and reactive, the project finished on time. Without this support I’m sure the project would have overrun.”

The fact that asbestos was being removed from the building as the windows were replaced meant that Harsco’s scaffolding design had to allow the proper protective sheeting to be installed all round the areas which were being worked on. This also involved Harsco being asked to make frequent changes to the scaffolding as the project progressed, and often at a moment’s notice.

CUPLOK®

cuplok

Harsco’s CUPLOK® is a multi-purpose steel scaffold system which is ideal for general access, shoring and vertical load support duties. A unique node point design allows up to four components to be connected in one fastening action, making CUPLOK® quick and simple to erect and strike. The fully galvanised, high grade tube is 20% lighter than conventional alternatives, has high resistance to damage and is compatible with up to 3 kN/m² platform loadings, making it strong enough for use in the most demanding applications.

 

ADVERTISEMENT

Popular Categories

Latest news

Brogan Group and Alimak strike global partnership

Brogan Group has formed a new strategic alliance with Alimak Group’s Construction Division, bringing its CAS Common Tower and Atlas gantry systems to a...

CITB announces major funding cuts despite £79m reserves

The Construction Industry Training Board has slashed grants and capped funding from January, citing rising demand but drawing criticism over timing and available reserves. The...

Trapped load drags labourer from scaffold as firms fined £800k

A labourer suffered life-changing injuries after being pulled from scaffolding during an unplanned lifting operation on a London refurbishment project. Two companies have been...

ITP opens new Product Development and Testing Facility at Yorkshire HQ

Yorkshire-based manufacturer ITP Ltd has opened a new Product Development and Testing Facility at its Easingwold headquarters following a major strategic investment. Clive Dickin, Chief...

CISRS reforms face delay as new QAC Chair withdraws

CISRS has reopened its search for a new Chair of the Quality Assurance Committee (QAC) after the organisation confirmed that Professor David Wooff, appointed...

Connolly Scaffolding strengthens partnership with TRAD UK in £3.5m investment

Connolly Scaffolding Ltd has agreed a further £3.5 million investment in TRAD UK’s Plettac Metrix system, reinforcing a partnership that has shaped both businesses...

Benetics introduces AI voice tool to cut site paperwork

A German construction technology firm has launched an AI-powered voice assistant designed to help site teams cut paperwork and speed up reporting. Benetics, based in...

Scaffolders at Sullom Voe Terminal walk out over pay dispute

Around 60 scaffolders, painters, insulators, and supervisors at the Sullom Voe Terminal in the Shetland Islands have staged a 24-hour walkout in an escalating...

Hong Kong contractors ‘hid unsafe scaffolding netting’ as tower fire toll rises to 151

Investigators in Hong Kong say contractors used unsafe scaffolding netting at the housing estate destroyed by last week’s deadly fire, and then tried to...

Costs climb again on Manchester Town Hall project as delays worsen

The cost of restoring Manchester Town Hall has risen by a further £95m, with completion now pushed back to spring 2027. The Grade I-listed...

Latest news

ADVERTISEMENT

The magazine

Issue 27 | Past issues >>

Popular

Trapped load drags labourer from scaffold as firms fined £800k

A labourer suffered life-changing injuries after being pulled from...

Brogan Group and Alimak strike global partnership

Brogan Group has formed a new strategic alliance with...

ITP opens new Product Development and Testing Facility at Yorkshire HQ

Yorkshire-based manufacturer ITP Ltd has opened a new Product...

CISRS reforms face delay as new QAC Chair withdraws

CISRS has reopened its search for a new Chair...

CITB announces major funding cuts despite £79m reserves

The Construction Industry Training Board has slashed grants and...

Related articles

ADVERTISEMENTS

Latest topics

New Construction and Scaffolding Academy launched to tackle skills shortages in Northern Ireland

A new Construction and Scaffolding Academy has been launched...

Brogan Group and Alimak strike global partnership

Brogan Group has formed a new strategic alliance with...

CITB announces major funding cuts despite £79m reserves

The Construction Industry Training Board has slashed grants and...

Trapped load drags labourer from scaffold as firms fined £800k

A labourer suffered life-changing injuries after being pulled from...
ADVERTISEMENTS