HARSCO is on display at new Bordeaux theatre

ADVERTISEMENT

A project to create a new, 1,500-seat theatre building on a site with a restricted footprint and limited access has highlighted the industry knowledge, expertise and value which Harsco Infrastructure brings to construction projects. Harsco was able to design and construct an innovative, bespoke support girder system which overcame the restrictions of the site and allowed the construction of a number of key structural elements of the new building.

The new theatre in Bordeaux, France, is being built on a site surrounded by existing buildings. Harsco was asked to provide a support system to carry formwork for the construction of a number of 6 ft wide, 7 ft high, 105 ft long in-situ concrete beams. These beams needed to span the stage area and also support a further 5 floors of apartments and office accommodation being built above. The girder systems supplied by Harsco were to vary in length – with the longest being 30.90m – which needed to be lowered, relocated, and in some cases altered in length before work on the next beam could begin.

Working on behalf of Portuguese contractor BUILDIN, Harsco was able to draw on its wealth of technical expertise and devise a bespoke H33 braced truss-girder system which was sufficiently flexible and reliable to satisfy this demand. The Harsco H33 beam system offers a flexible, robust and reliable solution with the high load-bearing capacity needed for this type of project. Its excellent weight-to-capacity ratio made it ideal for the long spans involved, while the easy to assemble nature of the system components ensured rapid construction of the girders required.

This proved to be a faster, more cost-effective and practical solution than other alternatives which might have been used. However a severe lack of working space on the site meant that Harsco also had to adapt the traditional methods used to construct such a system.

“We actually did much of the construction work on the girders about 10km away from the site itself,” explains Harsco’s Ingo Schnelting. “This meant that we could prefabricate the girder sections under more controlled conditions, which made it far easier to ensure that they complied fully with the drawings. That way we were able to avoid any unexpected problems on site and be confident that the girders would fit neatly into place.”

Harsco was then able to partially dismantle the girders for transportation and deliver them to site. This also minimised the disruption to other trades that would have been caused by fabricating the units on the site itself. Lack of on-site storage space meant that Harsco had to adopt a just-in-time schedule for these deliveries and also co-ordinate this with special permission from the city authorities to operate extended length transport vehicles.

“We had to remain flexible in our approach to every aspect of this project,” adds Ingo Schnelting. “The different lengths of concrete beam that the building required meant that we sometimes had to remove the girders from the building and transport them the 10 km back to the construction area. There we were then able to re-configure their length before delivering them back to site and using hydraulic jacks to raise them into place, ready to support the formwork required to make the next beam.

 

“This was an excellent example of Harsco’s ‘Insight onsite’ philosophy in action and illustrates the way we are able to develop bespoke solutions that are tailored to the specific requirements of individual projects,” adds Ingo. “The end result of this approach is that we can deliver the highest standards of reliability, cost-effectiveness and safety and that was certainly the case on this project.”

For more information please call. 01372 381 300 or visit www.harsco-i.co.uk

Via: Harsco Press Release

ADVERTISEMENT

Popular Categories

Latest news

NASC President David Brown takes on IASA Chair role

The International Access and Scaffolding Association (IASA) has announced the appointment of David Brown as its new Chairman. The appointment follows the death of former...

umdasch Industrial Solutions expands global scaffolding footprint with Catari acquisition

umdasch Industrial Solutions (UIS) has acquired Catari in a move that accelerates its ambition to create a leading global scaffolding group. The acquisition, announced today,...

AFIX Group secures German approval and opens new branch near Munich

AFIX Group has taken a significant step in its European growth strategy with the opening of a new German subsidiary and the award of...

Twenty teams confirmed for ScaffChamp 2026 in Vilnius

ScaffChamp powered by Layher has confirmed all 20 teams for its 2026 competition, following nearly five months of registrations and enquiries from around the...

Safety crackdown follows boy’s death caused by unsecured scaffolding

New safety standards covering the transport of scaffolding and other construction materials have been introduced following the death of a schoolboy killed by an...

Scaffolding demand expected to rise as construction returns to growth

UK construction activity is expected to recover in 2026 after a subdued year, with growth forecast to strengthen through to 2027, according to a...

Global demand to push scaffolding market to $16bn by end of decade

The global scaffolding and accessories market is expected to grow to $16.3bn by 2030, adding more than $4bn in value over the next four...

CSCS Smart Check reaches 60 million scans

The CSCS Smart Check platform has recorded its 60 millionth scan, highlighting its growing role in workforce verification and compliance across the construction industry. The...

Viktor Voroncov to leave Layher Baltic after 15 years

Viktor Voroncov is to leave Layher Baltic UAB at the end of January, bringing to a close a 15-year career with the company. In a...

HAKI opens new Swiss subsidiary to support regional growth

The HAKI Group has launched HAKI Safety SA, based in Thônex in the canton of Geneva, marking a further step in its expansion across...

Latest news

Magazine

Winter Issue #28 | Past issues >>

Popular

NASC President David Brown takes on IASA Chair role

The International Access and Scaffolding Association (IASA) has announced...

umdasch Industrial Solutions expands global scaffolding footprint with Catari acquisition

umdasch Industrial Solutions (UIS) has acquired Catari in a...

NASC and CISRS expand globally with Malaysia national deal

The National Access & Scaffolding Confederation and Construction Industry...

AFIX Group secures German approval and opens new branch near Munich

AFIX Group has taken a significant step in its...

Twenty teams confirmed for ScaffChamp 2026 in Vilnius

ScaffChamp powered by Layher has confirmed all 20 teams...

Related articles

Latest topics

NASC and CISRS expand globally with Malaysia national deal

The National Access & Scaffolding Confederation and Construction Industry...

NASC President David Brown takes on IASA Chair role

The International Access and Scaffolding Association (IASA) has announced...

umdasch Industrial Solutions expands global scaffolding footprint with Catari acquisition

umdasch Industrial Solutions (UIS) has acquired Catari in a...

AFIX Group secures German approval and opens new branch near Munich

AFIX Group has taken a significant step in its...
ADVERTISEMENTS