Layher Allround Elevates Science Museum Project

ADVERTISEMENT

In the heart of London, the iconic Science Museum is undergoing a transformative renovation, and it’s not just the exhibits that are evolving. Kent-based Browne’s Scaffolding Ltd has taken centre stage on the project by using the versatile Layher Allround scaffolding system to enhance the accessibility and safety of this prestigious project.

We spoke with Darren Bond, Project Manager at Browne’s Scaffolding, to get an inside look at their ground-breaking approach.

The journey began in October 2022 when HLS McConnell approached Browne’s Scaffolding to tender for the Science Museum project. After winning the contract, the team conducted a comprehensive site visit to assess the unique scaffolding requirements necessary for the stipulated works. During this initial assessment, it became clear that the museum’s limited access and egress presented a significant challenge.

Initially, the project called for installing a free-standing hoist with a scaffold frame support solely to the front of the sunscreen area. However, Browne’s Scaffolding had a vision for a more comprehensive solution.

Darren Bond explained, “Our idea was to incorporate both a stair access scaffold and a hoist tower support into a single scaffold structure. This not only provided a secondary means of escape but also offered an alternative access route to the roof, enhancing safety and efficiency.”

With this innovative approach in mind, the project was entrusted to Browne’s Scaffolding’s appointed scaffold engineer, who meticulously designed and calculated the necessary components. This led to a ground test to ensure the area could support the scaffold’s weight, with a major point of concern being how to tie the scaffold securely.

Kent-based Browne's Scaffolding Ltd has taken centre stage on the project by using the versatile Layher Allround scaffolding system to enhance the accessibility and safety of this prestigious project.

Overcoming Obstacles: Tying the Scaffold

The challenge of tying the scaffold arose due to the considerable distance between the existing gantry walkways, exceeding 8-10 meters. This necessitated calculations to overcome this issue, resulting in the incorporation of 152 x 76 x 19kg structural T steels behind the existing tubular steelwork to ensure the scaffold’s integrity.

Despite some logistical challenges, effective communication within the team helped overcome space and storage issues during the erection sequence. In the upcoming weeks, a cantilevered hanging scaffold will be erected from the 4th to the 3rd floor, further showcasing Browne’s Scaffolding’s expertise with the Layher system.

Layher’s Versatility: The Key to Success

Speaking about their experience with the Layher system, Darren Bond expressed their satisfaction, “As a company, and following feedback from the lads carrying out the works, we are extremely pleased with the practicality of using the Layher system. It has proven to be greatly adaptable and efficient in providing the access required.”

Browne’s Scaffolding has embraced the Layher system not only on this project but also in their European endeavours, where the system is becoming a favoured choice over traditional tube and fitting. With works in Germany and France currently underway, the Layher system is gaining traction among both existing clients and scaffolding professionals on the ground.

Shaping the Future of Access Solutions

The Science Museum project stands as a testament to the innovative solutions Browne’s Scaffolding Ltd brings to the scaffolding industry, with the Layher Allround scaffolding system at the forefront of their success. As they continue to push the boundaries of scaffolding excellence, it’s evident that this dynamic partnership will shape the future of access solutions across various projects.

ADVERTISEMENT

Popular Categories

Latest news

Scaffplan recruits former Footprint MD to lead global sales

Scaffplan has appointed former Footprint WFM Managing Director Ciaran Boyd as its Sales Director, strengthening its leadership team as the company prepares for global...

SIMIAN marks 20-year milestone in construction safety training

Leading construction and scaffolding safety specialist SIMIAN has marked 20 years of trading since its establishment in November 2005. The Warrington-based organisation has grown from...

Budget blowback: will tax hikes deepen construction downturn?

Construction supply chain firms are warning that potential tax increases in next week's Autumn Budget could derail the sector's fragile recovery, with material costs...

Scaffolding Association Australia expands leadership team

The Scaffolding Association Australia has appointed two non-executive board members and expanded the role of an existing director as the organisation strengthens its governance...

North Sea worker dies after incident on Valaris 121 rig

A 32-year-old worker has died following an incident on an offshore drilling rig in the North Sea. Police Scotland and the Health and Safety...

CMA approval clears the way for major HSS ProService and Speedy Hire partnership

A major shift in the UK equipment hire market has moved forward after the Competition and Markets Authority approved a new commercial agreement between...

Australia’s top scaffolding projects recognised at 2025 industry awards

Australia’s top scaffolding projects have been named at this year’s Australia’s Best Scaffolding Projects Awards. The event, held during Scaff25, drew a record thirty...

In Pictures: GKR completes major temporary roof structure at HS2 Euston

GKR Scaffolding has completed a large temporary roof structure at HS2’s Euston site. The installation sits beside the live station and supports enclosed works...

UK Construction output edges up just 0.1% in the third quarter

Construction output in Great Britain rose by only 0.1% in the third quarter of 2025, according to new figures from the Office for National...

Hong Kong launches construction safety drive after serious incidents

Hong Kong has begun a city-wide crackdown on unsafe practices in the construction sector after a series of fatal and serious accidents. The Labour Department...

Latest news

ADVERTISEMENT

The magazine

Issue 27 | Past issues >>

Popular

North Sea worker dies after incident on Valaris 121 rig

A 32-year-old worker has died following an incident on...

Australia’s top scaffolding projects recognised at 2025 industry awards

Australia’s top scaffolding projects have been named at this...

CMA approval clears the way for major HSS ProService and Speedy Hire partnership

A major shift in the UK equipment hire market...

Scaffplan recruits former Footprint MD to lead global sales

Scaffplan has appointed former Footprint WFM Managing Director Ciaran...

Budget blowback: will tax hikes deepen construction downturn?

Construction supply chain firms are warning that potential tax...

Related articles

Middlesbrough scaffolder’s steroid addiction left him fighting for life

A Teesside rope access scaffolder has spoken out about his near-fatal steroid addiction, which cost him more than £35,000 and left him in a medically-induced coma for seven days. Zak Wilkinson, 32, from Middlesbrough,...
ADVERTISEMENTS

Latest topics

Middlesbrough scaffolder’s steroid addiction left him fighting for life

A Teesside rope access scaffolder has spoken out about...

Scaffplan recruits former Footprint MD to lead global sales

Scaffplan has appointed former Footprint WFM Managing Director Ciaran...

SIMIAN marks 20-year milestone in construction safety training

Leading construction and scaffolding safety specialist SIMIAN has marked...

Budget blowback: will tax hikes deepen construction downturn?

Construction supply chain firms are warning that potential tax...
ADVERTISEMENTS