Special Access Solutions at Euston Station

ADVERTISEMENT

Large-scale access solutions are being provided by Palmers Scaffolding for the St James Park London Euston Station HS2 enabling construction works.

Palmers £3M tempory works contract for principal contractor CSJV began in July 2018. A 10,000m² temporary roof has been erected by the firm — supported below by 15 towers and 300m of bespoke Palmers special access spine beam. This was erected to house CSJV’s archaeology programme to carry out a number of operations in a cemetery that is buried underneath St James Park.

Over 30 Palmers Scaffolding operatives are involved in the project that is set to remain erected for approximately 18 months, whilst the archaeology works are carried out.

The firm has said, 90% of the works will be completed from the confines of a safe working platform (fully boarded and hand railed) and then be traversed into position, to avoid the risk of working at height.

“This is a marvellous project in every sense. The design process has taken a long time to perfect, but the solution is proving to be ideal for purpose,” said Palmers Managing Director, Donald Morrison.

Palmers Operations Director for Special Access, Paul Duggan added: “The design has involved months of planning and constructing demonstration rigs for the client at our base in Chester, prior to installation on site. We are all proud of the works. We believe Palmers are unique at producing something with a design this innovative.”

Ian McFarlane, Palmers Director of Business and Project Development concluded: “It is fantastic to be working at Euston station on such large-scale, high-profile construction works, within the rail sector. It is an specialised piece of scaffolding requiring specialist knowledge to erect and manage and Palmers are proud to be providing the modern special access here.”

ADVERTISEMENT

Popular Categories

Latest news

Connolly Scaffolding strengthens partnership with TRAD UK in £3.5m investment

Connolly Scaffolding Ltd has agreed a further £3.5 million investment in TRAD UK’s Plettac Metrix system, reinforcing a partnership that has shaped both businesses...

Benetics introduces AI voice tool to cut site paperwork

A German construction technology firm has launched an AI-powered voice assistant designed to help site teams cut paperwork and speed up reporting. Benetics, based in...

Scaffolders at Sullom Voe Terminal walk out over pay dispute

Around 60 scaffolders, painters, insulators, and supervisors at the Sullom Voe Terminal in the Shetland Islands have staged a 24-hour walkout in an escalating...

Hong Kong contractors ‘hid unsafe scaffolding netting’ as tower fire toll rises to 151

Investigators in Hong Kong say contractors used unsafe scaffolding netting at the housing estate destroyed by last week’s deadly fire, and then tried to...

Costs climb again on Manchester Town Hall project as delays worsen

The cost of restoring Manchester Town Hall has risen by a further £95m, with completion now pushed back to spring 2027. The Grade I-listed...

CSCS Alliance appoints new Chair

The CSCS Alliance has confirmed the appointment of Marion Marsland as its new Chair, marking a significant leadership change for the body representing 37...

ScaffEx26 set for growth as NASC prepares expanded programme

NASC says ScaffEx26 is on track to grow further, with early exhibitor demand already exceeding last year’s levels. The trade body confirmed to Scaffmag that...

New Gale Force Bolt introduced to honour industry figure Alan Gale

Tilbury Scaffolding has introduced a new fixing in honour of Alan Gale, a widely respected figure in the scaffolding supply sector whose career spanned...

Scaffolding under scrutiny after Hong Kong tower blaze kills 128

This article has been updated as authorities confirm a revised death toll and launch a criminal and corruption inquiry. At least 128 people have died,...

Budget 2025: NASC warns of rising costs as new tax increases hit construction firms and housing delivery stalls

The Autumn Budget has drawn strong criticism from scaffolding, construction and housebuilding leaders, who warn that a combination of higher wage costs, frozen tax...

Latest news

ADVERTISEMENT

The magazine

Issue 27 | Past issues >>

Popular

Connolly Scaffolding strengthens partnership with TRAD UK in £3.5m investment

Connolly Scaffolding Ltd has agreed a further £3.5 million...

Scaffolders at Sullom Voe Terminal walk out over pay dispute

Around 60 scaffolders, painters, insulators, and supervisors at the...

Hong Kong contractors ‘hid unsafe scaffolding netting’ as tower fire toll rises to 151

Investigators in Hong Kong say contractors used unsafe scaffolding...

CISRS reforms face delay as new QAC Chair withdraws

CISRS has reopened its search for a new Chair...

ScaffEx26 set for growth as NASC prepares expanded programme

NASC says ScaffEx26 is on track to grow further,...

Related articles

Palmers Scaffolding Hits One Million Hours Without a Lost Time Incident

The milestone has been hailed as a major safety achievement for the UK scaffolding firm. Palmers Scaffolding UK Limited has passed a major health and safety milestone after clocking more than one million man-hours...
ADVERTISEMENTS

Latest topics

CISRS reforms face delay as new QAC Chair withdraws

CISRS has reopened its search for a new Chair...

Connolly Scaffolding strengthens partnership with TRAD UK in £3.5m investment

Connolly Scaffolding Ltd has agreed a further £3.5 million...

Benetics introduces AI voice tool to cut site paperwork

A German construction technology firm has launched an AI-powered...

Scaffolders at Sullom Voe Terminal walk out over pay dispute

Around 60 scaffolders, painters, insulators, and supervisors at the...
ADVERTISEMENTS