PERI UP Crescent-shaped scaffolding

ADVERTISEMENT

In Calgary, Canada, a 236 m high office tower is currently being constructed. “The Bow” is shaped like a crescent whilst the most striking feature of the building is the diagonal arrangement of the steel support structure. A sophisticated PERI UP scaffolding concept provides secure access and spacious working platforms for all subsequent sub-contracting work following the completion of the building’s shell. PERI was awarded the contract to supply work scaffolding and stairs that are temporarily required for all subsequent work on the 59-storey building shell.

For painting, mounting of the fire protection cladding as well as the insulation and installation of the piping system, the sub contractors imposed various requirements concerning working area dimensions and potential loads. Installation of platforms at distances of 2.50 m over the entire height of the building was requested. One of the most important requirements to be fulfilled for all sub-contractors was to ensure that the working platforms were as close as possible to the complex steel structure whose main beams ascended at an angle of 76°. In addition, the front of the building is curved like a crescent.

Together with the Ledcor team, PERI developed a solution based on the PERI UP Rosett Flex scaffolding. In the process, the modular scaffold system has once again proven its high degree of flexibility and has shown itself to be extremely adaptable to suit the curved building layout and special form of the supporting structure – all requirements of both the client and sub-contractors have been fulfilled.

The modular PERI UP Rosett Flex scaffolding has a very wide range of applications. The metric grid dimensions along with the 25 cm and 37.5 cm decking widths provide maximum flexibility. Rosett nodes at spacings of 50 cm are especially rigid and allow connecting possibilities in all directions. Thanks to these characteristics, the modular scaffold has been able to fulfil the stringent technical requirements for construction of “The Bow”. This flexibility and high load-bearing capacity with only a small number of diagonals make the PERI UP solution quick and cost-effective.

For work on the steel construction, the diagonally-positioned profiles must be accessible from all sides. The required cantilevers are realised with brackets and node bracing. The brackets have a high load-bearing capacity and can be mounted at any height – regardless of the decking or ledger levels already installed.

Through the use of corner plates for the inside corners, the working areas can be adapted with minimum gap to the inclined steel components. In addition, adapting to the complex steel sculpture is also achieved by changing the direction of the decking: the span direction of the decks can be changed within a scaffold bay at any point – several times if required. Thanks to these possibilities, the form of the scaffold can be optimally adapted to match the steel structure of the building.

The PERI UP industrial decking with system widths of 25 cm allow working platforms and access means to be completely covered without any gaps. The surface of the decking is perforated and extremely slip-resistant. Due to this, the decks are ideally suited for use in those working areas where safety against slipping has a high priority. Another big advantage is the quick and safe installation: the integrated lock against lifting secures the decking without the need of any additional measures, and immediately after mounting has taken place.

For accessing the individual working areas, PERI UP steel staircases are used. The staircase fulfils the highest requirements regarding loads and accessibility: with a permissible load of 3.0 kN/m² and a width of 100 cm, the stairs are generously dimensioned and stable to allow site personnel to move in opposite directions at the same time. Installation is simple and fast. The stair stringers are mounted first and subsequently covered with the lightweight individual steps that interlock during assembly. The top step secures all the others.

PERI logic simplifies and accelerates assembly of the PERI UP scaffolding – even at great heights. The low weight of the individual system components, and the fact that each system part can be handled by only one person, facilitates fast and effortless operations. The high rigidity of the PERI UP ledger connections reduces the number of levels that need to be braced as well as reducing the amount of required diagonals. All PERI UP system components are compatible with each other which means working platforms, stairs and guardrails are easy to install. The “gravity lock” self-locking ledger connection provides a very high level of working and assembly safety: when mounting the ledger, the wedge drops automatically into the opening of the rosette through its own gravitational force and securely locks into position. PERI UP has been tried and tested over many years and the modular scaffold system fully complies with system scaffolding requirements according to European Standards.

“The Bow” is the future headquarters for the EnCana Corporation, a company operating in the oil and gas industry. Not only is the distinctive appearance of the office tower extraordinary but also the building concept itself: To create a best possible working environment, the London architects Foster + Partners first discussed the ideas and needs together with the companies’ employees before planning the building.

The building provides employees with working areas with daylight and natural ventilation. The spacious architecture, open work areas as well as three “sky gardens” facilitate the cooperation of the teams Form and orientation of the building have also been ideally adapted to suit the local climatic conditions. A glass atrium extends in a south-westerly direction over the entire building height of 236 m, an intelligent energy concept for optimum utilization of solar energy and minimum energy consumption. The distinctive design with a diagonal grid of steel beams also provides an especially good structural behaviour. For the first time in North America, this combination of a diagonal support structure and, at the same time, curved shape of a building has been realised.

Via: www.home.nestor.minsk.by

Most popular ↑

Hull scaffolding firm saved after difficult trading period

A Hull-based scaffolding firm has been saved after The...

PHD Access plays key role in latest HMS Victory conservation phase

PHD Access is playing a central role in the...

Australian scaffolding body warns Kwikform collapse exposes subcontractor risks

Australia’s scaffolding trade body has said the voluntary administration...

GKR scaffolders help save woman’s life at London project

A GKR Scaffolding site team has been praised after...

ScaffCycle relaunches used scaffolding marketplace

ScaffCycle has relaunched its online marketplace for used scaffolding...

Latest news

PERI UP Crescent-shaped scaffolding

ADVERTISEMENT

In Calgary, Canada, a 236 m high office tower is currently being constructed. “The Bow” is shaped like a crescent whilst the most striking feature of the building is the diagonal arrangement of the steel support structure. A sophisticated PERI UP scaffolding concept provides secure access and spacious working platforms for all subsequent sub-contracting work following the completion of the building’s shell. PERI was awarded the contract to supply work scaffolding and stairs that are temporarily required for all subsequent work on the 59-storey building shell.

For painting, mounting of the fire protection cladding as well as the insulation and installation of the piping system, the sub contractors imposed various requirements concerning working area dimensions and potential loads. Installation of platforms at distances of 2.50 m over the entire height of the building was requested. One of the most important requirements to be fulfilled for all sub-contractors was to ensure that the working platforms were as close as possible to the complex steel structure whose main beams ascended at an angle of 76°. In addition, the front of the building is curved like a crescent.

Together with the Ledcor team, PERI developed a solution based on the PERI UP Rosett Flex scaffolding. In the process, the modular scaffold system has once again proven its high degree of flexibility and has shown itself to be extremely adaptable to suit the curved building layout and special form of the supporting structure – all requirements of both the client and sub-contractors have been fulfilled.

The modular PERI UP Rosett Flex scaffolding has a very wide range of applications. The metric grid dimensions along with the 25 cm and 37.5 cm decking widths provide maximum flexibility. Rosett nodes at spacings of 50 cm are especially rigid and allow connecting possibilities in all directions. Thanks to these characteristics, the modular scaffold has been able to fulfil the stringent technical requirements for construction of “The Bow”. This flexibility and high load-bearing capacity with only a small number of diagonals make the PERI UP solution quick and cost-effective.

For work on the steel construction, the diagonally-positioned profiles must be accessible from all sides. The required cantilevers are realised with brackets and node bracing. The brackets have a high load-bearing capacity and can be mounted at any height – regardless of the decking or ledger levels already installed.

Through the use of corner plates for the inside corners, the working areas can be adapted with minimum gap to the inclined steel components. In addition, adapting to the complex steel sculpture is also achieved by changing the direction of the decking: the span direction of the decks can be changed within a scaffold bay at any point – several times if required. Thanks to these possibilities, the form of the scaffold can be optimally adapted to match the steel structure of the building.

The PERI UP industrial decking with system widths of 25 cm allow working platforms and access means to be completely covered without any gaps. The surface of the decking is perforated and extremely slip-resistant. Due to this, the decks are ideally suited for use in those working areas where safety against slipping has a high priority. Another big advantage is the quick and safe installation: the integrated lock against lifting secures the decking without the need of any additional measures, and immediately after mounting has taken place.

For accessing the individual working areas, PERI UP steel staircases are used. The staircase fulfils the highest requirements regarding loads and accessibility: with a permissible load of 3.0 kN/m² and a width of 100 cm, the stairs are generously dimensioned and stable to allow site personnel to move in opposite directions at the same time. Installation is simple and fast. The stair stringers are mounted first and subsequently covered with the lightweight individual steps that interlock during assembly. The top step secures all the others.

PERI logic simplifies and accelerates assembly of the PERI UP scaffolding – even at great heights. The low weight of the individual system components, and the fact that each system part can be handled by only one person, facilitates fast and effortless operations. The high rigidity of the PERI UP ledger connections reduces the number of levels that need to be braced as well as reducing the amount of required diagonals. All PERI UP system components are compatible with each other which means working platforms, stairs and guardrails are easy to install. The “gravity lock” self-locking ledger connection provides a very high level of working and assembly safety: when mounting the ledger, the wedge drops automatically into the opening of the rosette through its own gravitational force and securely locks into position. PERI UP has been tried and tested over many years and the modular scaffold system fully complies with system scaffolding requirements according to European Standards.

“The Bow” is the future headquarters for the EnCana Corporation, a company operating in the oil and gas industry. Not only is the distinctive appearance of the office tower extraordinary but also the building concept itself: To create a best possible working environment, the London architects Foster + Partners first discussed the ideas and needs together with the companies’ employees before planning the building.

The building provides employees with working areas with daylight and natural ventilation. The spacious architecture, open work areas as well as three “sky gardens” facilitate the cooperation of the teams Form and orientation of the building have also been ideally adapted to suit the local climatic conditions. A glass atrium extends in a south-westerly direction over the entire building height of 236 m, an intelligent energy concept for optimum utilization of solar energy and minimum energy consumption. The distinctive design with a diagonal grid of steel beams also provides an especially good structural behaviour. For the first time in North America, this combination of a diagonal support structure and, at the same time, curved shape of a building has been realised.

Via: www.home.nestor.minsk.by

Popular Categories

Latest posts

Scaffolder running length of Britain for children’s cancer charity

A Portsmouth scaffolder has begun an 860-mile charity run from John O’Groats to Land’s End to raise money for families affected by neuroblastoma. Charlie Chandler,...

Global access sector marks first industry awareness day

The scaffolding and access industry is today marking the first International Scaffolding and Access Day. The new annual event, launched by the International Access and...

Trade earnings lag inflation as site activity slows

Average weekly earnings for self-employed construction trades rose by just 2.3% year on year in April, as demand for skilled labour slowed across England...

Hull scaffolding firm saved after difficult trading period

A Hull-based scaffolding firm has been saved after The Yorkshire Maintenance Co stepped in to secure the future of the business and its 22...

PHD Access plays key role in latest HMS Victory conservation phase

PHD Access is playing a central role in the latest phase of the HMS Victory conservation programme at Portsmouth Historic Dockyard, delivering the specialist...

ScaffCycle relaunches used scaffolding marketplace

ScaffCycle has relaunched its online marketplace for used scaffolding after rebuilding the platform to make it easier for contractors, scaffolders and suppliers to buy,...

ScaffChamp 2026 confirms global live stream details

ScaffChamp powered by Layher 2026 will once again be broadcast live to the global scaffolding community. The official live stream will begin on 6 June...

Australian scaffolding body warns Kwikform collapse exposes subcontractor risks

Australia’s scaffolding trade body has said the voluntary administration of the Kwikform group highlights wider concerns over subcontractor exposure and payment risk across the...

HAKI CEO Sverker Lindberg to step down by 2027

HAKI Safety has confirmed that its President and CEO, Sverker Lindberg, will leave his position no later than April 2027. The company said Lindberg has...

Staht signs US distribution deal for digital pull testing range

UK digital pull testing manufacturer Staht has appointed Diversified Fall Protection as its exclusive distributor in the United States. The agreement will see Diversified market,...

Spring Issue #29 | Past issues >>

Latest topics

Most popular ⚡︎

Hull scaffolding firm saved after difficult trading period

A Hull-based scaffolding firm has been saved after The...

PHD Access plays key role in latest HMS Victory conservation phase

PHD Access is playing a central role in the...

Australian scaffolding body warns Kwikform collapse exposes subcontractor risks

Australia’s scaffolding trade body has said the voluntary administration...

GKR scaffolders help save woman’s life at London project

A GKR Scaffolding site team has been praised after...

ScaffCycle relaunches used scaffolding marketplace

ScaffCycle has relaunched its online marketplace for used scaffolding...

Related articles

ADVERTISEMENTS
More from
Latest articles

CSCS Smart Check upgrade to improve workforce skills data

CSCS has upgraded its Smart Check platform to collect more detailed data from construction...

Scaffolder running length of Britain for children’s cancer charity

A Portsmouth scaffolder has begun an 860-mile charity run from John O’Groats to Land’s...

Global access sector marks first industry awareness day

The scaffolding and access industry is today marking the first International Scaffolding and Access...

Trade earnings lag inflation as site activity slows

Average weekly earnings for self-employed construction trades rose by just 2.3% year on year...

Hull scaffolding firm saved after difficult trading period

A Hull-based scaffolding firm has been saved after The Yorkshire Maintenance Co stepped in...

PHD Access plays key role in latest HMS Victory conservation phase

PHD Access is playing a central role in the latest phase of the HMS...