A scaffolder sustained life-changing injuries after falling through a 5-meter high skylight fracturing his pelvis, elbow, wrist, and arm.

Poole Magistrates court heard how scaffolder Paul Norris (49) was completing work for the company Solar Scaffolding Services Limited who were contracted to erect an access tower and guard rails around the roof of some industrial units on 10th April 2017.

While assisting colleagues with the guard rails, Norris gained access via the roof then fell through a skylight 5 meters to the ground.

He was hospitalised for three weeks and had to undergo many surgeries and ongoing physiotherapy as a direct result of the accident.

When investigated by the HSE Solar Scaffold Services were found to have failed to take appropriate measures to prevent a fall through the fragile roof and that as an employer their duty to ensure that the work at height was adequately planned, supervised and carried out safely had failed.

A guilty plea was heard in court form the company after they were found to have breached the Work at Height Regulations 2005. Solar Scaffolding Services Limited was fined £10,000 and ordered to pay £3,666.80 in costs.

The courts also heard how Norris is now registered disabled and his wife has had to give up work to provide care for her husband. He has also had to move out of his home and move into an adapted flat and can no longer return to work.

HSE Inspector Caroline Penwill commented on the hearing, “Falls from height remain one of the most common causes of work-related fatalities and injuries in this country and the risks of working with heights are well known.

Mr. Norris’s injuries were life changing for both him and his family. He could have easily been killed. This serious incident could have been avoided if the work had been properly planned to reduce the risk”.

ADVERTISEMENT

Popular Categories

Latest posts

Scottish offshore workers urged to consider scaffolding careers

The Construction Industry Training Board is targeting workers from Scotland’s offshore energy sector as part of efforts to widen the construction talent pool and...

NASC warns members over online conduct in new media policy

The National Access and Scaffolding Confederation said the new Social Media and General Media Policy sets expectations for how its members, CISRS centres and...

Two workers killed in Spain after mast climbing platform collapse

Two workers have been killed following the collapse of a twin mast climbing work platform in Benidorm, Spain. The incident happened on Wednesday, 22 April,...

Brogan wins Manchester student accommodation access package

Brogan Group has secured the powered access package for a student accommodation building in Manchester. The access specialist will provide several passenger and goods hoists...

‘Not every scaffolder is ok’: Alan Osborn backs mental health campaign at ScaffChamp

Alan Osborn is set to shave his head at ScaffChamp 2026 as part of a campaign to raise £5,000 for men’s mental health and...

Baton opens early adopter programme for scaffolding contractors

Baton has opened applications for its Early Adopter Programme, giving scaffolding contractors early access to a software platform designed specifically for construction subcontractors. The company...

SCA joins Coriant in move to widen access and industrial services capability

Coriant has announced the acquisition of specialist contractor SCA, in a move that further expands the group’s capabilities in access, temporary containment and industrial...

Robot named Douglas begins work on Tilbury Douglas site

Tilbury Douglas has begun using a humanoid robot to carry out administrative and data-collection tasks on a live construction site. The contractor says the...

HAKI reports sharp UK sales drop as construction starts stall

The Swedish-listed scaffolding and access safety group said UK revenues fell to SEK 52 million (£4.2 million) in the three months to 31 March,...

CISRS appoints Kathryn Bowe after delay to quality committee reforms

CISRS has appointed Kathryn Bowe as full-time Chair of its Quality Assurance Committee, months after the organisation was forced to restart recruitment for the...

Latest news

Spring Issue #29 | Past issues >>

Latest topics

Most popular ⚡︎

Two workers killed in Spain after mast climbing platform collapse

Two workers have been killed following the collapse of...

Robot named Douglas begins work on Tilbury Douglas site

Tilbury Douglas has begun using a humanoid robot to...

Scottish offshore workers urged to consider scaffolding careers

The Construction Industry Training Board is targeting workers from...

Baton opens early adopter programme for scaffolding contractors

Baton has opened applications for its Early Adopter Programme,...

SCA joins Coriant in move to widen access and industrial services capability

Coriant has announced the acquisition of specialist contractor SCA,...

Related articles

ADVERTISEMENTS