Fatal New Malden fall followed missed scaffold inspections

A south west London construction company has been fined £50,000 after labourer Antonio Rodrigues died following a fall through an unglazed opening from an external scaffold platform.

ADVERTISEMENT

Lima Construction Limited has been fined £50,000 after a worker fell to his death through an unprotected window opening from an external scaffold platform at a redevelopment site in New Malden.

Antonio Rodrigues, 55, was working as a labourer for Lima Construction, the principal contractor on the conversion of a former department store on New Malden High Street into commercial and residential units.

On 27 July 2022, Mr Rodrigues fell through an unglazed opening intended for a Juliet door. He landed on a concrete ground floor more than 3m below.

He was taken to hospital but died from his injuries on 1 August 2022.

The Health and Safety Executive found that four window openings had been created for glazed Juliet doors. Some of the doors arrived with damaged glazing panels and were not installed.

Lima Construction had identified the openings as a fall risk for workers using the scaffold platform. Yet protective boarding was only fitted in the hours after Mr Rodrigues’ fall.

HSE said the risk could have been controlled as soon as the openings were created, either by boarding them over or installing additional internal scaffold guard rails.

The investigation also found that legally required weekly scaffold inspections had not been carried out after 5 July 2022. That removed an opportunity for a competent scaffold inspector to identify the danger created by the unglazed openings.

Lima Construction Limited, of Apsley Road, New Malden, pleaded guilty to breaching Regulation 13(1) of the Construction (Design and Management) Regulations 2015.

The company was fined £50,000 and ordered to pay £11,347 in costs at Westminster Magistrates’ Court on 18 June 2026.

HSE inspector Andrew Verrall-Withers said the company had generally tried to maintain good health and safety standards but had failed to respond effectively when the damaged doors created an unusual site condition.

He said: “As there was no CCTV and nobody witnessed the incident, we will never know exactly what caused Mr Rodrigues to fall.

“But if the boards added shortly afterwards had been in place, then there would have been no opening for him to fall through in the first place.”

The case is a reminder for scaffold contractors, principal contractors and inspectors that changes to building openings can create immediate fall hazards. Where glazing, doors or other permanent protection is delayed, the opening needs to be secured before workers are exposed to it.

Most popular ↑

£4.5m scaffolding framework opens for contractors in North East and Yorkshire

Beyond Housing has opened bidding for a £4.5m scaffolding framework covering planned and reactive works across Redcar and Cleveland and parts of North Yorkshire.

Australia steps up push for scaffolding to gain skilled-trade status

Scaffolding Association Australia has taken its campaign for formal trade recognition and a structured apprenticeship pathway to federal decision-makers in Canberra.

£260k Newcastle Cathedral scaffolding contract opens for bids

Newcastle City Council has opened a £260,000 scaffolding tender to provide specialist access for conservation repairs to Newcastle Cathedral’s historic 15th-century Lantern Tower.

London developer fined after required roof scaffold was never provided

A London developer and its director have been fined after unsafe roof work continued despite a subcontractor’s risk assessment identifying scaffolding as a required control.

NASC calls for HSE funding boost and national scaffolding training network

The NASC has called for increased HSE funding, a nationwide network of scaffolding training providers and stronger protections for contractors as it launches its updated 2026 manifesto.

Latest news

£260k Newcastle Cathedral scaffolding contract opens for bids

Newcastle City Council has opened a £260,000 scaffolding tender to provide specialist access for conservation repairs to Newcastle Cathedral’s historic 15th-century Lantern Tower.
- Advertisement -
More from

NASC calls for HSE funding boost and national scaffolding training network

The NASC has called for increased HSE funding, a nationwide network of scaffolding training providers and stronger protections for contractors as it launches its updated 2026 manifesto.

London developer fined after required roof scaffold was never provided

A London developer and its director have been fined after unsafe roof work continued despite a subcontractor’s risk assessment identifying scaffolding as a required control.

Bamboo scaffolder recounts dismantling fire-damaged Wang Fuk Court

Hong Kong scaffolder Yip Hon-ying has described how a 30-strong team spent 3 months removing fire-damaged bamboo scaffold from 7 blocks at Wang Fuk Court.

Former Devonport scaffolder dies after asbestos exposure

A former Plymouth scaffolder who worked on Royal Navy ships at Devonport dockyard died from an asbestos-related cancer, an...