Costs climb again on Manchester Town Hall project as delays worsen

ADVERTISEMENT

The cost of restoring Manchester Town Hall has risen by a further £95m, with completion now pushed back to spring 2027. The Grade I-listed project was originally due to finish in summer 2024.

Manchester City Council confirmed that the overall budget has increased to £524.8m. This is 59 per cent higher than the initial £330m allocation set when work began.

The council said the scheme had been affected by a “unique combination” of pressures. These include a shortage of specialist heritage labour, continued materials and labour cost inflation, and a series of subcontractor collapses.

Three unnamed subcontractors working on key packages have entered administration in the past six months. The council said the complexity of the 148-year-old building meant delays to one element of work often caused wider disruption across the programme.

Lendlease was appointed as main contractor in 2019. The job is now being delivered under the revived Bovis name after Lendlease’s UK construction arm was sold to Atlas Holdings.

Deputy council leader Garry Bridges said the project had “navigated a stream of challenges”. He acknowledged frustration over rising costs but argued that failing to intervene would have risked the building becoming “unusable and obsolete”.

The council reported last year that costs had already grown by nearly £100m due to hyperinflation, subcontractor claims and unexpected conservation work, including the presence of nesting falcons.

The latest funding increase will need approval from the council’s executive committee on 10 December. The additional money will be met through borrowing.

Bridges said the project was now on a “confident path” to completion in 2027 and would be ready for the 150th anniversary of the town hall’s original opening. He added that the restored building would serve the city “for the next 100 years”.

Most popular ↑

Fatal New Malden fall followed missed scaffold inspections

Lima Construction Limited has been fined £50,000 after a...

NASC AGM confirms new president and 10-region structure

Sarah Klieve has taken over as NASC president as...

AT-PAC expands European marketing support with Petite Agency

AT-PAC has expanded its marketing partnership with Petite Agency...

HSE warns employers to protect workers as extreme heat alert begins

Scaffolding contractors across much of England are being urged...

Freight surge raises warning over scaffold material costs

A sharp rise in global container shipping rates is...

Latest news

ADVERTISEMENT
More from
Latest articles

360 Degrees Consultancy: From Start-Up to Top 5 UK Scaffolding Consultancy

When Karl launched 360 Degrees Consultancy in 2020, he was drawing on more than...

The apprentice team that took on ScaffChamp

Ross Brown and Robbie Andrews didn’t take an all-apprentice team to ScaffChamp to chase...

NASC AGM confirms new president and 10-region structure

Sarah Klieve has taken over as NASC president as the trade body introduces a...

Fatal New Malden fall followed missed scaffold inspections

Lima Construction Limited has been fined £50,000 after a worker fell to his death...

Freight surge raises warning over scaffold material costs

A sharp rise in global container shipping rates is beginning to feed through to...

Des Moore: “The next five years are critical” for scaffolding

As Des Moore approaches his 70th birthday, he is not interested in nostalgia. After...

AT-PAC expands European marketing support with Petite Agency

AT-PAC has expanded its marketing partnership with Petite Agency to cover parts of its...

HSE warns employers to protect workers as extreme heat alert begins

Scaffolding contractors across much of England are being urged to act on heat risk...