Tyne Bridge Restoration Enters Next Phase with Scaffolding Across River

ADVERTISEMENT

Work on the iconic Tyne Bridge has taken a significant step forward as scaffolding is set to span the River Tyne in the next phase of its comprehensive restoration project.

The ambitious operation follows the successful installation of scaffolding adjacent to the Newcastle tower. Now, Esh Construction, in collaboration with specialist contractor Infrastructure Site Solutions (ISS), is moving ahead with an underdeck scaffold structure that will stretch from the Newcastle tower to its counterpart on the Gateshead side, 84 feet above the river.

This latest phase will see operatives working underneath the bridge, securely fastened with safety harnesses and supported by a safety boat stationed below for emergency rescues.

The 100-metre-long by 11-metre-wide scaffold will allow for detailed inspections beneath the bridge, paving the way for subsequent cleaning, grit blasting, and repainting. To ensure safety and minimise environmental impact, the structure will be enclosed in protective sheeting throughout the work.

Gareth Dawson, Project Manager for Esh Construction, highlighted the progress made:

“A programme resequencing exercise has allowed the underdeck scaffolding to be actioned earlier than originally planned. The change in programme will provide efficiencies throughout the project given the scale of the repair and restoration work to be delivered – this scheme is far more than ‘just a lick of paint.’”

The restoration, commissioned by Newcastle and Gateshead councils, is a monumental undertaking. Over four years, it will use more than 180 miles of scaffolding tubes—enough to stretch from Newcastle to Dundee—and over 13,000 tonnes of scaffolding components, equivalent to the weight of six London Eyes.

The work is divided into 20 phases due to the bridge’s weight restrictions.

Cllr Dr Juna Staithan, Newcastle City Council’s cabinet member for Climate Change and Transport, expressed her enthusiasm for the project:

“I am really delighted with the progress on site as we restore this icon to its former glory. Everyone involved is hugely proud and passionate to be part of this major project to preserve this much-loved icon for future generations.”

Major Repairs and a Historic Paint Job

Beyond the scaffolding, restoration work is advancing inside the bridge’s deck void, where three of the 36 steel hangers supporting the carriageway are set to undergo strengthening.

Repairs also include steel, concrete, stonework, and masonry restoration, along with drainage improvements, deck waterproofing, and parapet protection.

One of the restoration’s crowning achievements will be the bridge’s new coat of paint in the historic ‘Hollybush’ shade, chosen for its resemblance to the original colour. The new paint system is designed for durability and will protect the bridge for up to 30 years against the harsh conditions of the Tyne Valley gorge.

The restoration hit a major milestone in October when scaffolding around the Gateshead tower was dismantled, revealing the first section of blasted, repaired, and repainted steel.

With over 1,000 repairs planned, the Tyne Bridge restoration is as much about preserving history as it is about modernising infrastructure. As one of the North East’s most recognisable landmarks, the bridge will continue to be a symbol of regional pride for generations to come.

ADVERTISEMENT

Popular Categories

Latest posts

Scaffolding sector joins April Fools’ Day with wave of industry jokes

Scaffolding companies and industry figures have taken to social media to mark April Fools’ Day, with a wide range of posts blending humour with...

Founders step away as City Access Scaffolding completes buyout

From Left to Right: Ryan Scott, Mark Skinner, and Ross Archibald

JMAC completes first acquisition with Tees Site Support deal

JMAC Industrial and Access Group Ltd has acquired a majority shareholding in Tees Site Support Ltd, marking the company’s first acquisition as it looks...

Final 20 teams confirmed for ScaffChamp 2026

The final 20 teams competing at ScaffChamp powered by Layher 2026 have been confirmed, with the last place secured after a qualification event in...

£27bn road strategy opens major pipeline for specialist contractors

The government has confirmed Roads Investment Strategy 3 (RIS3), a £27 billion programme covering England's motorway and A-road network through to 2031. A record £8.4...

NASC expands regional leadership as membership rises 40%

The National Access and Scaffolding Confederation (NASC) has announced a series of new regional chair and vice chair appointments as part of a wider...

Layher UK launches ‘Sizzle & Learn’ open morning series for 2026

Layher UK has announced a series of open morning events aimed at giving customers and partners direct access to its latest systems, product developments...

Two taken to hospital after building collapse in Oldham

Two people have been taken to hospital after a building partially collapsed in Oldham town centre. Emergency services were called to King Street at about...

Scafom-rux delivers Manchester’s tallest ground-based scaffold

In the heart of Manchester’s financial district, a major high-rise development is setting new benchmarks for construction scaffolding in the UK. For this complex...

Teen scaffolding labourer dies after fall through shaft on London site

A construction company has been fined after a teenage scaffolding labourer died in a fall from height on a London building site. Renols Lleshi, 19,...

Latest news

Magazine

Spring Issue #29 | Past issues >>

Trending now ⚡︎

Fraud gang jailed for helping candidates cheat CITB safety tests

Three men have been sentenced for their role in...

Scaffolding sector joins April Fools’ Day with wave of industry jokes

Scaffolding companies and industry figures have taken to social...

Founders step away as City Access Scaffolding completes buyout

From Left to Right: Ryan Scott, Mark Skinner, and Ross Archibald

JMAC completes first acquisition with Tees Site Support deal

JMAC Industrial and Access Group Ltd has acquired a...

£27bn road strategy opens major pipeline for specialist contractors

The government has confirmed Roads Investment Strategy 3 (RIS3),...

Related articles

Latest topics

Fraud gang jailed for helping candidates cheat CITB safety tests

Three men have been sentenced for their role in...

Scaffolding sector joins April Fools’ Day with wave of industry jokes

Scaffolding companies and industry figures have taken to social...

Founders step away as City Access Scaffolding completes buyout

From Left to Right: Ryan Scott, Mark Skinner, and Ross Archibald

JMAC completes first acquisition with Tees Site Support deal

JMAC Industrial and Access Group Ltd has acquired a...
ADVERTISEMENTS